The owner of a small mill-working plant that builds cabinets is developing his aggregate plan for the next year. The relevant cost data and forecast for the next 4 quarters is provided below. The company currently has 12 employees and works one 8 hour shift each day with 2 paid 15 minute breaks. Assume each quarter has 65 working days, and that it currently has no units in stock. Use this information and the information from the table to answer the questions below.
Costs Forecast Other Data
Holding Cost/Unit/Quarter $25.00 Qtr 1 1500 Labor Hours/Unit 4.5
Hiring Cost $2,500.00 Qtr 2 1200 Beginning Inventory 0
Layoff Cost $3,500.00 Qtr 3 2100
Subcontract Cost $135.00 Qtr 4 1650
Avg. Labor Cost/Hour $18.00
Overtime Labor Cost/Hour $27.00
Part I
1) If the company used a chase demand startegy and rounded any fractional number of employees to the nearest whole number, how many employees would be used in each quarter?
2) If the company used a level capacity strategy and rounded any fractional number of employees to the nearest whole number, how many employees would be used?
Period 1 2 3 4
Forecast 1500 1200 2100 1650
Hours Req.
Workers Req.
Workers Used
Part II
Assume the company wants to use a Level Capacity Strategy with 14 employees (Round the Production in each period to the nearest whole number). In any period where on-hand inventory and production do not meet demand the company would supplement with overtime production. Use the table below to calculate the total costs associated with using this plan.
Q3) What would the overtime production cost be for this plan?
Q4) What would theTotal Cost be for this plan?
Level Capacity Aggregate Plan
Period 1 2 3 4
Forecast 1500 1200 2100 1650
Workers Used 14 14 14 14
Hire/(Fire)
Production
Production - Forecast
Beginning Inventory
Ending Inventory
Average Inventory
Overtime Production Total Cost
Hiring Cost
Firing Cost
Reg. Output
O.T.
Subcontract
Inventory
Backorder
Total Cost:
Total Cost For Plan

Sheet3