You need to schedule an order for 50 steppers which need to be shipped at the start of week 8.  Assume lot for lot ordering.  Indicate the planned order release(s) for component F.

Item

Lead Time

On Hand

Components

Stepper

A

B

C

D

E

F

2

1

2

3

1

2

2

20

10

30

10

15

5

20

A(1), B(3), C(2)

D(1), F(2)

E(1), F(3)

D(2), E(3)

 

 

 Planned order release for F:         Qty______________      Week:____________            Qty _______________          Week:  ______________