High level implementation plan:
High-level implementation plan of the business enterprise software application.
There are several phases that can be used to achieve this implementation. The table below indicates the phases with their timelines.
|
Phase |
timelines |
|
Project establishment. |
Comprises of the following activities: 1. Mobilization. 2. Project team formation. 3. Project plan detailing e.g. documentation and fine tuning. Deliverables of this phase are: 1. Project administration plan. 2. Project standards document. 3. Project board formation. 4. Project implementation committee formation. 5. Key users team formation. |
|
Procedure development. |
Comprises of the following activities which are iterative: 1. Process mapping. 2. Gap detention. 3. Work around identification. 4. Organizational impact analysis. Deliverables: 1. Business model through flow chart 2. Customization design specification document for identified modifications. 3. Draft procedure manual. 4. Acceptance test plan and data. |
|
Application software customization. |
Activities: 1. Program development. 2. Unit testing. 3. System testing. Deliverables: Customized unit and system tested application software. |
|
Acceptance testing. |
The central goal of user acceptance testing is to exhibit that the system works. Deliverables: • Tested application software. • Updated procedure manual. |
|
End user training |
All the selected end users will be trained in the specific functions they are needed to work. Deliverables: • End users trained as per training plan. |
|
Conference room trial |
This phase deals with the simulation of the actual business environment. Activities which are iterative: · Identification and entry of representative data. · Simulation of the business model. · Business model enhancement. · Finalization of procedure manual. Deliverables: · Final procedure manual. · Final business model |
|
Data loading. |
Activities: 1. Data conversion and loading. 2. Establishment of access rights and passwords. Deliverables: · Data loading completed. |
|
Live trail. |
This phase allows users to work on the application software with real time data. Deliverables: • live trial completion. |
References
1. Yusuf, Y., Gunasekaran, A., & Abthorpe, M. S. (2005). Enterprise information and project implementation: A case study of ERP in Rolls-Royce. International Journal of Production Economics, 87(3), 251-266.
2. Shiffman, R. N., Michel, G., Essaihi, A., & Thornquist, E. (2004). Bridging the guideline implementation gap: systematic, document-centered approach to guideline implementation. Journal of the American Medical Informatics Association, 11(5), 418-426.
3. Dawson, J., & Owens, J. (2008). Critical success factors in the chartering phase: a case study of an ERP implementation. International Journal of Enterprise Information Systems, 4(3), 9.