| Task Name | | | | | | | | | | Work | Duration | Start | Finish |
| 1. Set Up IT System for Marley's Dental Clinic | | | | | | | | | | 680 | 50 | Wed 6/7/17 | Wed 8/15/17 |
| | 1.1 Finalize Project Plan | | | | | | | | | 24 hrs | 2 days | Wed 6/7/17 | Thu 6/8/17 |
| | | 1.1.1 Project team and client meeting | | | | | | | | 24 hrs | 2 days | Wed 6/7/17 | Thu 6/8/17 |
| | | | 1.1.1.1 Review project plan | | | | | | | 16 hrs | 1 day | Wed 6/7/17 | Wed 6/7/17 |
| | | | | Cristy Conner - Project Sponsor | | | | | | 8 hrs | | Wed 6/7/17 | Wed 6/7/17 |
| | | | | Edward Guzinksi - Project Manager | | | | | | 8 hrs | | Wed 6/7/17 | Wed 6/7/17 |
| | | | 1.1.1.2 Review budget | | | | | | | 4 hrs | 0.5 days | Thu 6/8/17 | Thu 6/8/17 |
| | | | | Cristy Conner - Project Sponsor | | | | | | 4 hrs | | Thu 6/8/17 | Thu 6/8/17 |
| | | | 1.1.1.3 Finalize requirements | | | | | | | 4 hrs | 0.5 days | Thu 6/8/17 | Thu 6/8/17 |
| | | | | Antonio Jones - Requirements | | | | | | 4 hrs | | Thu 6/8/17 | Thu 6/8/17 |
| | 1.2 Order Hardware | | | | | | | | | 224 hrs | 15 days | Fri 6/9/17 | Thu 6/27/17 |
| | | 1.2.1 Order computers | | | | | | | | 48 hrs | 3 days | Fri 6/9/17 | Tue 6/13/17 |
| | | | 1.2.1.1 Determine type of computers needed | | | | | | | 32 hrs | 2 days | Fri 6/9/17 | Mon 6/12/17 |
| | | | | Antonio Jones - Requirements | | | | | | 16 hrs | | Fri 6/9/17 | Mon 6/12/17 |
| | | | | Tremaine Shivers - Technical Architect | | | | | | 16 hrs | | Fri 6/9/17 | Mon 6/12/17 |
| | | | 1.2.1.2 Determine quantity of computers needed | | | | | | | 16 hrs | 1 day | Tue 6/13/17 | Tue 6/13/17 |
| | | | | Antonio Jones - Requirements | | | | | | 8 hrs | | Tue 6/13/17 | Tue 6/13/17 |
| | | | | Tremaine Shivers - Technical Architect | | | | | | 8 hrs | | Tue 6/13/17 | Tue 6/13/17 |
| | | 1.2.2 Order tablets | | | | | | | | 48 hrs | 3 days | Wed 6/14/17 | Fri 6/16/17 |
| | | | 1.2.2.1 Determine type of tablets needed | | | | | | | 32 hrs | 2 days | Wed 6/14/17 | Thu 6/15/17 |
| | | | | Antonio Jones - Requirements | | | | | | 16 hrs | | Wed 6/14/17 | Thu 6/15/17 |
| | | | | Tremaine Shivers - Technical Architect | | | | | | 16 hrs | | Wed 6/14/17 | Thu 6/15/17 |
| | | | 1.2.2.2 Determine number of tables needed | | | | | | | 16 hrs | 1 day | Fri 6/16/17 | Fri 6/16/17 |
| | | | | Antonio Jones - Requirements | | | | | | 8 hrs | | Fri 6/16/17 | Fri 6/16/17 |
| | | | | Tremaine Shivers - Technical Architect | | | | | | 8 hrs | | Fri 6/16/17 | Fri 6/16/17 |
| | | 1.2.3 Order server | | | | | | | | 48 hrs | 3 days | Mon 6/19/17 | Wed 6/21/17 |
| | | | 1.2.3.1 Determine tyoe pf server needed | | | | | | | 32 hrs | 2 days | Mon 6/19/17 | Tue 6/20/17 |
| | | | | Antonio Jones - Requirements | | | | | | 16 hrs | | Mon 6/19/17 | Tue 6/20/17 |
| | | | | Tremaine Shivers - Technical Architect | | | | | | 16 hrs | | Mon 6/19/17 | Tue 6/20/17 |
| | | | 1.2.3.2 Determine number of servers needed | | | | | | | 16 hrs | 1 days | Wed 6/21/17 | Wed 6/21/17 |
| | | | | Antonio Jones - Requirements | | | | | | 8 hrs | | Wed 6/21/17 | Wed 6/21/17 |
| | | | | Tremaine Shivers - Technical Architect | | | | | | 8 hrs | | Wed 6/21/17 | Wed 6/21/17 |
| | | 1.2.4 Order network cables | | | | | | | | 32 hrs | 3 days | Thu 6/22/17 | Mon 6/26/17 |
| | | | 1.2.4.1 Determine length and quantity needed | | | | | | | 16 hrs | 2 days | Thu 6/22/17 | Fri 6/23/17 |
| | | | | Antonio Jones - Requirements | | | | | | 16 hrs | | Thu 6/22/17 | Fri 6/23/17 |
| | | | 1.2.4.2 Determine number of plenum cables needed | | | | | | | 16 hrs | 1 day | Mon 6/26/17 | Mon 6/26/17 |
| | | | | Antonio Jones - Requirements | | | | | | 8 hrs | | Mon 6/26/17 | Mon 6/26/17 |
| | | | | Tremaine Shivers - Technical Architect | | | | | | 8 hrs | | Mon 6/26/17 | Mon 6/26/17 |
| | | 1.2.5 Order network switch | | | | | | | | 48 hrs | 3 days | Tue 6/27/17 | Thu 6/29/17 |
| | | | 1.2.5.1 Determine type of switches needed | | | | | | | 32 hrs | 2 days | Tue 6/27/17 | Wed 6/28/17 |
| | | | | Antonio Jones - Requirements | | | | | | 16 hrs | | Tue 6/27/17 | Wed 6/28/17 |
