| P301 Project Mgt. Homework |
| Task | Optimistic | Most Likely | Pessimistic |
| A | 10 | 12 | 20 |
| B | 14 | 16 | 24 |
| C | 7 | 14 | 21 |
| D | 15 | 19 | 29 |
| E | 12 | 21 | 24 |
| F | 5 | 17 | 23 |
| G | 10 | 13 | 16 |
| H | 7 | 10 | 19 |
| I | 10 | 16 | 28 |
| J | 10 | 20 | 24 |
| K | 10 | 15 | 26 |
| L | 15 | 21 | 27 |
| M | 2 | 4 | 12 |
| | | | | | | | | | |
| 1. What is the critical path for this project & its expected duration? |
| 2. What is the standard deviation of the critical path? |
| 3. What is the slack on each activity? |
| 4. What is the probability of completing the critical path in 75 weeks? |
| 5. What completion time would give you a 99% confidence of completing the critical path on-time? |