Problem 5 answer
| Problem 5 - Use the data below to calculate two forecasts: 1) A 4 period Moving Average; 2) An Exponetial Smoothed forecast with an alpha of .2 What is the expected error for these two forecasting techniques? Which one do you recommend using? | ||
| Actual | ||
| Month | Demand | |
| January | 1150 | |
| February | 1480 | |
| March | 1610 | |
| April | 1500 | |
| May | 1110 | |
| June | 660 | |
| July | 690 | |
| August | 760 | |
| September | 810 | |
| October | 960 | |
| November | 750 | |
| December | 720 | |
| January | 630 | |
| February | 700 | |
| March | 770 | |
| April | 860 | |
| May | 910 | |
| June | 740 | |
| July | 750 | |
| August | 1000 | |
| September | 1450 | |
| October | 1760 | |
| November | 1630 | |
| December | 1200 | |