| | | | | Tremaine Shivers - Technical Architect | | | | | | 16 hrs | | Tue 6/27/17 | Wed 6/28/17 |
| | | | 1.2.5.2 Determine number of swiches needed | | | | | | | 16 hrs | 1 day | Thu 6/29/17 | Thu 6/29/17 |
| | | | | Antonio Jones - Requirements | | | | | | 8 hrs | | Thu 6/29/17 | Thu 6/29/17 |
| | | | | Tremaine Shivers - Technical Architect | | | | | | 8 hrs | | Thu 6/29/17 | Thu 6/29/17 |
| | 1.3 Order Software | | | | | | | | | 16 hrs | 1 day | Fri 6/30/17 | Fri 6/30/17 |
| | | 1.3.1 Buy appointment software | | | | | | | | 4.8 hrs | 0.3 days | Fri 6/30/17 | Fri 6/30/17 |
| | | | Antonio Jones - Requirements | | | | | | | 2.4 hrs | | Fri 6/30/17 | Fri 6/30/17 |
| | | | Tremaine Shivers - Technical Architect | | | | | | | 2.4 hrs | | Fri 6/30/17 | Fri 6/30/17 |
| | | | ScheduleOne Appointment Software |
| | | 1.3.2 Buy Curve Dental Hero | | | | | | | | 4.8 hrs | 0.3 days | Fri 6/30/17 | Fri 6/30/17 |
| | | | Antonio Jones - Requirements | | | | | | | 2.4 hrs | | Fri 6/30/17 | Fri 6/30/17 |
| | | | Tremaine Shivers - Technical Architect | | | | | | | 2.4 hrs | | Fri 6/30/17 | Fri 6/30/17 |
| | | | Curve Dental Hero |
| | | 1.3.3 Register for anti-virus software | | | | | | | | 6.4 hrs | 0.4 days | Fri 6/30/17 | Fri 6/30/17 |
| | | | Antonio Jones - Requirements | | | | | | | 3.2 hrs | | Fri 6/30/17 | Fri 6/30/17 |
| | | | Tremaine Shivers - Technical Architect | | | | | | | 3.2 hrs | | Fri 6/30/17 | Fri 6/30/17 |
| | | | Norton Anti-Virus |
| | 1.4 Network Installation | | | | | | | | | 108 hrs | 14 days | Mon 7/3/17 | Thu 7/20/17 |
| | | 1.4.1 Find networking contractors | | | | | | | | 60 hrs | 6 days | Mon 7/3/17 | Mon 7/10/17 |
| | | | 1.4.1.1 Research networking contractors | | | | | | | 16 hrs | 2 days | Mon 7/3/17 | Tue 7/4/17 |
| | | | | Yvelisse Orana - Business Analyst | | | | | | 16 hrs | | Mon 7/3/17 | Tue 7/4/17 |
| | | | 1.4.1.2 Contact networking contractor | | | | | | | 44 hrs | 4 days | Wed 7/5/17 | Mon 7/10/17 |
| | | | | 1.4.1.2.1 Negotiate contract | | | | | | 16 hrs | 2 days | Wed 7/5/17 | Thu 7/6/17 |
| | | | | | Yvelisse Orana - Business Analyst | | | | | 16 hrs | | Wed 7/5/17 | Thu 7/6/17 |
| | | | | 1.4.1.2.2 Sign contract | | | | | | 4 hrs | 0.5 days | Fri 7/7/17 | Fri 7/7/17 |
| | | | | | Cristy Conner - Project Sponsor | | | | | 4 hrs | | Fri 7/7/17 | Fri 7/7/17 |
| | | | | 1.4.1.2.3 Schedule networking install | | | | | | 8 hrs | 0.5 days | Fri 7/7/17 | Fri 7/7/17 |
| | | | | | Antonio Jones - Requirements | | | | | 4 hrs | | Fri 7/7/17 | Fri 7/7/17 |
| | | | | | Tremaine Shivers - Technical Architect | | | | | 4 hrs | | Fri 7/7/17 | Fri 7/7/17 |
| | | | | 1.4.1.2.4 Install network cabling | | | | | | 16 hrs | 1 day | Mon 7/10/17 | Mon 7/10/17 |
| | | | | | Tremaine Shivers - Technical Architect | | | | | 8 hrs | | Mon 7/10/17 | Mon 7/10/17 |
| | | | | | Victor Wynn - Quality Assurance/Test Engineer | | | | | 8 hrs | | Mon 7/10/17 | Mon 7/10/17 |
| | | | | | Network Contractors |
| | | 1.4.2 Contact ISP | | | | | | | | 24 hrs | 3 days | Tue 7/11/17 | Thu 7/13/17 |
| | | | 1.4.2.1 Negotiate contract | | | | | | | 16 hrs | 2 days | Tue 7/11/17 | Wed 7/12/17 |
| | | | | Yvelisse Orana - Business Analyst | | | | | | 16 hrs | | Tue 7/11/17 | Wed 7/12/17 |
| | | | 1.4.2.2 Sign contract | | | | | | | 8 hrs | 1 day | Thu 7/13/17 | Thu 7/13/17 |
| | | | | Cristy Conner - Project Sponsor | | | | | | 8 hrs | | Thu 7/13/17 | Thu 7/13/17 |
| | | 1.4.3 ISP Install | | | | | | | | 24 hrs | 2 days | Mon 7/17/17 | Tue 7/18/17 |
| | | | 1.4.3.1 Schedule install | | | | | | | 8 hrs | 1 day | Mon 7/17/17 | Mon 7/17/17 |
| | | | | Edward Guzinski - Project Manager | | | | | | 8 hrs | | Mon 7/17/17 | Mon 7/17/17 |
| | | | 1.4.3.2 Conduct install | | | | | | | 16 hrs | 1 day | Tue 7/18/17 | Tue 7/18/17 |
| | | | | Tremaine Shivers - Technical Architect | | | | | | 8 hrs | | Tue 7/18/17 | Tue 7/18/17 |
| | | | | Victor Wynn - Quality Assurance/Test Engineer | | | | | | 8 hrs | | Tue 7/18/17 | Tue 7/18/17 |
| | | | | Network Contractors |
| | 1.5 Implement Technology | | | | | | | | | 48 hrs | 5 days | Fri 7/21/17 | Thu 7/27/17 |
