Solve the following problems from your text in an MS Word document with questions using APA style. Your answers should provide thoughtful, supporting details, and examples and graphics as necessary.
Chapter 16
Use the information provided in the Table 1 and the network diagram in Figure 1 for the following problems.
|
Activity |
Normal Time(weeks) |
Normal Cost ($) |
Crash Time (weeks) |
Crash Cost ($) |
Maximum weeks Reduced |
Crash Cost per Week ($) |
|
A |
4 |
550 |
3 |
950 |
2 |
450 |
|
B |
5 |
650 |
4 |
750 |
2 |
150 |
|
C |
7 |
850 |
4 |
1350 |
4 |
550 |
|
D |
7 |
1550 |
5 |
2200 |
3 |
100 |
|
E |
7 |
1800 |
5 |
2300 |
3 |
550 |
|
F |
6 |
250 |
6 |
1250 |
1 |
1050 |
|
G |
8 |
1550 |
6 |
1850 |
3 |
350 |
Table 1
Figure 1. AON network diagram
1. Using the information given,
· Calculate the completion time of the project.
· Identify the activities on the critical path.
2. Using the information given and the project completion time calculated in Problem 1, reduce the completion time of the project 3 weeks in the most economical way.
3. Using the information given and the project completion time calculated in Problem 1, calculate the minimum time for completing the project possible.
image1.png
- Nr 361 week 4 Assignment_Telenursing the future is now
- MKT571 NEW PRODUCT LAUNCH MARKETING PLAN, PART III (A+++++++++)
- In pediatric patients aged 2months to 5 years who receive the MMR vaccination, is there an increased risk of autism against those who do not receive the vaccination?
- Help with discusion
- Music paper
- Statistical Analysis and p Values
- Strategic Plan Part 1
- Can you help?
- Computer Science - Word and Excel - assignment
- Investment Recommendation