Learning Team: Project Costing CMGT/410

profiledridthwaye2
copy_of_copy_of_project_baseline2.xlsx

riordan-team_project-week4_0

Task Name Duration Start Date End Date Predecessors % Complete Status Assigned To Comments Fixed Cost Fixed Cost Accrual Total Cost Baseline Variance Actual Remaining Budget Cost Budget Work
HR System Estimated cost 166d 05/22/17 01/08/18 0% IT Manager HR System estimated cost will be 100,000.00 for the project. $100000 PRORATED $111940 $100000 $11940 $115000 -$3060
Finalization of Project 1d 01/08/18 01/08/18 0% Project Manager $0 PRORATED $2240 $2000 $240 $2300 -$60 $30 0.5
Meeting 1d 01/08/18 01/08/18 0% HR Manager, IT Manager, Project Manager $0 PRORATED $1600 $1200 $400 $1677 -$77 $20 0.5
Meeting Room A 0.75d 06/05/17 06/05/17 0% IT Team $250 PRORATED $5220 $5300 -$80 $5516 -$296 $20 0.5
Define problem 0.75d 06/05/17 06/05/17 0% Project Manager $1410 PRORATED $3370 $3300 $70 $3270 $100 $20 0.5
Discussions on documents 0.75d 06/05/17 06/05/17 0% HR Manager, IT Manager, Project Manager $0 PRORATED $360 $360 $0 $390 -$30 $430 0.5
Checking current system 5d 06/05/17 06/09/17 0% Testing Team $30000 PRORATED $62805 $62800 $5 $6210 $56595 $25 0.5
Analyzing the problem 5d 06/05/17 06/09/17 0% IT Manager, Project Manager $10000 PRORATED $15600 $15400 $200 $15399 $201 $34 0.5
Interview users 3d 06/05/17 06/07/17 0% Project Manager $15000 PRORATED $16920 $17000 -$80 $16789 $131 $21 0.5
Gathering Information 1d 06/05/17 06/05/17 0% Project Team $10000 PRORATED $15240 $15000 $240 $14000 $1240 $32 0.5
Report to Stakeholders 1d 06/05/17 06/05/17 0% $5000 PRORATED $5000 $5000 $0 $4700 $300 $45 0.5
Designing Phase 10d 06/05/17 06/16/17 0% Project Manager $50000 PRORATED $67760 $67700 $60 $67555 $205 $23 0.5
Design Task 1 10d 06/05/17 06/16/17 0% Project Team $0 PRORATED $2400.0000000000000 $2400 $0 $2800 -$400 $76 0.5
Design Task 2 10d 06/05/17 06/16/17 0% Project Team $0 PRORATED $2400.0000000000000 $2350 $50 $2550 -$150 $23 0.5
Developing and Implementationn 20d 08/07/17 09/01/17 0% Project Team $35000 PRORATED $44630 $44500 $130 $44690 -$60 $34 0.5
Program Task 1 10d 08/07/17 08/18/17 0% Project Team $0 PRORATED $2400.0000000000000 $2500 -$100 $2700 -$300 $68 0.5
Program Task 2 10d 08/21/17 09/01/17 16 0% Project Team $0 PRORATED $2400.0000000000000 $2450 -$50 $2590 -$190 $34 0.5
Data Migration 20d 06/19/17 07/14/17 0% Project Manager $0 PRORATED $12800 $12000 $800 $11607 $1193 $44 0.5
Testing Phase 15d 07/17/17 08/04/17 0% Testing Team $0 PRORATED $4860 $4900 -$40 $5000 -$140 $21 0.5
Testing the equipment 8d 07/17/17 07/26/17 0% Testing Team $0 PRORATED $960 $800 $160 $850 $110 $10 0.5
Test Task 1 15d 07/17/17 08/04/17 0% Testing Team $0 PRORATED $1800 $2000 -$200 $2190 -$390 $80 0.5
Test 2--Software 10d 07/24/17 08/04/17 0% Testing Team $0 PRORATED $1200.0000000000000 $1250 -$50 $1230 -$30 $30 0.5
Training user guide 0 12/18/17 12/18/17 0% Project Team $5000 PRORATED $5000 $4000 $1000 $3000 $2000 $33 0.5
50 copies of the user guide 0 12/18/17 12/18/17 0% HR Admin $0 PRORATED $0 $5 -$5 $0 $0 $34 0.5
Train end user 0 12/18/17 12/20/17 0% HR Admin $0 PRORATED $600.0000000000000 $650 -$50 $690 -$90 $26 0.5

