Assignment: The Stevens Company is converting from the SQL Server database to the Oracle® database. 

 

Using the sample shown below, create a Risk Information Sheet for at least five risks that might be encountered during the conversion.

 

Risk Information Sheet

Risk id: PO2-4-32

Date: March 4, 2014

Probability: 80%

Impact: High

Description: 

Over 70% of the software components scheduled for reuse will be integrated into the application. The remaining functionality will have to be custom developed.

Refinement/Context:

  • Certain reusable components were developed by a third party with no knowledge of internal design standards.
  • Certain reusable components have been implemented in a language that is not supported on the target environment.
 

Mitigation/Monitoring:

  • Contact third party to determine conformance to design standards.
  • Check to see if language support can be acquired.
 

Management/Contingency Plan/Trigger:

  • Develop a revised schedule assuming that 18 additional components will have to be built.
  • Trigger: Mitigation steps unproductive as of March 30, 2014
 

Current Status:

In process

Originator: 

Jane Manager

    • 11 years ago
    • 25
    Answer(2)

    Purchase the answer to view it

    blurred-text
    • attachment
      database_migration.docx

    Purchase the answer to view it

    blurred-text
    NOT RATED
    • attachment
      week2_name_risk_information_sheet.docx