PMP Critique 2000 words report ? for project management
Project Management Plan (PMP)
University of Ballarat
Team x Project Plan
Developing a customised finance application
Team Members:
Dianne Kankas
xxxxxx
Terry Goldham
Yohan Naddam
Carren Gerden
1
Contents 1.0 Executive summary
2.0 Introduction
2.1 Project Overview 4
2.2 Evolution of SPMP 4
2.3 References 5
2.4 Definition and acronyms 6
3.0 Project Organisation 7
3.1.1 Organisational charts 14
3.1.2 Project responsibilities 15
4.0 Managerial Process 20
4.1 Management Objectives and Priorities 20
4.2 Assumptions, Dependencies, and Priorities 20
4.3 Risk Management 21
4.3.1 Probability Matrix 22
4.3.2 Risk Response Plan 23
4.3.3 Risk Register 24
4.4 Technical process 26
5.0 Work to be done 27
5.1 Scope of the Project 27
5.2 Work Breakdown Structure port 27
6.0 package, Schedule and Budget 28
6.1 Work Packages 28
6.2 Resource requirements 28
7.0 Budget 30
7.1.1 Detailed Budget 30
7.1.2 Other Budget Related Information 32
8.0 Conclusion 33
9.0 Bibliography
Appendix 1- Status Report Template 34
2
Appendix 2- Gantt chart 35
Appendix 3- WBS 18
Appendix 4- Internal Organizational Chart 10
Preface
This document, the Project Management Plan (PMP) .This
project will be used for managing the project. The Project Management Plan
outlines the scope of the project, deliverables of the project, structure of the
team, roles and responsibility of each member in the team. The Managerial
and Technical Processes have been outlined as well identification of any risks.
It also outlines the schedule and budget for each resource required.
Finally, the project plan results in conclusion and recommendations for the
reference of the project team.
3
1.0 Executive summary:
The project is about creating a finance application for feed
franchise. The Management Team members have strong computer
backgrounds. The information collected from the members and the sponsor
thus assigning work to each individual. The objective of the project is:-
� Creating a customized finance application contains payroll, debtors,
creditors, BAS calculation, bank reconciliation, stock control, reports
etc...
� Application should support the multi user operating system.
� Application should be web-based, running on current browsers and the
Windows Vista operating system. .
The scope of the project which defines what the project
boundaries, the project clearly and explicitly defines what the project is to
cover and not to cover. It states hardware, deliverables, assumptions and
constraints of the project. The project gives a precise definition of the
purpose and scope of the project to ensure that both Business Partners and
Technical personnel are clear about the field of reference. It explains about
the number of phases in the project. All of which creates schedule and
budget of the project. The schedule creates a timeline for each individual
phase which has to be completed by the milestone and critical path for the
project. The schedule of the projects is breaking down of work into various
categories which also brings the budget; it creates an estimate of cost for
each phase and estimate for completion date for the project.
4
2.0 Introduction “A project is complete when it starts working for you, rather than you
working for it.”(Scott Allen). The project clearly explains the name of the
project which is a positive aspect but it doesn’t say much of the feed
franchise and the layout. The description of the project gives a clear
statement objective of the project which very much useful for the sponsor so
that he can what is the project is all about. The sponsors detail is provided in
the project which is very essential to the project. The sponsor has to know
who has been appointed as a team for this project where the sponsor has to
be informed about the team member’s details which are done in the project
.This is a positive thing in the project. Each team member’s details like phone
number and email address is provided to contact which is very useful. The
deliverables and the documentation of the project are explained in detail
which gives a clear understanding of the project. The Reference details has
been left out or omitted in the project which is a negative aspect of the
project. The project should have references where the material was taken or
cited from which gains knowledge in order for preparing the project. The
phase review of each stage is completed at each stage and asked for
acceptance for the project which is omitted in the project which is not a good
thing in the project. However this list would be more helpful if it contained a
greater number of references.
Project manager and team details:
The Project Management Plan (PMP) outlines the project.
