Project Management Red Zuma Project
Herbert Greene
Week 5 Assignment Memo
Dr. Proffit
December 15, 2020
Red zuma memo 2
Date: 15-Dec-20
To: Company management
From: Project engineer
Subject: overallocation of resources
Management
We are writing for you approval for Zuma project. The introduction of start-to-start lad into schedule might result into an overall reduction on the project duration. However, this might cause an increase the current budget since additional requirements will be necessary. There might be need for additional engineers.
For additional requirement, development and design engineer are required. They are the necessary for fast development and improvement of the scooter. A lot of engineers mean work will be divided into many simpler tasks that will be performed by the many engineers available.
Well, the critical will reduce significantly where the total number of days will reduce from 76 days to almost 65 days. This is a significant improvement.
Check the changes in the Ghant chart below.