Comments

Sheet1

Task Name Duration Start Date End Date Predecessors % Complete Status Assigned To Comments Fixed Cost Fixed Cost Accrual Total Cost Baseline Variance Actual Remaining Budget Cost Budget Work
HR System Estimated cost 166d 05/22/17 01/08/18 0% IT Manager HR System estimated cost will be 100,000.00 for the project. $100000 PRORATED $111940 $0 $111940 $0 $111940 $0 0.0h
Finalization of Project 1d 01/08/18 01/08/18 0% Project Manager $0 PRORATED $2240 $0 $2240 $0 $2240 $0 0.0h
Meeting 1d 01/08/18 01/08/18 0% HR Manager, IT Manager, Project Manager $0 PRORATED $1600 $0 $1600 $0 $1600 $0 0.0h
Meeting Room A 0.75d 06/05/17 06/05/17 0% IT Team $250 PRORATED $5220 $0 $5220 $0 $5220 $0 0.0h
Define problem 0.75d 06/05/17 06/05/17 0% Project Manager $1410 PRORATED $3370 $0 $3370 $0 $3370 $0 0.0h
Discussions on documents 0.75d 06/05/17 06/05/17 0% HR Manager, IT Manager, Project Manager $0 PRORATED $360 $0 $360 $0 $360 $0 0.0h
Checking current system 5d 06/05/17 06/09/17 0% Testing Team $30000 PRORATED $62805 $0 $62805 $0 $62805 $0 0.0h
Analyzing the problem 5d 06/05/17 06/09/17 0% IT Manager, Project Manager $10000 PRORATED $15600 $0 $15600 $0 $15600 $0 0.0h
Interview users 3d 06/05/17 06/07/17 0% Project Manager $15000 PRORATED $16920 $0 $16920 $0 $16920 $0 0.0h
Gathering Information 1d 06/05/17 06/05/17 0% Project Team $10000 PRORATED $15240 $0 $15240 $0 $15240 $0 0.0h
Report to Stakeholders 1d 06/05/17 06/05/17 0% $5000 PRORATED $5000 $0 $5000 $0 $5000 $0 0.0h
Designing Phase 10d 06/05/17 06/16/17 0% Project Manager $50000 PRORATED $67760 $0 $67760 $0 $67760 $0 0.0h
Design Task 1 10d 06/05/17 06/16/17 0% Project Team $0 PRORATED $2400.0000000000000 $0 $2400.0000000000000 $0 $2400.0000000000000 $0 0.0h
Design Task 2 10d 06/05/17 06/16/17 0% Project Team $0 PRORATED $2400.0000000000000 $0 $2400.0000000000000 $0 $2400.0000000000000 $0 0.0h
Developing and Implementationn 20d 08/07/17 09/01/17 0% Project Team $35000 PRORATED $44630 $0 $44630 $0 $44630 $0 0.0h
Program Task 1 10d 08/07/17 08/18/17 0% Project Team $0 PRORATED $2400.0000000000000 $0 $2400.0000000000000 $0 $2400.0000000000000 $0 0.0h
Program Task 2 10d 08/21/17 09/01/17 16 0% Project Team $0 PRORATED $2400.0000000000000 $0 $2400.0000000000000 $0 $2400.0000000000000 $0 0.0h
Data Migration 20d 06/19/17 07/14/17 0% Project Manager $0 PRORATED $12800 $0 $12800 $0 $12800 $0 0.0h
Testing Phase 15d 07/17/17 08/04/17 0% Testing Team $0 PRORATED $4860 $0 $4860 $0 $4860 $0 0.0h
Testing the equipment 8d 07/17/17 07/26/17 0% Testing Team $0 PRORATED $960 $0 $960 $0 $960 $0 0.0h
Test Task 1 15d 07/17/17 08/04/17 0% Testing Team $0 PRORATED $1800 $0 $1800 $0 $1800 $0 0.0h
Test 2--Software 10d 07/24/17 08/04/17 0% Testing Team $0 PRORATED $1200.0000000000000 $0 $1200.0000000000000 $0 $1200.0000000000000 $0 0.0h
Training user guide 0 12/18/17 12/18/17 0% Project Team $5000 PRORATED $5000 $0 $5000 $0 $5000 $0 0.0h
50 copies of the user guide 0 12/18/17 12/18/17 0% HR Admin $0 PRORATED $0 $0 $0 $0 $0 $0 0.0h
Train end user 3d 12/18/17 12/20/17 0% HR Admin $0 PRORATED $600.0000000000000 $0 $600.0000000000000 $0 $600.0000000000000 $0 0.0h