Project Management Question
(Not rated)
(Not rated)
. The following information concerns progress at day 40 of an Internet marketing project. Determine if the project is in control based on time and cost to date. If not, what is the cost overage or underage?
Activity | Duration | Budget | Actual | % |
1-2 | 10 | 300 | 250 | 100.00 |
2-3 | 8 | 400 | 450 | 100.00 |
2-4 | 12 | 350 | 380 | 100.00 |
4-3 | 0 | 0 | 0 |
|
3-5 | 18 | 405 | 400 | 70.00 |
5-6 | 16 | 450 | ------- | 0.00 |
12 years ago
Answer for you...
NOT RATED
Purchase the answer to view it
- project_management_question_answer.doc