asap
ID: Task List: Duration: Predecessors:
1 Preparation
2 Get trash bags 5 min
3 Pick up trash 15 min 2
4 Put gas in the equipment 5 min
5 Get the hedge clippers 5 min
6 Do the work
7 Trim weeds 30 min 3,4
8 Mow front yard 45 min 3,4
9 Edge sidewalk 15 min 3,4
10 Trim Hedge 30 min 5
11 Mow back yard 30 min 8
12 Clean up
13 Bag grass 30 min 7,9,10,11
14 Bundle trash 15 min 7,9,10,11
15 Haul trash 45 min 13,14
This exercise consists of a list of tasks for a home yard project. Working in Microsoft Project, you will create the task list, including summary tasks and their sub-tasks, create links between tasks and their predecessors. Set a start date for your project of April 30, 2013. Enter the following tasks, including the duration, where specified. Tasks with unspecified duration are summary tasks and the rest are sub-tasks
13 years ago
15
- Which words in the sentence are the misplaced participial phrase? I finally reached the peak climbing steadily to the top of...
- WHOLE COURSE ETH 316 Week 1-5
- Analysis
- Summative Discussion Board
- ACC 205 Week 2 Brand new for nov 2013
- Experiment 5: prelab EXPERIMENTS IN CHEMICAL EQUILIBRIUM, chem 206 (1.5 marks) Write the expression for the equilibrium constants for the following reactions: a. N2(g)...
- Individual Online Therapy Paper
- For Jayce Writer
- Computer Paper
- What is the difference between a felony and a misdemeanor?