Is there anyone that knows Project management and can do this assignment?
Earned Value Problems
Of the three problems below, choose and solve one problem. Show your work. Along with your answer, define each term and explain the significance (meaning) of the solution.
1. During a project, Earned Value Analysis is performed and gives the following numbers:
EV: 523,000; PV: 623,000; AC: 643,000.
Which results are correct?
A. CV: +120,000; SV: +100,000
B. CV: +100,000; SV: +120,000
C. CV: -100,000; SV: -120,000
D. CV: -120,000; SV: -100,000
2. You found the following Earned Value Analysis information for a recently closed out project:
SPI = 0.7, CPI = 1.0
A. The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.
B. The project's deliverables have all been finished. The project came in ahead of schedule but on budget.
C. The project's deliverables have all been finished. The project came in on schedule but over budget.
3. You are assigned as the project manager to a project which had a one-time cost variance in the past caused by unexpected rework which has meanwhile
been finished.
You perform Earned Value Analysis and find the following results:
EV: 250,000; PV: 200,000; AC 275,000
BAC is 500,000.
What is right?
A. EAC = 550,000
B. EAC = 525,000
C. EAC = 500,000
D. EAC = 425,000
10 years ago
20
Purchase the answer to view it

- EarnedValueProblems.docx
- ethical in criminal justice
- grammar check
- history essays
- Attn: HelpClick / Please help with assignment.
- Research Paper
- BIZ 435 Week 3 Assignment 1
- BUS 401 Principles of Finance Week 1 Quizzes__2015 Verison
- CJA 444 Week 4 Individual Assignment Political Environment Case Study
- CJA 394 Week 3 Individual Assignment Court Issues Analysis
- Corporate Strategy Question 5