INF 337 WK 3 DISCUSSION 1 & 2
[removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed] [removed]
Ashford 4: - Week 3 - Discussion 1
Earned Value Fundamentals |
Describe the linkages of the work breakdown structure and the time-phased budget to arrive at an earned value analysis. What is the impact on earned value if the cost estimation is significantly lower because of low estimates or specification changes in the project? Provide examples of projects you have been involved with or read about that may have had this problem.
Earned Value Problems
Of the three problems below, choose and solve one problem. Show your work. Along with your answer, define each term and explain the significance (meaning) of the solution.
1. During a project, Earned Value Analysis is performed and gives the following numbers:
EV: 523,000; PV: 623,000; AC: 643,000.
Which results are correct?
A. CV: +120,000; SV: +100,000
B. CV: +100,000; SV: +120,000
C. CV: -100,000; SV: -120,000
D. CV: -120,000; SV: -100,000
2. You found the following Earned Value Analysis information for a recently closed out project:
SPI = 0.7, CPI = 1.0
A. The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.
B. The project's deliverables have all been finished. The project came in ahead of schedule but on budget.
C. The project's deliverables have all been finished. The project came in on schedule but over budget.
3. You are assigned as the project manager to a project which had a one-time cost variance in the past caused by unexpected rework which has meanwhile
been finished.
You perform Earned Value Analysis and find the following results:
EV: 250,000; PV: 200,000; AC 275,000
BAC is 500,000.
What is right?
A. EAC = 550,000
B. EAC = 525,000
C. EAC = 500,000
D. EAC = 425,000
10 years ago
15
Purchase the answer to view it

- inf_337_week_3_homework_problems_earned_value_problems.docx
Purchase the answer to view it

- inf_337_wk_3_discussion_1.docx
Purchase the answer to view it

- EarnedValueProblems.docx
- Research an historical example of inflation (greater than 10% in the US or greater than 15% in any other country): Summarize the time-frame, duration and rate of inflation Analyze the root causes of the inflation Describe interest rates during the inflat
- Discussion: How do you tie it all togetweek 11
- Discussion #6
- < Business Law CRN 51884 - Quiz 1,23,4,6,7,8,9,10,11 MidTerm & Final Exam 2015- ALL >
- environment science
- For Professor Xavier - 5.2
- PHL 458 Week 3 Individual Assignment Refining Solutions Visual Organizer 5
- PHI208 WEEK 2 QUIZ
- 5
- Involving Fathers
