 The following information concerns progress at day 40 of an Internet marketing project. Determine if the project is in control based on time and cost to date.  If not, what is the cost overage or underage?

 

 

Activity

Duration

Budget

Actual

Cost

%

Complete

1-2

10

300

250

100.00

2-3

8

400

450

100.00

2-4

12

350

380

100.00

4-3

0

0

0

 

3-5

18

405

400

70.00

5-6

16

450

-------

0.00

 