Busi 680 quiz 8 pt 1
Question 1
2 out of 2 points
In terms of project classification, ________ constrained means that project duration is fixed
and resources are flexible.
Selected
Answer:
tim
e
Response
Feedback:
correct
MC Qu. 58 (Static) In terms of project...
AACSB: Reflective Thinking
Accessibility: Keyboard Navigation
Accessibility: Screen Reader Compatible
Blooms: Remember
Difficulty: 1 Easy
Learning Objective: 08-02 Identify different types of resource
constraints.
Topic: Types of Resource Constraints
Type: Static
Question 2
2 out of 2 points
When scheduling activities in a resource-constrained project, typically the activity
scheduled first has the __________ amount of slack.
Selected
Answer:
lea
st
Response
Feedback:
correct
MC Qu. 54 (Static) When scheduling activities in a...
AACSB: Reflective Thinking
Accessibility: Keyboard Navigation
Accessibility: Screen Reader Compatible
Blooms: Remember
Difficulty: 1 Easy
Learning Objective: 08-04 Describe how the leveling approach is
used for resource-constrained projects.
Topic: Resource Allocation Methods
Type: Static
Question 3
2 out of 2 points
A project engineer has been scheduled to run the product system test at the same time
as building a marketing prototype. This is an example of what type of resource
constraint?
Selected
Answer:
Peopl
e
Response
Feedback:
correct
MC Qu. 06 (Static) A project engineer has been scheduled...
AACSB: Knowledge Application
Accessibility: Keyboard Navigation
Accessibility: Screen Reader Compatible
Blooms: Apply
Difficulty: 3 Hard
Learning Objective: 08-02 Identify different types of resource
constraints.
Topic: Types of Resource Constraints
Type: Static
Question 4
2 out of 2 points
In a resource-constrained project, the first, or primary, priority in assigning resources is
usually given to activities with the
Selected
Answer:
least
slack.
Response
Feedback:
correct
MC Qu. 20 (Static) In a resource-constrained...
AACSB: Reflective Thinking
Accessibility: Keyboard Navigation
Accessibility: Screen Reader Compatible
Blooms: Understand
Difficulty: 2 Medium
Learning Objective: 08-04 Describe how the leveling approach is
used for resource-constrained projects.
Topic: Resource Allocation Methods
Type: Static
Question 5
2 out of 2 points
When there are not enough people, money, and/or equipment available for a project it is
known as being
Selected
Answer:
resource
constrained.
Response
Feedback:
correct
MC Qu. 32 (Static) When there are not enough,...
AACSB: Reflective Thinking
Accessibility: Keyboard Navigation
Accessibility: Screen Reader Compatible
Blooms: Remember
Difficulty: 1 Easy
Learning Objective: 08-04 Describe how the leveling approach is
used for resource-constrained projects.
Topic: Resource Allocation Methods
Type: Static
Question 6
2 out of 2 points
In scheduling resource-constrained projects, _________ are typically used rather than
optimum mathematical solutions.
Selected
Answer:
heuristi
cs
Response
Feedback:
correct
MC Qu. 57 (Static) In scheduling resource-constrained...
AACSB: Reflective Thinking
Accessibility: Keyboard Navigation
Accessibility: Screen Reader Compatible
Blooms: Understand
Difficulty: 2 Medium
Learning Objective: 08-04 Describe how the leveling approach is
used for resource-constrained projects.
Topic: Resource Allocation Methods
Type: Static
Question 7
2 out of 2 points
Since resource leveling or smoothing delays noncritical activities, a common result is a
decrease in network sensitivity.
Selected
Answer:
Fals
e
Response
Feedback:
As noncritical activities are delayed, slack levels are reduced which
increases the number of critical and noncritical activities. This results in
an increase in network sensitivity.
TF Qu. 91 (Static) Since resource leveling or smoothing delays...
AACSB: Reflective Thinking
Accessibility: Keyboard Navigation
Accessibility: Screen Reader Compatible
Blooms: Understand
Difficulty: 2 Medium
Learning Objective: 08-03 Describe how the smoothing approach is
used on time-constrained projects.
Topic: Resource Allocation Methods
Type: Static
Question 8
2 out of 2 points
Since resource leveling or smoothing delays noncritical activities, a common result is an
increase in network ___________.
Selected
Answer:
sensitivi
ty
Response
Feedback:
correct
MC Qu. 55 (Static) Since resource leveling or smoothing...
AACSB: Reflective Thinking
Accessibility: Keyboard Navigation
Accessibility: Screen Reader Compatible
Blooms: Understand
Difficulty: 2 Medium
Learning Objective: 08-03 Describe how the smoothing approach is
used on time-constrained projects.
Topic: Resource Allocation Methods
Type: Static
Question 9
2 out of 2 points
In reality resource allocation generally occurs in a(n) ___________ environment where the
demands of one project have to be reconciled with the needs of other projects.
Selected
Answer:
multiproje
ct
Response
Feedback:
correct
MC Qu. 64 (Static) In reality resource allocation...
AACSB: Reflective Thinking
Accessibility: Keyboard Navigation
Accessibility: Screen Reader Compatible
Blooms: Understand
Difficulty: 2 Medium
Learning Objective: 08-08 Identify common problems with
multiproject resource scheduling.
Topic: Multiproject Resource Schedules
Type: Static
Question 10
2 out of 2 points
When a company will reduce the number of projects they have to manage internally to
only core projects and send noncritical projects to contractors and consulting firms this is
called
Selected
Answer:
outsourcin
g.
Response
Feedback:
correct
MC Qu. 26 (Static) When a company will reduce the...
AACSB: Reflective Thinking
Accessibility: Keyboard Navigation
Accessibility: Screen Reader Compatible
Blooms: Understand
Difficulty: 2 Medium
Learning Objective: 08-08 Identify common problems with
multiproject resource scheduling.
Topic: Multiproject Resource Schedules
Type: Static