| | | 1.5.1 Set Up PCs | | | | | | | | 32 hrs | 3 days | Fri 7/21/17 | Tue 7/25/17 |
| | | | 1.5.1.1 Connect PCs to wireless network | | | | | | | 16 hrs | 2 days | Fri 7/21/17 | Mon 7/24/17 |
| | | | | Victor Wynn - Quality Assurance/Test Engineer | | | | | | 16 hrs | | Fri 7/21/17 | Mon 7/24/17 |
| | | | | 10 PCs |
| | | | | Network Contractors | | | | | | 16 hrs |
| | | | | WiFi Extender |
| | | | | Internet Modem |
| | | | 1.5.1.2 Install appointment software | | | | | | | 7.2 hrs | 0.3 days | Tue 7/25/17 | Tue 7/25/17 |
| | | | | Tremaine Shivers - Technical Architect | | | | | | 2.4 hrs | | Tue 7/25/17 | Tue 7/25/17 |
| | | | | Victor Wynn - Quality Assurance/Test Engineer | | | | | | 2.4 hrs | | Tue 7/25/17 | Tue 7/25/17 |
| | | | | 10 PCs |
| | | | | ScheduleOne Appointment Software |
| | | | | Network Contractors | | | | | | 2.4 hrs |
| | | | 1.5.1.3 Install Curve Dental Hero | | | | | | | 7.2 hrs | 0.3 days | Tue 7/25/17 | Tue 7/25/17 |
| | | | | Tremaine Shivers - Technical Architect | | | | | | 2.4 hrs | | Tue 7/25/17 | Tue 7/25/17 |
| | | | | Victor Wynn - Quality Assurance/Test Engineer | | | | | | 2.4 hrs | | Tue 7/25/17 | Tue 7/25/17 |
| | | | | 10 PCs |
| | | | | Curve Dental Hero |
| | | | | Network Contractors | | | | | | 2.4 hrs |
| | | | 1.5.1.4 Install anti-virus software | | | | | | | 9.6 hrs | 0.4 days | Tue 7/25/17 | Tue 7/25/17 |
| | | | | Tremaine Shivers - Technical Architect | | | | | | 3.2 hrs | | Tue 7/25/17 | Tue 7/25/17 |
| | | | | Victor Wynn - Quality Assurance/Test Engineer | | | | | | 3.2 hrs | | Tue 7/25/17 | Tue 7/25/17 |
| | | | | 10 PCs |
| | | | | Curve Dental Hero |
| | | | | Network Contractors | | | | | | 3.2 hrs |
| | | 1.5.2 Set up Tablets | | | | | | | | 32 hrs | 2 days | Wed 7/26/17 | Thu 7/27/17 |
| | | | 1.5.2.1 Connect tablets to wireless network | | | | | | | 16 hrs | 1 day | Wed 7/26/17 | Wed 7/26/17 |
| | | | | Tremaine Shivers - Technical Architect | | | | | | 8 hrs | | Wed 7/26/17 | Wed 7/26/17 |
| | | | | 10 Tablets |
| | | | | Network Contractors | | | | | | 8 hrs |
| | | | | WiFi Extender |
| | | | 1.5.2.2 Install appointment software | | | | | | | 6.4 hrs | 0.4 days | Thu 7/27/17 | Thu 7/27/17 |
| | | | | Tremaine Shivers - Technical Architect | | | | | | 3.2 hrs | | Thu 7/27/17 | Thu 7/27/17 |
| | | | | 10 Tablets |
| | | | | ScheduleOne Appointment Software |
| | | | | Network Contractors | | | | | | 3.2 hrs |
| | | | 1.5.2.3 Install curve Dental Hero | | | | | | | 4.8 hrs | 0.3 days | Thu 7/27/17 | Thu 7/27/17 |
| | | | | Tremaine Shivers - Technical Architect | | | | | | 2.4 hrs | | Thu 7/27/17 | Thu 7/27/17 |
| | | | | 10 Tablets |
| | | | | Curve Dental Hero |
| | | | | Network Contractors | | | | | | 2.4 hrs |
| | | | 1.5.2.4 Install anti-virus software | | | | | | | 4.8 hrs | 0.3 days | Thu 7/27/17 | Thu 7/27/17 |
| | | | | Tremaine Shivers - Technical Architect | | | | | | 2.4 hrs | | Thu 7/27/17 | Thu 7/27/17 |
| | | | | 10 Tablets |
| | | | | Norton Anti-Virus |
| | | | | Network Contractors | | | | | | 2.4 hrs |
| | 1.6 Test Technology | | | | | | | | | 8 hrs | 1 day | Fri 7/28/17 | Fri 7/28/17 |
| | | 1.6.1 Add a client into appointment software | | | | | | | | 2.4 hrs | 0.3 days | Fri 7/28/17 | Fri 7/28/17 |
| | | | Victor Wynn - Quality Assurance/Test Engineer | | | | | | | 2.4 hrs | | Fri 7/28/17 | Fri 7/28/17 |
| | | | 10 PCs |
| | | | 10 Tablets |
| | | | ScheduleOne Appointment Software |
| | | 1.6.2 Verify that you can find the newly added appointment | | | | | | | | 2.4 hrs | 0.3 days | Fri 7/28/17 | Fri 7/28/17 |
| | | | Victor Wynn - Quality Assurance/Test Engineer | | | | | | | 2.4 hrs | | Fri 7/28/17 | Fri 7/28/17 |
| | | | 10 PCs |
| | | | 10 Tablets |
| | | | ScheduleOne Appointment Software |
| | | 1.6.3 Evaluate Curve Dental Hero by locating insurance information | | | | | | | | 3.2 hrs | 0.4 days | Fri 7/28/17 | Fri 7/28/17 |
| | | | Victor Wynn - Quality Assurance/Test Engineer | | | | | | | 3.2 hrs | | Fri 7/28/17 | Fri 7/28/17 |
| | | | 10 PCs |
| | | | 10 Tablets |
| | | | Curve Dental Hero |
