IVR Continued
ID Task
Mode
Task Name Duration Start Finish Predecessors
1 IVR System 69.5 days Fri 07/08/20 Thu 12/11/20 2 Scope 7.5 days Fri 07/08/20 Tue 18/08/20
3 Developing Project Scope
2 days Fri 07/08/20 Mon 10/08/20
4 Writing of Proposal 3 days Tue 11/08/20
Thu 13/08/20
3
5 Stakeholders Meeting 2.5 days Fri 14/08/20 Tue 18/08/20
4
6 Project Approved 0 days Tue 18/08/20
Tue 18/08/20
5
7 Analysis and design 34 days Tue 18/08/20Mon 05/10/20
8 Feasibility analysis 7.5 days Tue 18/08/20
Thu 27/08/20
6
9 Requirement analysis 5 days Tue 18/08/20
Tue 25/08/20
6
10 Reviewing of Requirement and budgeting
3 days Tue 25/08/20
Fri 28/08/20 9
11 Design functional requirements
4 days Tue 25/08/20
Thu 01/10/20
9
12 Review functional specifications
2 days Tue 25/08/20
Thu 27/08/20
9
13 Design a prototype 2 days Thu 01/10/20Mon 05/10/2011
14 Design complete 3 days Thu 27/08/20Tue 01/09/2012
15 Development 26.5 days Tue 01/09/20Wed 07/10/20
Project Manager
Project Manager,Analyst
Management,Project Manager,Technical Communicators
18/08
Analyst,Technical Communicators
Analyst,Developer
Project Manager,Testers
Developer
Developer
Developer
W T F S S M T W T F S S M T W
02 Aug '20 09 Aug '20 16 Aug '20
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
Page 1
Project: IVR System
Date: Fri 07/08/20
ID Task
Mode
Task Name Duration Start Finish Predecessors
16 Review requirement and functionality
3 days Tue 01/09/20
Fri 04/09/20 14
17 Istalling of call system 2 days Fri 04/09/20 Tue 08/09/2016
18 Coding 12 days Tue 08/09/20Thu 24/09/2017
19 Module Implementation 4 days Thu 24/09/20
Wed 30/09/20
18
20 Code testing 5.5 days Wed 30/09/20Wed 07/10/2019
21 Development complete 0 days Thu 24/09/20
Thu 24/09/20
18
22 Testing 6 days Thu 24/09/20Fri 02/10/20
23 Design Test Plan 2 days Thu 24/09/20Mon 28/09/2021
24 Integration Testing 3 days Mon 28/09/20Thu 01/10/2023
25 Unit Testing 3 days Mon 28/09/20Thu 01/10/2023
26 Integration Testing 1 day Thu 01/10/20Fri 02/10/20 24
27 Training 8 days Thu 01/10/20Tue 13/10/20
28 Develop training plan 2 days Thu 01/10/20Mon 05/10/2025
29 Training staff 3 days Fri 02/10/20 Wed 07/10/2026
30 Training of other users 4 days Mon 05/10/20
Fri 09/10/20 28
31 Training Done 2 days Fri 09/10/20 Tue 13/10/2030
32 Documentation 13 days Wed 07/10/20Mon 26/10/20
33 Develop guide 2 days Tue 13/10/20Thu 15/10/2031
34 Help system 3 days Wed 07/10/20Mon 12/10/2029
Developer W T F S S M T W T F S S M T W
02 Aug '20 09 Aug '20 16 Aug '20
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
Page 2
Project: IVR System
Date: Fri 07/08/20
ID Task
Mode
Task Name Duration Start Finish Predecessors
35 Review Help documentation
2 days Mon 12/10/20
Wed 14/10/20
34
36 user manual development
3 days Wed 14/10/20
Mon 19/10/20
35
37 Develop user manuals 2 days Mon 19/10/20Wed 21/10/2036
38 Documentation Report 3 days Wed 21/10/20
Mon 26/10/20
37
39 Application Deployment 10 days Mon 26/10/20Mon 09/11/20
40 Design deployment plan 2 days Mon 26/10/20
Wed 28/10/20
38
41 Deploying applications 3 days Wed 04/11/20
Mon 09/11/20
40
42 Hosting the VoIP System 3 days Wed 28/10/20
Mon 02/11/20
40
43 System Deployed 2 days Mon 02/11/20Wed 04/11/2042
44 Project Handing Over 6 days Wed 04/11/20Thu 12/11/20
45 Customer acceptance 2 days Wed 04/11/20Fri 06/11/20 43
46 User acceptance 3 days Fri 06/11/20 Wed 11/11/2045
47 Handing to ICT department
4 days Fri 06/11/20 Thu 12/11/20
45
48 Project complete 0 days Thu 12/11/20Thu 12/11/2047
W T F S S M T W T F S S M T W
02 Aug '20 09 Aug '20 16 Aug '20
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
Page 3
Project: IVR System
Date: Fri 07/08/20
Project Manager
Project Manager,Analyst
Management,Project Manager,Technical Communicators
18/08
Analyst,Technical Communicators
Analyst,Developer
Project Manager,Testers
Developer
Developer
Developer
Developer
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
16 Aug '20 23 Aug '20 30 Aug '20 06 Sep '20 13 Sep '20 20 Sep '20 27 Sep '20 04 Oct '20
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
Page 4
Project: IVR System
Date: Fri 07/08/20
Developer
Deployment Team,Developer
Developer
Deployment Team,Developer
Developer,Testers
24/09
Testers
Technical Communicators
Technical Communicators
Technical Communicators
Trainers
Trainers
Trainers
Trainers
Trainers
Technical Communicators
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
16 Aug '20 23 Aug '20 30 Aug '20 06 Sep '20 13 Sep '20 20 Sep '20 27 Sep '20 04 Oct '20
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
Page 5
Project: IVR System
Date: Fri 07/08/20
Project Manager
Analyst
Technical Communicators
Technical Communicators
Deployment Team
Deployment Team
Deployment Team
Deployment Team
Project Manager,Technical Communicators
Project Manager
IT
12/11
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
16 Aug '20 23 Aug '20 30 Aug '20 06 Sep '20 13 Sep '20 20 Sep '20 27 Sep '20 04 Oct '20
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
Page 6
Project: IVR System
Date: Fri 07/08/20
Analyst,Technical Communicators
Analyst,Developer
Project Manager,Testers
Developer
Developer
Developer
Developer
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
04 Oct '20 11 Oct '20 18 Oct '20 25 Oct '20 01 Nov '20 08 Nov '20 15 Nov '20
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
Page 7
Project: IVR System
Date: Fri 07/08/20
Developer
Deployment Team,Developer
Developer
Deployment Team,Developer
Developer,Testers
24/09
Testers
Technical Communicators
Technical Communicators
Technical Communicators
Trainers
Trainers
Trainers
Trainers
Trainers
Technical Communicators
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
04 Oct '20 11 Oct '20 18 Oct '20 25 Oct '20 01 Nov '20 08 Nov '20 15 Nov '20
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
Page 8
Project: IVR System
Date: Fri 07/08/20
Project Manager
Analyst
Technical Communicators
Technical Communicators
Deployment Team
Deployment Team
Deployment Team
Deployment Team
Project Manager,Technical Communicators
Project Manager
IT
12/11
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
04 Oct '20 11 Oct '20 18 Oct '20 25 Oct '20 01 Nov '20 08 Nov '20 15 Nov '20
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
Page 9
Project: IVR System
Date: Fri 07/08/20