| Activity | Normal
Time | Normal
Cost | Crash
Time | Crash
Cost | Crash
Cost
Per
Week | Notes |
| A | 3 | 300 | 2 | 500 | | The minimal time for this activity is 2. This activity can only be crashed once. |
| B | 4 | 800 | 2 | 1800 | | This activity can only be crashed twice. |
| C | 2 | 600 | 1 | 900 | | This activity can only be crashed once. Time must be at least 1. |
| E | 2 | 300 | 2 | 300 | | This activity is not crashable at all. |
| F | 3 | 750 | 2 | 1400 | | The minimal time for this activity is 2. This activity can only be crashed once. |
| G | 2 | 700 | 1 | 1600 |
| H | 3 | 675 | 2 | 1875 | | This activity can only be crashed once. Time must be at least 1. |
| Use the chart of PJ2a. |
| Step1. | Compute the Crash Cost Per Week (column F) above. Submit this excel sheet as PJ4 (your name). |
| Step2. | Crash this project to 9 weeks. Draw the picture. Be sure to tell me which activity(s) you crashed and the cost. |
| | Take a picture. Submit this as PJ4a. So PJ4a shows a project time of 9 weeks. The picture shows EST LST EFT LFT slacks and critical path(s). |
| Step3. | Crash this project to 8 weeks. Draw the picture. Be sure to tell me which activity(s) you crashed and the cost. |
| | Take a picture. Submit this as PJ4b. So PJ4b shows a project time of 8 weeks. The picture shows EST LST EFT LFT slacks and critical path(s). |
| Step4. | Crash this project to 7 weeks. Draw the picture. Be sure to tell me which activity(s) you crashed and the cost. |
| | Take a picture. Submit this as PJ4c. So PJ4c shows a project time of 7 weeks. The picture shows EST LST EFT LFT slacks and critical path(s). |