| | 1.7 Train Employees | | | | | | | | | 120 hrs | 10 days | Mon 7/31/17 | Fri 8/11/17 |
| | | 1.7.1 Build training material | | | | | | | | 48 hrs | 2 days | Mon 7/31/17 | Tue 8/1/17 |
| | | | Antonio Jones - Requirements | | | | | | | 16 hrs | | Mon 7/31/17 | Tue 8/1/17 |
| | | | Tremaine Shivers - Technical Architect | | | | | | | 16 hrs | | Mon 7/31/17 | Tue 8/1/17 |
| | | | Victor Wynn - Quality Assurance/Test Engineer | | | | | | | 16 hrs | | Mon 7/31/17 | Tue 8/1/17 |
| | | | 10 PCs |
| | | | Microsoft PowerPoint |
| | | 1.7.2 Set up training environment | | | | | | | | 12 hrs | 0.5 days | Wed 8/2/17 | Wed 8/2/17 |
| | | | Antonio Jones - Requirements | | | | | | | 4 hrs | | Wed 8/2/17 | Wed 8/2/17 |
| | | | Tremaine Shivers - Technical Architect | | | | | | | 4 hrs | | Wed 8/2/17 | Wed 8/2/17 |
| | | | Victor Wynn - Quality Assurance/Test Engineer | | | | | | | 4 hrs | | Wed 8/2/17 | Wed 8/2/17 |
| | | | 10 PCs |
| | | 1.7.3 Schedule training | | | | | | | | 8 hrs | 0.5 days | Wed 8/2/17 | Wed 8/2/17 |
| | | | Edward Guzinski - Project Manager | | | | | | | 4 hrs | | Wed 8/2/17 | Wed 8/2/17 |
| | | | Dental Employees | | | | | | | 4 hrs |
| | | 1.7.4 Conduct training | | | | | | | | 88 hrs | 4 days | Thu 8/3/17 | Tue 8/8/2017 |
| | | | 1.7.4.1 Run employees through training | | | | | | | 16 hrs | 1 day | Thu 8/3/17 | Thu 8/3/17 |
| | | | | Antonio Jones - Requirements | | | | | | 8 hrs | | Thu 8/3/17 | Thu 8/3/17 |
| | | | | 10 PCs |
| | | | | Microsoft PowerPoint |
| | | | | Training Video |
| | | | | Dental Employees | | | | | | 8 hrs |
| | | | 1.7.4.2 Let employees test drive | | | | | | | 24 hrs | 1 day | Fri 8/4/17 | Fri 8/4/17 |
| | | | | Tremaine Shivers - Technical Architect | | | | | | 8 hrs | | Fri 8/4/17 | Fri 8/4/17 |
| | | | | Victor Wynn - Quality Assurance/Test Engineer | | | | | | 8 hrs | | Fri 8/4/17 | Fri 8/4/17 |
| | | | | 10 PCs |
| | | | | ScheduleOne Appointment Software |
| | | | | Dental Employees | | | | | | 8 hrs |
| | | | 1.7.4.3 Run employees through training | | | | | | | 24 hrs | 1 day | Mon 8/7/17 | Mon 8/7/17 |
| | | | | Tremaine Shivers - Technical Architect | | | | | | 8 hrs | | Mon 8/7/17 | Mon 8/7/17 |
| | | | | Victor Wynn - Quality Assurance/Test Engineer | | | | | | 8 hrs | | Mon 8/7/17 | Mon 8/7/17 |
| | | | | 10 PCs |
| | | | | Training Video |
| | | | | Dental Employees | | | | | | 8 hrs |
| | | | 1.7.4.4 Let employees test drive Ace Dental | | | | | | | 12 hrs | 0.5 days | Tue 8/8/17 | Tue 8/8/17 |
| | | | | Tremaine Shivers - Technical Architect | | | | | | 4 hrs | | Tue 8/8/17 | Tue 8/8/17 |
| | | | | Victor Wynn - Quality Assurance/Test Engineer | | | | | | 4 hrs | | Tue 8/8/17 | Tue 8/8/17 |
| | | | | 10 PCs |
| | | | | Curve Dental Hero |
| | | | | Dental Employees | | | | | | 4 hrs |
| | | | 1.7.4.5 Regroup for questions on both | | | | | | | 12 hrs | 0.5 days | Tue 8/8/17 | Tue 8/8/17 |
| | | | | Tremaine Shivers - Technical Architect | | | | | | 4 hrs | | Tue 8/8/17 | Tue 8/8/17 |
| | | | | Victor Wynn - Quality Assurance/Test Engineer | | | | | | 4 hrs | | Tue 8/8/17 | Tue 8/8/17 |
| | | | | ScheduleOne Appointment Software |
| | | | | Curve Dental Hero |
| | | | | Dental Employees | | | | | | 4 hrs |
| | 1.8 Gauge How Team is Feeling | | | | | | | | | 48 hrs | 2 days | Wed 8/9/17 | Thu 8/10/17 |
| | | 1.8.1 Gather team for meeting to assess | | | | | | | | 40 hrs | 1 day | Wed 8/9/17 | Wed 8/9/17 |
| | | | Cristy Conner Project Sponsor | | | | | | | 8 hrs | | Wed 8/9/17 | Wed 8/9/17 |
| | | | Edward Guzinski - Project Manager | | | | | | | 8 hrs | | Wed 8/9/17 | Wed 8/9/17 |
| | | | Antonio Jones - Requirements | | | | | | | 8 hrs | | Wed 8/9/17 | Wed 8/9/17 |
| | | | Tremaine Shivers - Technical Architect | | | | | | | 8 hrs | | Wed 8/9/17 | Wed 8/9/17 |
| | | | Victor Wynn - Quality Assurance/Test Engineer | | | | | | | 8 hrs | | Wed 8/9/17 | Wed 8/9/17 |
| | | 1.8.2 Talk individually to team for feedback | | | | | | | | 16 hrs | 1 day | Thu 8/10/17 | Thu 8/10/17 |
| | | | Victor Wynn - Quality Assurance/Test Engineer | | | | | | | 8 hrs | | Thu 8/10/17 | Thu 8/10/17 |
