Basic Data Review for Construction Project Equipment Arrangement
Step Description Actual Cycle Time (Hours) Potential Difference
1 Read basic data package 4 4 0
2 Write, type, proof, sign, copy, and distribute cover letter 21.9 0.5 21.4
3 Queue 40 0 40
4 Lead Engineer calls key people to schedule meeting 4 0.25 3.75
5 Write, type, proof, sign, copy, and distribute confirmation letter 25.4 2.1 23.3
6 Hold meeting; develop path forward and concerns 4 4 0
7 Project leader and specialist develop missing information 12 12 0
8 Determine plant preferred vendors 12 12 0
9 Review notes from meeting 12 12 0
10 Resolve open issues 106 104 2
11 Write, type, proof, sign, copy, and distribute acceptance letter 26.5 0.25 26.25
TOTALS 267.8 151.1 116.7