2 pages executive summmary

profileFearofGod
MyPowerPoint.pptx

Location of project

Project overview

Provide a preliminary design analysis for two alternatives

Provide recommendations on the best way to get the pipe across the channel

Provide engineering plans for our selected alternative

Provide a detailed construction schedule and cost estimate for the selected alternative

Transportation recommendations

No additional trips generated during construction of the project

No future, long-term or short-term implications

Pedestrian bridge will provide a protected corridor along Washington Avenue

Geotechnical recommendations

Due to infiltration the Jack and Bore alternative requires a large amount of dewatering

Granite rock layer provides a suitable foundation for the pedestrian bridge

Structural recommendations

Prefabricated bridge

Main structure components include concrete and steel

Pipe is supported by the deck via saddles

Considered various load cases including seismic and wind load

Construction recommendations

Cost – Pedestrian bridge was significantly cheaper

Right-of-Way

Close proximity to City of Escondido public works yard

Construction Schedule

bridge would take approximately 4-5 months

Conclusions

Donovan & Associates recommends constructing a pedestrian bridge with the pipe crossing along the span of the bridge based on the following:

Transportation: Safe pedestrian corridor

Geotechnical: Granite rock provided a solid support foundation

Structural: Simplicity of design and prefabricated features

Construction: Cost of the bridge is $500,000 and can be constructed in a reasonable time frame

Final design