| | | | Edward Guzinski - Project Manager | | | | | | | 8 hrs | | Thu 8/10/17 | Thu 8/10/17 |
| | 1.9 Maintenance on IT System | | | | | | | | | 40 hrs | 3 days | Fri 8/11/17 | Tue 8/15/17 |
| | | 1.9.1 Run system check on internet | | | | | | | | 2.4 hrs | 0.3 days | Fri 8/11/17 | Fri 8/11/17 |
| | | | Victor Wynn - Quality Assurance/Test Engineer | | | | | | | 2.4 hrs | | Fri 8/11/17 | Fri 8/11/17 |
| | | | 10 PCs |
| | | | Internet Modem |
| | | 1.9.2 Back up financials and customer data | | | | | | | | 5.6 hrs | 0.7 days | Fri 8/11/17 | Fri 8/11/17 |
| | | | Antonio Jones - Requirements | | | | | | | 5.6 hrs | | Fri 8/11/17 | Fri 8/11/17 |
| | | | 1 Storage and Active Directory Server |
| | | | External Backup Server |
| | | 1.9.3 Run updates for PCs | | | | | | | | 8 hrs | 0.5 days | Mon 8/14/17 | Mon 8/14/17 |
| | | | Tremaine Shivers - Technical Architect | | | | | | | 4 hrs | | Mon 8/14/17 | Mon 8/14/17 |
| | | | Victor Wynn - Quality Assurance/Test Engineer | | | | | | | 4 hrs | | Mon 8/14/17 | Mon 8/14/17 |
| | | | 10 PCs |
| | | 1.9.4 Run updates for tablets | | | | | | | | 8 hrs | 0.5 days | Mon 8/14/17 | Mon 8/14/17 |
| | | | Tremaine Shivers - Technical Architect | | | | | | | 4 hrs | | Mon 8/14/17 | Mon 8/14/17 |
| | | | Victor Wynn - Quality Assurance/Test Engineer | | | | | | | 4 hrs | | Mon 8/14/17 | Mon 8/14/17 |
| | | | 10 Tablets |
| | | 1.9.5 Update appointment software | | | | | | | | 8 hrs | 0.5 days | Tue 8/15/17 | Tue 8/15/17 |
| | | | Tremaine Shivers - Technical Architect | | | | | | | 4 hrs | | Tue 8/15/17 | Tue 8/15/17 |
| | | | Victor Wynn - Quality Assurance/Test Engineer | | | | | | | 4 hrs | | Tue 8/15/17 | Tue 8/15/17 |
| | | | ScheduleOne Appointment Software |
| | | 1.9.6 Update Ace Dental Bundle | | | | | | | | 8 hrs | 0.5 days | Tue 8/15/17 | Tue 8/15/17 |
| | | | Tremaine Shivers - Technical Architect | | | | | | | 4 hrs | | Tue 8/15/17 | Tue 8/15/17 |
| | | | Victor Wynn - Quality Assurance/Test Engineer | | | | | | | 4 hrs | | Tue 8/15/17 | Tue 8/15/17 |
| | | | Curve Dental Hero |
| Task | | Labor | | Hours x Rate | | Supplies | | Unit x Cost | | Total | | Running Total |
| 1.1.1.1 Review project plan | | Cristy Conner - Project Sponsor | | 8 hrs x $115.30 | | | | | | $922.40 | | $1,844.80 |
| | | Edward Guzinski - Project Manager | | 8 hrs x $115.30 | | | | | | $922.40 |
| 1.1.1.2 Review Budget | | Cristy Conner - Project Sponsor | | 4 hrs x $115.30 | | | | | | $461.20 | | $2,306 |
| 1.1.1.3 Finalize Requirements | | Antonio Jones - Requirements | | 4 hrs x $115.30 | | | | | | $461.20 | | $2,767.20 |
| 1.2.1.1 Determine type of computers needed | | Antonio Jones - Requirements | | 16 hrs x $115.30 | | | | | | $1,844.80 | | $6,456.80 |
| | | Tremaine Shivers - Technical Architect | | 16 hrs x $115.30 | | | | | | $1,844.80 |
| 1.2.1.2 Determine quantity of computers needed | | Antonio Jones - Requirements | | 8 hrs x $115.30 | | | | | | $922.40 | | $8,301.60 |
| | | Tremaine Shivers - Technical Architect | | 8 hrs x $115.30 | | | | | | $922.40 |
| 1.2.2.1 Determine type of tablets needed | | Antonio Jones - Requirements | | 16 hrs x $115.30 | | | | | | $1,844.80 | | $11,991.20 |
| | | Tremaine Shivers - Technical Architect | | 16 hrs x $115.30 | | | | | | $1,844.80 |
| 1.2.2.2 Determine number of tablets needed | | Antonio Jones - Requirements | | 8 hrs x $115.30 | | | | | | $922.40 | | $13,836 |
| | | Tremaine Shivers - Technical Architect | | 8 hrs x $115.30 | | | | | | $922.40 |
| 1.2.3.1 Determine type of server needed | | Antonio Jones - Requirements | | 16 hrs x $115.30 | | | | | | $1,844.80 | | $17,525.60 |
| | | Tremaine Shivers - Technical Architect | | 16 hrs x $115.30 | | | | | | $1,844.80 |
| 1.2.3.2 Determine number of servers needed | | Antonio Jones - Requirements | | 8 hrs x $115.30 | | | | | | $922.40 | | $19,370.40 |
| | | Tremaine Shivers - Technical Architect | | 8 hrs x $115.30 | | | | | | $922.40 |
| 1.2.4.1 Determine length and quanity needed | | Antonio Jones - Requirements | | 16 hrs x $115.30 | | | | | | $1,844.80 | | $21,215.20 |
