Comprehensive AAP (Implementation Section)
Implementation Plan WWTC
Project Schedule
|
Date Completed |
Project Milestone |
|
July 2nd |
Business requirements and network design requirements completed |
|
July 9th |
The draft of the network design, scope of work, equipment list, IP scheme, high level diagram, VoIP design, voice bandwidth, and wireless design |
|
July 23rd |
Requests for network design modification received from WWTC |
|
July 23rd |
The draft of the business security needs, security policies, security design, role of devices, and security diagram |
|
July 30th |
Requests for security design modification received from WWTC |
|
July 30th |
The draft of the business Active Directory needs, Active Directory features, creation of a forest, link New York site to HQ, creation of OUs, add users to OUs, creation of groups, creation of a GPO, and implementation of GPO policies |
|
August 13th |
Requests for Active Directory design modification received from WWTC |
|
August 13th |
The draft of the project implementation plan |
|
August 20th |
Requests for project implementation plan modification received from WWTC |
|
August 20th |
The final network design and implementation plan is submitted to WWTC |
|
August 27th |
Purchase of all required hardware and software is completed |
|
September 11th |
All required hardware and software is received |
|
September 25th |
All networking devices for the unclassified network are configured, put in place, and connected |
|
September 29th |
Connectivity testing completed for unclassified network devices |
|
October 13th |
Unclassified Security devices configured, put in place, and connected |
|
October 20th |
Security testing completed |
|
November 3rd |
Unclassified Servers installed and connected |
|
November 10th |
Server functionality testing |
|
November 24th |
All unclassified endpoint systems i.e. desktops, VoIP phones, and printers are configured and put in place on the unclassified network |
|
December 4th |
Active Directory is implemented on the unclassified network |
|
December 8th |
Testing completed for Active Directory and endpoints |
|
December 18th |
Unclassified VoIP is implemented; ISP and PSTN connections contracted |
|
December 22nd |
Internal testing completed for Wireless and VoIP |
|
January 8th |
Testing completed for ISP connectivity on the unclassified network; External testing completed for VoIP on the unclassified network |
|
January 12th |
Unclassified VPN connection to HQ is established |
|
January 15th |
Connectivity testing completed for the VPN connection to HQ |
|
January 19th |
All classified network devices are configured, put in place, and connected |
|
January 26th |
Connectivity testing completed for network devices |
|
February 9th |
All classified security devices are configured, put in place, and connected |
|
February 14th |
Security testing completed |
|
February 21st |
All classified servers are configured, put in place, and connected |
|
February 26th |
Server connectivity testing completed |
|
March 2nd |
All classified end user laptops are configured and put in place |
|
March 7th |
Connectivity testing completed for all end user laptops |
|
March 9th |
Classified connection with HQ is established |
|
March 13th |
Connectivity testing completed with HQ; all hardware and software are backed up |
|
March 19th |
All network documentation has been updated with any changes |
|
April 30th |
All WWTC administrators are trained |
|
April 30th |
All WWTC user accounts are created |
|
May 5th |
Validation testing completed for all WWTC user accounts |
|
May 30th |
Acceptability testing completed by WWTC |
|
May 30th |
The project is completed |
Implementation Plan Template Group 5
UMUC CMIT 495
UMUC CMIT 495