Project Management
8 hours ago 30
Instructions.docx_safe.pdf
Instructions.docx_safe.pdf
1
PRACTICAL EXAMPLE DIRECTIONS Many times, our clients will ask us to do an analysis of what we can build with what we have on hand. This is something that is needed right away, so timelines are always tight, and information is hard to find. The knowledge of how to do this cannot be taught but must be figured out on each job. Every one of our clients has different methods and references for the engineering.
In this scenario, you are given the drawings for the conductor assemblies and the tower data sheets. These are common drawings on our projects. Additionally, you have been given an on hand count of the inventory on your yard.
You are to answer the question of which assemblies on which towers can we build with the inventory on hand; the order of construction at this point is from Tower 213 – Tower 135.
The expectation is that you put together a product that you will email out to the client and the project management staff answering this question. It is also expected that you can explain how you got your answers if needed.
ON HAND INVENTORY
QTY Description 176 polymer insulator 50 kip 345 socket-clevis 50 kip 234 yoke plate, 60 kip 500 clevis-eye Y 90degree 30 kip 550 anchor shackle 50 kip 334 clamp, armor grip susp, 30 kip 1590 kcmil acsr 45/7 26 anchor shackle 80 kip 37 chain link 85 kip 17 yoke plate 80 kip 7 anchor shackle 60 kip
24 compr dead end with eye 1590 kcmil 31 compr jumper terminal 1590 kcmil 12 extension strap, adjustable 75 kip
456 socket-clevis 45kip 23 yoke assy w/300lbs wt 1590 kcmil
Instructions.docx_safe.pdf
1
PRACTICAL EXAMPLE DIRECTIONS Many times, our clients will ask us to do an analysis of what we can build with what we have on hand. This is something that is needed right away, so timelines are always tight, and information is hard to find. The knowledge of how to do this cannot be taught but must be figured out on each job. Every one of our clients has different methods and references for the engineering.
In this scenario, you are given the drawings for the conductor assemblies and the tower data sheets. These are common drawings on our projects. Additionally, you have been given an on hand count of the inventory on your yard.
You are to answer the question of which assemblies on which towers can we build with the inventory on hand; the order of construction at this point is from Tower 213 – Tower 135.
The expectation is that you put together a product that you will email out to the client and the project management staff answering this question. It is also expected that you can explain how you got your answers if needed.
ON HAND INVENTORY
QTY Description 176 polymer insulator 50 kip 345 socket-clevis 50 kip 234 yoke plate, 60 kip 500 clevis-eye Y 90degree 30 kip 550 anchor shackle 50 kip 334 clamp, armor grip susp, 30 kip 1590 kcmil acsr 45/7 26 anchor shackle 80 kip 37 chain link 85 kip 17 yoke plate 80 kip 7 anchor shackle 60 kip
24 compr dead end with eye 1590 kcmil 31 compr jumper terminal 1590 kcmil 12 extension strap, adjustable 75 kip
456 socket-clevis 45kip 23 yoke assy w/300lbs wt 1590 kcmil
- Health Care case study
- LDR 300 Week 3 Leadership Diversity [15 Slides + SpeakerNotes]
- Segmentation and Target Market Paper - MKT 571 - Week 3
- art appreciation
- Strategic Fit With the Industry Environment Assessment
- economic development reading paper find answer
- New class
- BUS 317 Week 3 Discussion 2 ( Media Pros and Cons ) - Tutorial Contains Two Answers For This Discussion - A Graded - Best Tutorial - Quality Work - Latest Syllabus
- Games strategies and decision 1 question quick!!
- Healthcare Quality Assurance Article Reviews