| 1.2.4.2 Determine number of plenum cables needed | | Antonio Jones - Requirements | | 8 hrs x $115.30 | | | | | | $922.40 | | $23,060 |
| | | Tremaine Shivers - Technical Architect | | 8 hrs x $115.30 | | | | | | $922.40 |
| 1.2.5.1 Determine type of switches needed | | Antonio Jones - Requirements | | 16 hrs x $115.30 | | | | | | $1,844.80 | | $26,749.60 |
| | | Tremaine Shivers - Technical Architect | | 16 hrs x $115.30 | | | | | | $1,844.80 |
| 1.2.5.2 Determine number of switches needed | | Antonio Jones - Requirements | | 8 hrs x $115.30 | | | | | | $922.40 | | $28,594.40 |
| | | Tremaine Shivers - Technical Architect | | 8 hrs x $115.30 | | | | | | $922.40 |
| 1.3.1 Buy appointment software | | Antonio Jones - Requirements | | 2.4 hrs x $115.30 | | | | | | $276.72 | | $35,147.84 |
| | | Tremaine Shivers - Technical Architect | | 2.4 hrs x $115.30 | | | | | | $276.72 |
| | | | | | | ScheduleOne Appointment Software | | 10 x $600 | | $6,000 |
| 1.3.2 Buy Curve Dental Hero | | Antonio Jones - Requirements | | 2.4 hrs x $115.30 | | | | | | $276.72 | | $41,701.28 |
| | | Tremaine Shivers - Technical Architect | | 2.4 hrs x $115.30 | | | | | | $276.72 |
| | | | | | | Curve Dental Hero | | 10 x $600 | | $6,000 |
| 1.3.3 Register for anti-virus software | | Antonio Jones - Requirements | | 3.2 hrs x $115.30 | | | | | | $368.96 | | $48,439.20 |
| | | Tremaine Shivers - Technical Architect | | 3.2 hrs x $115.30 | | | | | | $368.96 |
| | | | | | | Norton Anti-Virus | | 10 x $600 | | $6,000 |
| 1.4.1.1 Research networking contractors | | Yvelisse Orana - Business Analyst | | 16 hrs x $115.30 | | | | | | $1,844.80 | | $50,284 |
| 1.4.1.2.1 Negotiate contract | | Yvelisse Orana - Business Analyst | | 16 hrs x $115.30 | | | | | | $1,844.80 | | $57,888.80 |
| | | Network Contractors | | 72 hrs x $80 | | | | | | $5,760 |
| 1.4.1.2.2 Sign Contract | | Cristy Conner - Project Sponsor | | 4 hrs x $115.30 | | | | | | $461.20 | | $58,350 |
| 1.4.1.2.3 Schedule networking install | | Antonio Jones - Requirements | | 4 hrs x $115.30 | | | | | | $461.20 | | $59,272.40 |
| | | Tremaine Shivers - Technical Architect | | 4 hrs x $115.30 | | | | | | $461.20 |
| 1.4.1.2.4 Install network gear | | Tremaine Shivers - Technical Architect | | 8 hrs x $115.30 | | | | | | $922.40 | | $61,117.20 |
| | | Victor Wynn - QA/Test Engineer | | 8 hrs x $115.30 | | | | | | $922.40 |
| | | Network Contractors | | 72 hrs x $80 | | | | | | Included |
| 1.4.2.1 Negotiate contract | | Yvelisse Orana - Business Analyst | | 16 hrs x $115.30 | | | | | | $1,844.80 | | $62,962 |
| 1.4.2.2 Sign contract | | Cristy Conner - Project Sponsor | | 8 hrs x $115.30 | | | | | | $922.40 | | $63,884.40 |
| 1.4.3.1 Schedule install | | Edward Guzinski - Project Manager | | 8 hrs x $115.30 | | | | | | $922.40 | | $64,806.80 |
| 1.4.3.2 Conduct install | | Tremaine Shivers - Technical Architect | | 8 hrs x $115.30 | | | | | | $922.40 | | $66,651.60 |
| | | Victor Wynn - QA/Test Engineer | | 8 hrs x $115.30 | | | | | | $922.40 |
| | | Network Contractors | | 72 hrs x $80 | | | | | | Included |
| 1.5.1.1 Connect PCs to wireless network | | Victor Wynn - QA/Test Engineer | | 16 hrs x $115.30 | | | | | | $1,844.80 | | $79,346.40 |
| | | Network Contractors | | 72 hrs x $80 | | | | | | Included |
| | | | | | | PC | | 10 x $1,000 | | $10,000 |
| | | | | | | WiFi Extender | | 2 x $300 | | $600 |
| | | | | | | Internet Modem | | 1 x $250 | | $250 |
| 1.5.1.2 Install appointment software | | Tremaine Shivers - Technical Architect | | 2.4 hrs x $115.30 | | | | | | $276.72 | | $79,899.84 |
| | | Victor Wynn - QA/Test Engineer | | 2.4 hrs x $115.30 | | | | | | $276.72 |
| | | Network Contractors | | 72 hrs x $80 | | | | | | Included |
| | | | | | | ScheduleOne Appointment Software | | 10 x $600 | | Included |
| | | | | | | PC | | 10 x $1,000 | | Included |
| 1.5.1.3 Install Curve Dental Hero | | Tremaine Shivers - Technical Architect | | 2.4 hrs x $115.30 | | | | | | $276.72 | | $80,453.28 |
| | | Victor Wynn - QA/Test Engineer | | 2.4 hrs x $115.30 | | | | | | $276.72 |