Project team members are responsible for documentations, which show team
has worked on PMP. Through out the development cycle all team members of
the project are responsible for updating and maintaining the Plan. At weekly
team meetings will be discussed about the various issue and motivate the
group by participating in the problem solving. If there is necessary to make
changes in the plan then it is done.
5
Project Deliverables
Project Management Deliverables
The major project deliverables for the project include:
Project Management Deliverables
� A completed PMP document
� A Gantt Chart
� A completed and signed-off Design document
� A completed and signed-off Test plan document
� Test reports
� A presentation to key stakeholders
� A working prototype(s)
� A project customises finance application containing all documents and
information relating to the project for team and client to view.
Application Deliverables
� Completed Customized finance application
6
Definitions / Acronyms
The team will apply a process models to the Customised finance
application project .The prototype model were chosen for the design of the
Term Meaning
PMP
A PMP stands for Project Management Plan. A PMP is a plan for a project
Java
Programming code
PC
Personal Computer
PM
Project Manager
CI
Change Initiator
CS
Change Sponsor
WBS
Work Breakdown Structure
RPM
Risk Probability Matrix
7
application because the application is planned to be built in stages. Building
the application in stages allows testing during each stage to find bugs early
and also allows the client to approve the prototype and allows the developers
to implement changes early and more efficiently then waiting till the
application is finished.
The three phases of the prototype model have been briefly described below:
Figure 1: Prototype model
Design: This is a design phase where the planning of the prototype is
done and the design of the prototype is defined...
� Implement: After the design phase, the implement phase where the
applications coding is done for the prototype and implemented.
Testing: This phase is where prototype is checked whether it is working
properly or not and check for any bugs in the application
Design
Implement
Test
8
References Schwalbe. K. (2004). Information Technology Project Management. (3rd Ed.). Canada: Thomson
Project Smart. (2008). Project Management Success with Top 7 Best Practices, viewed
April15th, 2008, from
http://www.projectsmart.co.uk/project_management_success.html
Method123. (2003). Project Management Life Cycle Methodology, viewed April 15,
2008, from
http://www.method123.com/project-lifecycle.php
Berkun, Scott (2005). Art of Project Management. Cambridge, MA: O'Reilly Media.
Brooks, Fred (1995). The Mythical Man-Month, 20th Anniversary Edition, Adison
Wesley. I
Comninos D &, Frigenti E (2002). The Practice of Project Management - a guide to the
business-focused approach. Kogan Page.
Heerkens, Gary (2001). Project Management (The Briefcase Book Series). McGraw-Hill.
Kerzner, Harold (2003). Project Management: A Systems Approach to Planning,
Scheduling, and Controlling, 8th Ed., Wiley.
Lewis, James (2002). Fundamentals of Project Management, 2nd ed., American
Management Association.
Meredith, Jack R. and Mantel, Samuel J. (2002). Project Management: A Managerial Approach, 5th ed., Wiley.
9
3.0 Organisational
Internal Organisation
Project Manager Carren Gerden
Research Specialist
Carren Gerden
Programmer Yohan Naddam
System Analyst Tanya Gillham
Consultant Tanya Gillham
Tester Yohan Naddam
Purchasing Specialist Dianne
Marketing Specialist Dianne
Business Analyst Dianne
Documenter Tanya Gillham
Tester 1 Tanya Gillham
Tester 2 Dianne
10
Organisational Boundaries and Interfaces Overall Project Management
Client
Client
Client
Client
11
Project Responsibilities Roles Member Responsible
Role Definitions
Project Sponsor
A role of a Project Sponsor is to offer strategic business leadership and
directions. Some of the roles of a project sponsor are approve changes in
scope, approve budget variance and remove project barriers.
Project Manager
A role of the Project Manager is to determine and implement exact needs of
the client. Some of the roles of a project management team management,
communication, decision making. The project manager is responsible for
reducing risk significantly, ensuring that every significant participant has an
opportunity to express opinions and concerns.
