BMGT 487 Individual deliverable
Work Breakdown Structure (WBS)
|
Task Name |
Duration |
Start |
Finish |
|
Diesel Truck Project |
|
|
|
|
Planning |
10 days |
Fri 6/9/17 |
Thu 6/22/17 |
|
Develop Project Charter |
3 days |
Thu 6/22/17 |
Fri 6/24/17 |
|
Create Management Plan |
3 days |
Thu 6/22/17 |
Fri 6/24/17 |
|
Set Goals |
2 days |
Fri 6/23/17 |
Mon 6/26/17 |
|
Perform Research |
10 days |
Mon 6/26/17 |
Fri 7/7/17 |
|
Scope documentation |
4 days |
Fri 7/7/17 |
Wed 7/12/17 |
|
Scope approval |
23 days |
Sat 7/8/17 |
Tue 8/8/17 |
|
Reviews and approves Deliverables |
2 days |
Wed 8/9/17 |
Thu 8/10/17 |
|
Documents, test, and train efforts related to project plan |
223 days |
6/9/17 |
4/17/18 |
|
Conducts risk analysis |
5 days |
Mon 8/13/17 |
Fri 8/17/17 |
|
Review of overall Plan |
10 days |
Fri 8/18/17 |
Thu 8/31/17 |
|
System Development |
35 days |
Tue 7/11/17 |
Mon 8/28/17 |
|
Kick off Meeting |
3 days |
Tue 7/11/17 |
Thu 7/13/17 |
|
Architecture |
10 days |
Thu 7/13/17 |
Wed 7/26/17 |
|
Function |
10 days |
Thu 7/13/17 |
Wed 7/26/17 |
|
Interface |
10 days |
Mon 7/24/17 |
Fri 8/4/17 |
|
Subsystem |
10 days |
Fri 8/4/17 |
Thu 8/17/17 |
|
Component |
10 days |
Fri 8/4/17 |
Thu 8/17/17 |
|
Model |
20 days |
Fri 8/4/17 |
Thu 8/31/17 |
|
Requirements analysis |
30 days |
Fri 8/25/17 |
Mon 9/25/17 |
|
Documentation |
30 days |
Fri 8/25/17 |
Mon 9/25/17 |
|
final approval |
35 days |
Thu 8/31/17 |
Wed 10/18/17 |
|
Prototype |
59 days |
Mon 10/16/17 |
Wed 1/3/18 |
|
|
|
|
|
|
Paper prototype |
2 days |
Mon 10/16/17 |
Wed 10/18/17 |
|
Virtual Prototype |
3 days |
Wed 10/18/17 |
Fri 10/20/17 |
|
Procurement |
40 days |
Wed 10/20/17 |
Tues/12/17 |
|
Assembly |
15 days |
Wed 10/18/17 |
Tues 11/7/17 |
|
Testing |
15 days |
Tues 11/7/17 |
Mon 11/27/17 |
|
quality control inspection |
5 days |
Tue 11/7/17 |
Mon 11/13/17 |
|
laboratory testing |
10 days |
Mon 11/13/17 |
Fri 11/24/17 |
|
Documentation |
5 days |
Mon 11/13/17 |
Fri 11/17/17 |
|
Review |
5 days |
Mon 11/13/17 |
Fri 11/17/17 |
|
Integration |
98 days |
Wed 10/18/17 |
Fri 3/2/18 |
|
Develop Project Charter |
5 days |
Mon 10/18/17 |
Fri 10/22/17 |
|
Develop Management Plan |
5 days |
Mon 10/18/17 |
Fri 10/22/17 |
|
8-12 vehicles |
40 days |
Wed 10/20/17 |
Tue 12/12/17 |
|
Testing |
90 days |
Wed 10/20/17 |
Tue 2/20/18 |
|
Maintenance |
7 days |
Wed 10/25/17 |
Thu 11/2/17 |
|
Review |
1 day |
Wed 10/25/17 |
Wed 10/25/17 |
|
documentation |
1 day |
Wed 10/25/17 |
Wed 10/25/17 |
|
final test |
5 days |
Fri 3/2/18 |
Tue 3/6/18 |
|
Close project |
1 day |
Tue 3/6/18 |
Tue 3/6/18 |
|
recommendations |
2 days |
Wed 3/7/18 |
Thu 3/8/18 |
|
Testing |
1 day |
Thu 3/8/18 |
Thu 3/8/18 |
|
Laboratory on Wheels |
5 days |
Thu 3/8/18 |
Wed 3/14/18 |
|
Vehicles to determine |
5 days |
Wed 3/14/18 |
Tue 3/20/18 |
|
research verification |
8 days |
Tue 3/20/18 |
Thu 3/29/18 |
|
road testing |
5 days |
Thu 3/29/18 |
Wed 4/4/18 |
|
procedure development |
10 days |
Thu 3/29/18 |
Wed 4/11/18 |
|
plan review |
5 days |
Wed 4/11/18 |
Tue 4/17/18 |
|
instrumentation design |
15 days |
Tue 11/14/17 |
Mon 12/4/17 |
|
instrumentation RFP |
21 days |
Wed 11/8/17 |
Wed 12/6/17 |
|
instrumentation acquisition |
30 days |
Mon 10/30/17 |
Fri 12/8/17 |
|
documentation |
8 days |
Mon 10/30/17 |
Wed 11/8/17 |
|
Review |
2 days |
Fri 12/8/17 |
Mon 12/11/17 |