| | | Network Contractors | | 72 hrs x $80 | | | | | | Included |
| | | | | | | Curve Dental Hero | | 10 x $600 | | Included |
| | | | | | | PC | | 10 x $1,000 | | Included |
| 1.5.1.4 Install anti-virus software | | Tremaine Shivers - Technical Architect | | 3.2 hrs x $115.30 | | | | | | $368.96 | | $81,191.20 |
| | | Victor Wynn - QA/Test Engineer | | 3.2 hrs x $115.30 | | | | | | $368.96 |
| | | Network Contractors | | 72 hrs x $80 | | | | | | Included |
| | | | | | | Norton Anti-Virus | | 10 x $600 | | Included |
| | | | | | | PC | | 10 x $1,000 | | Included |
| 1.5.2.1 Connect tablets to wireless network | | Tremaine Shivers - Technical Architect | | 8 hrs x $115.30 | | | | | | $922.40 | | $87,113.60 |
| | | Network Contractors | | 72 hrs x $80 | | | | | | Included |
| | | | | | | WiFi Extender | | 2 x $300 | | Included |
| | | | | | | Tablets | | 10 x $500 | | $5,000 |
| 1.5.2.2 Install appointment software | | Tremaine Shivers - Technical Architect | | 3.2 hrs x $115.30 | | | | | | $368.96 | | $87,482.56 |
| | | Network Contractors | | 72 hrs x $80 | | | | | | Included |
| | | | | | | ScheduleOne Appointment Software | | 10 x $600 | | Included |
| | | | | | | Tablets | | 10 x $500 | | Included |
| 1.5.2.3 Install Curve Dental Hero | | Tremaine Shivers - Technical Architect | | 2.4 hrs x $115.30 | | | | | | $276.72 | | $87,759.28 |
| | | Network Contractors | | 72 hrs x $80 | | | | | | Included |
| | | | | | | Curve Dental Hero | | 10 x $600 | | Included |
| | | | | | | Tablets | | 10 x $500 | | Included |
| 1.5.2.4 Install anti-virus software | | Tremaine Shivers - Technical Architect | | 2.4 hrs x $115.30 | | | | | | $276.72 | | $88,036 |
| | | Network Contractors | | 72 hrs x $80 | | | | | | Included |
| | | | | | | Norton Anti-Virus | | | | Included |
| | | | | | | Tablets | | 10 x $500 | | Included |
| 1.6.1 Add a cleint into appointment software | | Victor Wynn - QA/Test Engineer | | 2.4 hrs x $115.30 | | | | | | $276.72 | | $88,312.72 |
| | | | | | | ScheduleOne Appointment Software | | 10 x $600 | | Included |
| | | | | | | PC | | 10 x $1,000 | | Included |
| | | | | | | Tablets | | 10 x $500 | | Included |
| 1.6.2 Verify that you can find the newly added appointment | | Victor Wynn - QA/Test Engineer | | 2.4 hrs x $115.30 | | | | | | $276.72 | | $88,589.44 |
| | | | | | | ScheduleOne Appointment Software | | 10 x $600 | | Included |
| | | | | | | PC | | 10 x $1,000 | | Included |
| | | | | | | Tablets | | 10 x $500 | | Included |
| 1.6.3 Evaluate Curve Dental Hero by locating insurance information | | Victor Wynn - QA/Test Engineer | | 3.2 hrs x $115.30 | | | | | | $368.96 | | $88,958.40 |
| | | | | | | Curve Dental Hero | | 10 x $600 | | Included |
| | | | | | | PC | | 10 x $1,000 | | Included |
| | | | | | | Tablets | | 10 x $500 | | Included |
| 1.7.1 Build training material | | Antonio Jones - Requirements | | 16 hrs x $115.30 | | | | | | $1,844.80 | | $96,492.80 |
| | | Tremaine Shivers - Technical Architect | | 16 hrs x $115.30 | | | | | | $1,844.80 |
| | | Victor Wynn - QA/Test Engineer | | 16 hrs x $115.30 | | | | | | $1,844.80 |
| | | | | | | Microsoft PowerPoint | | 1 x $2,000 | | $2,000 |
| | | | | | | PC | | 10 x $1,000 | | Included |
| 1.7.2 Set up training environent | | Antonio Jones - Requirements | | 4 hrs x $115.30 | | | | | | $461.20 | | $97,876.40 |
| | | Tremaine Shivers - Technical Architect | | 4 hrs x $115.30 | | | | | | $461.20 |
| | | Victor Wynn - QA/Test Engineer | | 4 hrs x $115.30 | | | | | | $461.20 |
| | | | | | | PC | | 10 x $1,000 | | Included |
| 1.7.3 Schedule training | | Edward Guzinski - Project Manager | | 4 hrs x $115.30 | | | | | | $461.20 | | $99,448.80 |
| | | Dental Employees | | 4 hrs x $277.8 | | | | | | $1,111.20 |
| 1.7.4.1 Run employees through training videos on appointment software | | Antonio Jones - Requirements | | 8 hrs x $115.30 | | | | | | $922.40 | | $102,593.60 |
| | | Dental Employees | | 8 hrs x $277.8 | | | | | | $2,222.40 |
| | | | | | | Microsoft PowerPoint | | 1 x $2,000 | | Included |
| | | | | | | Training Video | | N/A | | N/A |
| | | | | | | PC | | 10 x $1,000 | | Included |
