project and change management

profilejymthi.co.pettt
using_ms_project.pptx

Using MS Project

Presentation to Accompany the MS Project Assignment During Week Three of IST7060

To Start

Open MS Project

Select a Blank Presentation

Open It

Have your Work Breakdown Structure (WBS) open as well

This is how the blank project will appear

Copy your detail from column A of your WBS ( copy of rows with data, not the entire column)

Now Paste your WBS into the Task Column

When that is done it will look similar to the example below

Find the Indent icon at the top (shown here)

Indent all but the name of your project (line 1)

It will now look like the example below

Now, indent the tasks below each deliverable until your project looks like this

Right hand mouse-click over the column labeled “Duration”, point to Insert Column, and add a column called “Work”

For each task, insert the number of hours of work and the number of days of duration required to complete it.

Remember…

Work indicates the time needed to actually do the task

Duration refers to the amount of time allocated for the work to be done

For eample, you may have a task that takes 16 hours, but, realizing that your team member has other work to do as well, you may allot 4 days duration to complete it

Caution!!!

Do not complete the columns labeled “Start” and “Finish”

Doing so sets up hard constraints within the software

Instead you will shown how to select a start date or finish date when the project file is complete

Also

Do not put hours and days in the deliverable or project name rows

These rows contain formulae that will sum up the work and duration for each task within a deliverable and for each deliverable for the entire project55

When done, your project will look like this

Notice

There are no dates for the tasks

That is because w have not sequenced them yet

That is the next task for you

Sequencing Tasks

We sequence tasks by determining, for each task, the task number that comes just before it

That task is called a predecessor

Task numbers are the line numbers in the software

In my example, task 3 is “Review outcomes from year one training”

In the Predecessor column, for tasks and tasks only, indicate any task that must come before it. You can have multiple tasks numbers separated by commas.

Some tasks happen first – they have no predecessor

Look at the example on the next slide

Here is the example of the project with predecessors indicatedc

Notice

The lines appearing in blue to the right

Look at the next slide and you will see a schedule sequence for the project

And Now for Resources and a Budget

In the upper left hand corner of the software is a tab indicated as the Gantt Chart

This pull down allows you to select views for the project

One of these is called the “Resource Sheet”

Select it

It will look like the next slide

This is where you will enter all of the resources for your project

For our purposes there are two kinds:

People (listed here as Work)

And

Things (listed here as Materials)

Go to the next slide to learn how to enter data here

Entering Resources

Enter data for People as follows:

Column Name What to enter
Resource Name The name or type of resource (John, or Web Develop, for example
Type Select Work
Max. Indicates a full time employee; leave at that for class purposes
Std. Rate Cost per hour for the person indicated
Ovt. Cost per hour of overtime for the person indicated
Accrue Leave as prorated
Base Indicated calendar; use Standard

Entering Resources

Enter data for Materials as follows:

Column Name What to enter
Resource Name The type of resources (computer, software, etc.)
Type Select Material
Max. Indicates a full time employee; leave at that for class purposes
Std. Rate Leave blank
Cost/Use Indicate the cost per unit – for one time purschases, these will be selected just once in the project; for multiple uses (as with consumables

Resource Sheet Example

Now we can add these resources to each task

This process will give us a budget

Go back to the Gantt Chart View (click on the Gantt Chart Icon in the upper left hand corner)

Assigning Resources to Tasks

Assign resources to tasks

Never to deliverables or to the project name

To do this, go to the column named “Resource Names”

Go down until you hit the first task

A pull down tab will appear when you click on the cell for that task

Pull it down and all of the resources you palaced on the resource sheet will appear

Select all that are appropriate for that task by clicking on the box next to it

Each task must have at least one person assigned

Go down until you hit the first task

A pull down tab will appear when you click on the cell for that task

Pull it down and all of the resources you placed on the resource sheet will appear

Select all that are appropriate for that task by clicking on the box next to it

Each task must have at least one person assigned

This is what the resource names column look like when complete

And now to select a start (or finish) date

Some projects must start on a certain date – they finish when the project is done

Other projects must finish on a certain date – they must start early enough to be done by that date

This is easy to do in MS Project

First go to the “Project” ribbon at the top of the software and select “Project Information”

Go to the next slide

This dialogue box appears

Under the tab named Schedule from:

Select either start or finish

One and only one of the two boxes above will highlight

Select the date

Click “OK”

And you are done!!

You now have a project plan with

A schedule

A budget

Resources

You can also see reports, have various additional views, etc.