ASAP
ID: Task List: Duration: Predecessors:
1 Preparation
2 Get trash bags 5 min
3 Pick up trash 15 min 2
4 Put gas in the equipment 5 min
5 Get the hedge clippers 5 min
6 Do the work
7 Trim weeds 30 min 3,4
8 Mow front yard 45 min 3,4
9 Edge sidewalk 15 min 3,4
10 Trim Hedge 30 min 5
11 Mow back yard 30 min 8
12 Clean up
13 Bag grass 30 min 7,9,10,11
14 Bundle trash 15 min 7,9,10,11
15 Haul trash 45 min 13,14
This exercise consists of a list of tasks for a home yard project. Working in Microsoft Project, you will create the task list, including summary tasks and their sub-tasks, create links between tasks and their predecessors. Set a start date for your project of April 30, 2013. Enter the following tasks, including the duration, where specified. Tasks with unspecified duration are summary tasks and the rest are sub-tasks
13 years ago 15
- Howell and Newcombe examined 6 month old infants who were low birth weight babies when they were born. Each child...
- (TCO A) The Dividends account _____. (Points : 5)
- Marks: 2 What is the amount of FIT withheld for the year for Ruth V. Williams?
- 4 Accounting Questions
- FF hwww
- 3 online pre-final quizes
- GeometryREVISED SENT13 and 14
- Accounting
- Founder of modern egypt with what justification can it be argued that muhammad ali served to be described as such?
- EC Last Lecture