| 1.7.4.2 Let employees test drive appointment software | | Tremaine Shivers - Technical Architect | | 8 hrs x $115.30 | | | | | | $922.40 | | $106,660.80 |
| | | Victor Wynn - QA/Test Engineer | | 8 hrs x $115.30 | | | | | | $922.40 |
| | | Dental Employees | | 8 hrs x $277.8 | | | | | | $2,222.40 |
| | | | | | | ScheduleOne Appointment Software | | 10 x $600 | | Included |
| | | | | | | PC | | 10 x $1,000 | | Included |
| 1.7.4.3 Run employees through training videos on Curve Dental Hero | | Tremaine Shivers - Technical Architect | | 8 hrs x $115.30 | | | | | | $922.40 | | $110,728 |
| | | Victor Wynn - QA/Test Engineer | | 8 hrs x $115.30 | | | | | | $922.40 |
| | | Dental Employees | | 8 hrs x $277.8 | | | | | | $2,222.40 |
| | | | | | | Training Video | | N/A | | N/A |
| | | | | | | PC | | 10 x $1,000 | | Included |
| 1.7.4.4 Let employees test drive Curve Hero | | Tremaine Shivers - Technical Architect | | 4 hrs x $115.30 | | | | | | $461.20 | | $112,761.60 |
| | | Victor Wynn - QA/Test Engineer | | 4 hrs x $115.30 | | | | | | $461.20 |
| | | Dental Employees | | 4 hrs x $277.8 | | | | | | $1,111.20 |
| | | | | | | Curve Dental Hero | | 10 x $600 | | Included |
| | | | | | | PC | | 10 x $1,000 | | Included |
| 1.7.4.5 Regroup for questions on both softwares | | Tremaine Shivers - Technical Architect | | 4 hrs x $115.30 | | | | | | $461.20 | | $114,795.20 |
| | | Victor Wynn - QA/Test Engineer | | 4 hrs x $115.30 | | | | | | $461.20 |
| | | Dental Employees | | 4 hrs x $277.8 | | | | | | $1,111.20 |
| | | | | | | Curve Dental Hero | | 10 x $600 | | Included |
| | | | | | | ScheduleOne Appointment Software | | 10 x $600 | | Included |
| 1.8.1 Gather team for meeting to assess changes | | Cristy Conner - Project Sponsor | | 8 hrs x $115.30 | | | | | | $922.40 | | $119,407.20 |
| | | Edward Guzinski - Project Manager | | 8 hrs x $115.30 | | | | | | $922.40 |
| | | Antonio Jones - Requirements | | 8 hrs x $115.30 | | | | | | $922.40 |
| | | Tremaine Shivers - Technical Architect | | 8 hrs x $115.30 | | | | | | $922.40 |
| | | Victor Wynn - QA/Test Engineer | | 8 hrs x $115.30 | | | | | | $922.40 |
| 1.8.2 Talk individually to team for feedback | | Edward Guzinski - Project Manager | | 8 hrs x $115.30 | | | | | | $922.40 | | $121,252.00 |
| | | Victor Wynn - QA/Test Engineer | | 8 hrs x $115.30 | | | | | | $922.40 |
| 1.9.1 Run system check on internet | | Victor Wynn - QA/Test Engineer | | 2.4 hrs x $115.30 | | | | | | $276.72 | | $121,528.72 |
| | | | | | | Internet Modem | | 1 x $250 | | Included |
| | | | | | | PC | | 10 x $1,000 | | Included |
| 1.9.2 Back up financial data and customer records | | Antonio Jones - Requirements | | 5.6 hrs x $115.30 | | | | | | $645.68 | | $128,174.40 |
| | | | | | | Storage and Active Directory Server | | 1 x $1,000 | | $1,000 |
| | | | | | | External Backup Server | | 1 x $5,000 | | $5,000 |
| 1.9.3 Run updates for PCs | | Tremaine Shivers - Technical Architect | | 4 hrs x $115.30 | | | | | | $461.20 | | $129,096.80 |
| | | Victor Wynn - QA/Test Engineer | | 4 hrs x $115.30 | | | | | | $461.20 |
| | | | | | | PC | | 10 x $1,000 | | Included |
| 1.9.4 Run updates for tablets | | Tremaine Shivers - Technical Architect | | 4 hrs x $115.30 | | | | | | $461.20 | | $130,019.20 |
| | | Victor Wynn - QA/Test Engineer | | 4 hrs x $115.30 | | | | | | $461.20 |
| | | | | | | Tablets | | 10 x $500 | | Included |
| 1.9.5 Update appointment software to latest version | | Tremaine Shivers - Technical Architect | | 4 hrs x $115.30 | | | | | | $461.20 | | $130,941.60 |
| | | Victor Wynn - QA/Test Engineer | | 4 hrs x $115.30 | | | | | | $461.20 |
| | | | | | | ScheduleOne Appointment Software | | 10 x $600 | | Included |
| 1.9.6 Update Curve Dental Hero to latest version | | Tremaine Shivers - Technical Architect | | 4 hrs x $115.30 | | | | | | $461.20 | | $131,864 |
| | | Victor Wynn - QA/Test Engineer | | 4 hrs x $115.30 | | | | | | $461.20 |
| | | | | | | Curve Dental Hero | | 10 x $600 | | Included |
| | | | | | | X-Ray Machine | | 1 x $8,136 | | $8,136 | | $140,000 |