hm23
ID: Task List: Duration: Predecessors:
1 Preparation
2 Get trash bags 5 min
3 Pick up trash 15 min 2
4 Put gas in the equipment 5 min
5 Get the hedge clippers 5 min
6 Do the work
7 Trim weeds 30 min 3,4
8 Mow front yard 45 min 3,4
9 Edge sidewalk 15 min 3,4
10 Trim Hedge 30 min 5
11 Mow back yard 30 min 8
12 Clean up
13 Bag grass 30 min 7,9,10,11
14 Bundle trash 15 min 7,9,10,11
15 Haul trash 45 min 13,14
This exercise consists of a list of tasks for a home yard project. Working in Microsoft Project, you will create the task list, including summary tasks and their sub-tasks, create links between tasks and their predecessors. Set a start date for your project of April 30, 2013. Enter the following tasks, including the duration, where specified. Tasks with unspecified duration are summary tasks and the rest are sub-tasks
13 years ago 15
- I need to explain how this sentence is a "play on words". Fingers probably provided the first counting tools since...
- Clauses for dickson only
- Politics in Russia (Late 80s to Present) HWK : 10 1-page Max Answers
- draw your own bohr model for dickson only
- Essay for phyllis young
- What is success for teenagers?
- 200 words due tomorrow
- Exercise 20-38 Incentive Pay in the Hotel Industry
- George Washington, For Rey writer
- What types of learning strategies and evidence of accomplishments will you be using for your practicum project? Give some specific examples.