Processing times
marlasProblem 16-17
Given the following information on job times and due dates. |
Job | Job Time (Hours) | Due Date (Hours) |
a | 3.5 | 7 |
b | 2.0 | 6 |
c | 4.5 | 18 |
d | 5.0 | 22 |
e | 2.5 | 4 |
f | 6.0 | 20 |
a-1. | Determine the optimal processing sequence using (1) First come, first served, (2) Shortest processing time, (3) Earliest due date, and (4) Critical ratio. |
Sequence for First come, first served | |
Sequence for Shortest processing time | |
Sequence for Earliest due date | |
Sequence for Critical ratio | |
a-2. | For each method, find the average job flow time and the average job tardiness. (Round your answers to 2 decimal places.) |
First Come, First Served | Shortest Processing Time | Earliest Due Date | Critical Ratio | |
Average flow time | [removed] | [removed] | [removed] | [removed] |
Average job tardiness | [removed] | [removed] | [removed] | [removed] |
- 9 years ago
- 5
Answer(3)
Purchase the answer to view it
- paper_01.docx
Purchase the answer to view it
NOT RATED
- 1.jpg
- 2.jpg
Purchase the answer to view it
NOT RATED
Bids(1)
other Questions(10)