WEDDING PLAN SCHEDULE TRUE
HIGHLIGHT ASSIGNMENTS DUE WITHIN 2 MONTHS
Activity Responsible Estimated Duration Earliest Start Eariest Finish Latest Start Latest Finish Progress Percent
1 Locate wedding venue Alania 2 Weeks 2/6/17 2/20/17 2/13/17 3/27/17 0% 0%
3 Order flowers (wedding) Monti 2 Weeks 2/6/17 2/20/17 2/13/17 3/27/17 0% 0%
4 Order flowers (reception) Monti 2 Weeks 2/6/17 2/20/17 2/13/17 3/27/17 0% 0%
5 Order wedding cake Monti 3 Weeks 2/6/17 2/27/17 2/13/17 3/27/17 0% 0%
6 Order food & beverages for reception Karen 4 Weeks 2/6/17 3/6/17 2/13/17 3/27/17 0% 0%
7 Equipment rental for wedding Karen 5 Weeks 2/6/17 3/13/17 2/13/17 3/27/17 0% 0%
8 Equipment rental for reception Karen 5 Weeks 2/6/17 3/13817 2/13/17 3/27/17 0% 0%
9 Photagrapher for wedding Alania 4 Weeks 2/6/17 3/6/17 2/13/17 3/27/17 0% 0%
10 Photographer for reception Alania 4 Weeks 2/6/17 3/6/17 2/13/17 3/27/17 0% 0%

ASSIGNMENT MATRIX u

/xl/drawings/drawing1.xml#'Assignments%20Detail'!A1

Assignment Matrix

ASSIGNMENT MATRIX
WBS Item Work Item Alania Monti Karen Bride Groom
1 Wedding Venue
1.1 Locate venue P S S S
1.2 Book venue P S
2 Flowers
2.1 Order wedding flowers P S
2.2 Order reception flowers P S
3 Wedding Cake
3.1 Locate bakery P S
3.2 Order cake P S
4 Catering
4.1 Locate Caterer S P S S
4.2 Order food for reception S P
4.3 Order beverages for reception S P
5 Equipment Rental
5.1 Equipment for wedding S P
5.2 Equipment for reception S P
6 Photographer
6.1 Photographer for wedding P S
6.2 Photographer for reception P S