Business Analyst
The role of the Business Analyst is to analyze the needs of the client and
stakeholder and provide solutions. Some of the roles are to find out the risks
and business case for the project.
Project Sponsor Sally Firmin
Project Manager Carren Gerden
Business Analyst Dianne
Systems Analyst Terry Goldham
Developer/ Programmer Yohan Naddam
Research Specialist Terry Goldham
Tester Yohan Naddam
Documenter Terry Goldham
Marketing Specialist Terry Goldham
Purchasing Specialist Dianne
Consultant Terry Goldham
12
System Analyst
A role of System Analyst is designing computer information systems; identify
the system requirements, modifying systems to improve the work flow or
expanding systems for new purpose.
Developer/ Programmer
The role of the programmer is to create and manage the program code.
Some of the roles of the programmer are to create prototypes and to
implement the design of the designer and test the prototypes and the final
product.
Research Specialist
The role of the Research Specialist is to research product relevant with the
project. The team are assigned to do research on similar product designed by
the competitors and collect the results to create a product to suit the
customer needs.
Tester
The role of the tester is to test the program ensure that the program is
working as expected and make appropriate changes and recheck the
program until it produces correct results.
Documenter
The role of the Documenter is to create documentation process of the entire
project. Documenter checks the integrity of the documents before the sign
off. Some of the roles of the documenter is status reports, build document,
design document, test document and ensures the standards required for the
project.
Marketing Specialist
The role of the Marketing Specialist is to create innovative ways to advertise
the products. To create an advertise campaigns for the project.
13
Purchasing Specialist
The role of the Purchasing Specialist is to research and purchase the
required equipments within the budget for the project. The purchasing
specialist is also responsible for the delivery of the product.
Consultant
The role of the Consultant is to provide expertise to the project team. The
consultant also provides new experiences and techniques.
Contacts
4.0 Management and Technical Process
Management Objectives and Priorities
Each project team member has their own roles
and responsibility and the manager’s role is to manage the objectives and
priorities of the team. Each member of the project team has been assigned
roles and the project manager should have an overall understanding on how
the project will operate. The project team will work solely on this project, if
more personal are required to meet the project deadline, Ms. Carren Gerden
will interview available personal and select the most suitable candidate for
the roles available. All the team members have to achieve their goals and
objective for the project. Each task is broken down to phases which are
Name Role Phone Number Email
Sally Firmin Project Sponsor 5327 9878 [email protected]
Dianne Kankas Team Member 9343 3736 [email protected]
Terry Goldham Team Member 8323 7982 [email protected]
Carren Gerden Team Member 8232 8755 [email protected]
Yohan Naddam Team Member 8563 5345 [email protected]
14
displayed in the Gantt chart. To identify the risk factors in the project, the
team members have to follow the procedures to identify and to resolve the
risks.
Assumptions, Dependencies and Constraints
� It is assumed the application will be need coding from various other
software’s
� It is assumed that the client will provide an adequate connection to
the internet at the installation premises once the implementation
phase is reached and suitable testing have been performed.
� It is assumed that the client will supply and be responsible for physical
maintenance of a desktop computer to act as an application/ database
server for the solution once the implementation phase of the project is
reached.
� Project Team members will be committed 10 hours per week for 7
weeks of the project which equates to 70 hours over the entire
duration of the project
� Project has a number of dependencies such as the SRS document
cannot start until the completion of the PMP document.
� The tests documents cannot start until the prototype has commenced.
� The application cannot be delivered to the client until it is completed.
� The project has to be completed within 4 months and should come in under the
budget of $180,000. If the project faces a risk that could jeopardize the deadline
of 10months.
Risk Management
Throughout the project, procedures will need to be followed in relation
to risk management. If a new threat to the project arises, the team member
is required to follow these procedures. As this document is a ‘live’ document,
15
it is important that the process below is followed so that this document can
remain up-to-date.
