RFP for project management

profileMalansari23
LocationoftheLand.docx

Location of the Land:

The following photo is showing a very good residential area, since the project is a family house so this is the best area that we could build the house in.

address: 3545 King Edward Way, Dayton, OH 45431

https://lh6.googleusercontent.com/QZiii6TDy2pSXP-h-8EP22ACebf1_NKx3dFP0AUjgS9lWdKay7pVTRZh5roBeVqoLPwD7cDrCibYOXhTFbZqq_YJjz2s4kFVCsMhNWe8chd9PI4yYEingTew-Lnm76r3RpF3FbvH

House Construction Plan:

The house is going to be one story house and the size is about 2734 sq-ft.

https://lh5.googleusercontent.com/LJn3Bd3dtF2wimQ1_kYyW05ul_65unUqcjVjcbBxO4J8KSFnPNDQVzGEoQS8w3hCDXOhQIfyexdCuFL9KyV9zVmb-gzKUwzGTtZxsGP8Zcu-BUj9QZSimXfzwsYSxgckrEYYbmgy

Assigns Work to Team:

This story home is located in a charming area which is characterized by the open green space and healthy environment. The house is environment-friendly since it contains large windows which make the house energy efficient. This house contains 3 charming bedrooms including master bedroom with three bathrooms including two full bathrooms and a half bathroom.in addition, there is a kitchen equipped with the modern appliances that every chief wish to use. The dining room is next to the kitchen which facilitates the dining the food and near to the media room to watch an enjoyable movie after a delicious food. in addition there is a charming pool with the European style that makes every summer refreshing. Last, there is enough space for two cars. The total space for this house is 2734 sq-ft.

Assigns Work to Team:

Number

Task

Duration

1

Start

0 days

2

Site clearing

10 days

3

Foundation construction

20 days

4

Pool Excavation

21 days

5

Framing

36 days

6

Installation of windows and doors

7 days

7

Roofing

6 days

8

House Insulation

8 days

9

Pool Insulation

10 days

10

Pool Finishing

15 days

11

Bathroom and kitchen counters and cabinets

9 days

12

Electrical and plumbing

6 days

13

Painting

4 days

14

Carpet and flooring

8 days

15

End

0 days

https://lh4.googleusercontent.com/XKTXIyOiGqApIQOdQj6F2OioDosoEAV4MwPE-4eM8nP6kk0ng_fEB1L9HbTcYLZtTurqJEiRJeQfV0W7lKcNBfAjSwu1j2SZxnYo_o9zmhgYyusRvVgXIpU5ZTTEMKQD4ysHWKrMCritical Path:

1-2-3-5-6/7-8-11-12-14-15 with 104 days duration.