project management

zhichen1027
344SAMLecture4-PlanningPart2.pptx

344SAM Project Management L4: Project Planning (Part 2)

Learning Outcomes

Explain the different approaches to estimating duration of tasks

Describe the different approaches used for planning projects (low level)

Critical Path Analysis

Gantt Charts

Re-cap from last lecture

Start of the planning process

Work breakdown structures (WBS)

You can use WBS to help to identify tasks

It can help to ensure the team understands the project scope

‘Draws a picture’ of task requirements

Dissertation

Identify Problem

Literature Review

Methodology

Data Gathering

Data Analysis

Conclusion

What

How

Why

Questionnaire

Interview

Case Study

Observation

Experiment

Questionnaire Design

Questionnaire Pilot

Questionnaire Correction

Allocating time to activities

Once a WBS is agreed, time can be allocated to each stage/task.

How do we estimate time?

Using historical data

Based upon past experience

Time the activity

Trial run

Impact of learning

Using a probabilistic method

With uncertainty/no experience

Weighted average technique

Based upon three estimates of duration for the activity:

Most optimistic (a)

Most likely (m)

Most pessimistic (b)

Weighted average = a + 4m + b

6

a = 24 hrs (most optimistic)

m = 48 hrs (most likely)

b = 96 hrs (most pessimistic)

WA = 24 + (4x48) + 96 = 52 hrs

6

Four simple questions

What can be done now?

What must you have done before that?

What can be done at the same time?

What must follow what you do now?

Importance of Sequential activities

Chicago Millennium Park

Delay: 4 years

Proposed cost: $150 million

Final cost: $482.4 million

Critical path analysis

Background

Developed in the late 1950’s by Remington Rand Univac

Improved the control of production to sales turnaround

Purpose

To calculate the longest sequence of dependent activities needed to complete the project

Use

Enables the PM to see the impact of delays/which activities can tolerate delays

Float highlights delay tolerance

Method

Two stages:

forward pass (earliest start)

reverse pass (latest start)

Activity boxes

Earliest start time (ES) Identifier number/code Earliest finish time (EF)
Float (FL) Activity descriptor
Latest start time (LS) Duration Latest finish time (LF)

Example (writing a book): organise activities

A
Write draft
B
Type manuscript
C
Create drawings
D
Design cover
E
Collate
F
Print
Earliest start time (ES) Identifier number/code Earliest finish time (EF)
Float (FL) Activity descriptor
Latest start time (LS) Duration Latest finish time (LF)

Example (writing a book): organise activities

A
Write draft
20
B
Type manuscript
10
C
Create drawings
5
D
Design cover
2
E
Collate
6
F
Print
5
Earliest start time (ES) Identifier number/code Earliest finish time (EF)
Float (FL) Activity descriptor
Latest start time (LS) Duration Latest finish time (LF)

Example (writing a book): Forward pass: ES + Duration = EF

0 A 20
Write draft
20
20 B 30
Type manuscript
10
20 C 25
Create drawings
5
20 D 22
Design cover
2
30 E 36
Collate
6
36 F 41
Print
5
Earliest start time (ES) Identifier number/code Earliest finish time (EF)
Float (FL) Activity descriptor
Latest start time (LS) Duration Latest finish time (LF)

Example (writing a book): Backward pass: LF – Duration = LS

0 A 20
Write draft
0 20 20
20 B 30
Type manuscript
20 10 30
20 C 25
Create drawings
25 5 30
20 D 22
Design cover
28 2 30
30 E 36
Collate
30 6 36
36 F 41
Print
36 5 41
Earliest start time (ES) Identifier number/code Earliest finish time (EF)
Float (FL) Activity descriptor
Latest start time (LS) Duration Latest finish time (LF)

Example (writing a book): determine slack = difference between LS and ES

0 A 20
0 Write draft
0 20 20
20 B 30
0 Type manuscript
20 10 30
20 C 25
5 Create drawings
25 5 30
20 D 22
8 Design cover
28 2 30
30 E 36
0 Collate
30 6 36
36 F 41
0 Print
36 5 41

Earliest start time (ES) Identifier number/code Earliest finish time (EF)
Float (FL) Activity descriptor
Latest start time (LS) Duration Latest finish time (LF)

Limitations to CPA

Sharing ‘slack’ with the team

Resources not visible

Can be visually complex on larger projects

Gantt Charts

Developed by Harvey Gantt in 1917

Most widely used planning tool by PMs

Show activities by calendar dates

Horizontal time line showing:

What should have been completed

Which activities should be in progress

What’s scheduled for the future

Predecessor & successor activities

Milestones

Project Gantt chart

Adding Resources

Gantt Charts

Easy to understand

Easy to continually update activities

Enables resources to be scheduled

Intuitive and easy to create

Basis for most project planning software

Limitations?

Gantt chart limitations

If all dependencies are added to the chart it may be overcrowded and difficult to read

All bars are the same thickness, suggesting similar workloads

Many activities are particularly front or back loaded, not as even as suggested by the bars

Unmanageable for very large projects

Gates and milestones

Phases/stages are punctuated by gates and milestones

These may correspond to completion of one or more project deliverables

e.g. in the development of a new concept car a milestone might be the completion of the engine design

Gates and milestones

What types of decisions need to be made when a project reaches a gate/milestone/end of stage?

If you were planning a project that would take 3 years to complete, how much detail would you go into?

Additional Information

Gantt chart software:

MS Project (available as a Microsoft product)

Project in a Box (free downloadable software)

http://www.projectinabox.org.uk/

Gantt Project (free downloadable software)

http://www.ganttproject.biz/

Problems in planning

Poorly defined scope

No WBS

Poor estimations

Poor communication

Procrastination

Trilogy Project

Scrapped in 2005

$170M

Three major components of a budget (APM 2012)

Base cost estimate

Resourcing

Accommodation

Consumables

Expenses

Capital items

Contingency

Identified risks

Management

Changes to scope of unidentified risks

Cost planning

Two basic approaches:

Top down – where you develop or set the total or top budget and then break it down into the component parts within that budget.

Bottom up – where you start with a list or plan or schedule of the things you want to do and then cost it up to get the total budget.

Cost estimations

Parametric

Works well when experienced in similar projects

E.g. highway development projects, office refurbishments

Forecasting

When little is known

More prone to change

Common with bid proposals

Considerations when budgeting

The base cost estimate

Outsourcing

Contingency

Direct and indirect costs

Fixed and variable costs

Currency fluctuations

Key factors in planning projects

1. Time

Timescales

Resources (will be discussed later)

Task dependencies

2. Cost

3. Quality (will be discussed later)

Recommended reading

Maylor, H. (2010) Project Management 4th ed. Essex: Prentice Hall (Chapter 5)

Pinto, J.K. (2013) Project Management: Achieving Competitive Advantage, 3rd edition, Harlow, Pearson (Chapters 9 and 10)

Online Self Study Task

References

APM (2012) APM Body of Knowledge. 6th ed. Bucks: APM

Lock, D. (2010) Project Management. 4th ed. Harlow: Prentice Hall

Maylor, H (2010) Project Management 4th ed. Essex: Prentice Hall

Office of Government Commerce (2009). Managing Successful Projects with PRINCE2: 2009 Edition . Norwich: TSO

Thanks!

Any questions?