Crashing by hand.
Please see attachment for question: Answer below is what professor provided
Here is my answer. Please check my work.
Initially, the critical path takes 10 weeks. The critical path is B-F-H. We choose B as it is only 500. F is 650 H is 1200.
After redrawing the diagram, we see the project duration is 9 weeks and TWO critical paths. A-F-H and B-F-H. I chose F as its only 650 and it is common to both paths. The next closest is A and B (200 plus 500) which is 700. H is 1200.
After redrawing the picture, we see project duration is 8 weeks and we still see THREE critical paths A-E-H and A-F-H and B-F-H.
F cannot be crashed again. While A is in common to two critical paths, crashing A will not shorten the 3rd critical path. So I choose A and B which is 700. While H is in common to all three critical paths, H costs1200 which is more than 700.
After redrawing the diagram, we see the project duration is 7 weeks and THREE critical paths A-E-H A-F-H and B-F-H
If you wanted to crash it to 6 weeks - we need to crash H despite its high cost. (You do not need to crash to 6 weeks.)
F cannot be crashed again. A cannot be crashed again. While we can crash B, it will not save time on A-E-H and A-F-H. The only alternative is to choose H for 1200.
10 years ago 10
- How does the size of a person affect a bungee jump rope when they jump?
- Rhetorical Analysis and Commentary (for book "Becoming a Learner: Realizing the Opportunity of Education")
- Need help answering the question
- write a simple java program to calculate the sum of two numbers.
- BUS 610 Week 2 HR Performance Issues and Motivation
- 2. Consider the following cash flow [-100, + 230, -132]. We want to decide under what range of discount rate...
- ADJ 215 Week 2 Assignment Just Desserts Paper
- The Internet and Distributed Data
- For Tim.Makori
- As we discussed