Problem 16-17
Problem 16-17
| Given the following information on job times and due dates. |
| Job | Job Time (Hours) | Due Date (Hours) |
| a | 3.5 | 7 |
| b | 2.0 | 6 |
| c | 4.5 | 18 |
| d | 5.0 | 22 |
| e | 2.5 | 4 |
| f | 6.0 | 20 |
| a-1. | Determine the optimal processing sequence using (1) First come, first served, (2) Shortest processing time, (3) Earliest due date, and (4) Critical ratio. |
| Sequence for First come, first served | |
| Sequence for Shortest processing time | |
| Sequence for Earliest due date | |
| Sequence for Critical ratio | |
| a-2. | For each method, find the average job flow time and the average job tardiness. (Round your answers to 2 decimal places.) |
| First Come, First Served | Shortest Processing Time | Earliest Due Date | Critical Ratio | |
| Average flow time | [removed] | [removed] | [removed] | [removed] |
| Average job tardiness | [removed] | [removed] | [removed] | [removed] |