You need to schedule an order for 50 steppers which need to be shipped at the start of week 8. Assume lot for lot ordering. Indicate the planned order release(s) for component F.
Item | Lead Time | On Hand | Components |
Stepper A B C D E F | 2 1 2 3 1 2 2 | 20 10 30 10 15 5 20 | A(1), B(3), C(2) D(1), F(2) E(1), F(3) D(2), E(3)
|
Planned order release for F: Qty______________ Week:____________ Qty _______________ Week: ______________