Risk Management Procedures
In the event of a member discovering a new threat they must notify the PM
with the following details:
F Risk
A title that describes the risk.
F Description
A description of the risk explaining how it is a risk to the project.
F Probability (High/Medium/Low)
An estimation of the chance of this risk occurring.
High – This constitutes that the risk identified is very likely to happen and it
should be tracked very carefully
Medium – Constitutes that the risk has an average chance of occurring and it
should be tracked if suspicions are aroused.
Low – Means that the risk is unlikely to happen but nevertheless it must be
identified and watched for.
F Damage (High/Medium/Low)
16
Probability Matrix
Prepared By Dianne Kankas
Dated By: 16-05-2008
Potential Risk
1. Standard Application that are bring used.
2. Feasibility of the Project.
3. Availability of the resources at the proper time.
4. Will the Application for a period of time without
any major modification or Upgradation.
5. Affordability of the project.
6. Usage of Financial resources
7. Future Sustainability of the project.
8. Competency of the Team Members
9. Risk of Over Budget
10. Risk of non completion of the project.
High Probability Medium Low Low Medium High
Impact
10 9 3 7, 8 6 1,2,4,5
17
Risk Response Plan:
1. Standard Application that are bring used.
The Application used is compatible so there
won’t any problem occurring at this area. If
problems did occur then we have to choose
other similar technologies.
2. Feasibility of the Project
The project feasibility should be positive.
3. Availability of the resources at the proper
time.
Most of the resources like software are readily
available in the market and free to download. On
the other hand supplier of the hardware has to be
sought upon the quality of the product and detail
specifications of the product from various suppliers
to keep the option open.
4. Will the application for a period of time
without any major modification or
Upgradation.
Application is created with using latest
technologies however the I.T keeps blooming , if
there is any changes need to be made or
Upgradation it can be done in the future.
5. Affordability of the project.
The forecasting of the product shows positive
signs so it is affordable for the prospective.
6. Usage of Financial resources
Ongoing of the project will take some resources
from each of the departments to complete the
project efficiently.
7. Future Sustainability of the project.
The business will pay for itself with the
developed Application
18
Risk Register Risk register identifies the risk at the beginning and during the life of the project,
their grading in terms of likelihood of occurring and seriousness of impact on the
project, initial plans for mitigating each high level risk, and subsequent results.
8. Competency of the Team Members
Check on the background of each team before
the project Charter, regular meeting will provide
insight of the project and any of the team
member breaches the contract, the project
leader can replace that person with a new
member.
9. Risk of Over Budget
Regular meeting and the status report of the
project how the project is moving on and regular
checks will ensure the progress of the project
and cost analysis will tell us whether the project
is meeting the cost goals.
10. Risk of non completion of the project
Controlling the budget of the project will also
control the project over run time.
19
It usually includes:
� Unique identifier for each risk
� Description of each risk and how it will affect the project
� Assessment of the likelihood it will occur and the possible
seriousness/impact if it does occur (low, medium, high)
� Grading of each risk according to a risk assessment table
� Responsibility of managing the risk
� An outline of proposed mitigation actions (preventative and contingency).
Risk Identification
Risk register
Rating for likelihood and seriousness for each risk
L Rated as low E Rated as extreme (used for seriousness only)
M Rated as medium NA Not assessed
H Rated as high
Grade: Combined effect of likelihood/seriousness
Seriousness
low medium high EXTREME
low E D C A
medium D C B A Likelihood
high C B A A
Recommended actions for grades of risk
Grade Risk actions
A Actions to reduce the likelihood and seriousness to be identified and implemented as soon as the project commences.
B Actions to reduce the likelihood and seriousness to be identified and appropriate actions implemented during project execution.
C Actions to reduce the likelihood and seriousness to be identified and costed for possible action if funds permit.
D No action is needed unless grading increases over time.
E No action is needed unless grading increases over time.
20
Ref: Description of risk
Likelihood
Seriousness
Grade
Actions Responsible officer
1 Inadequate funding to complete the project
M M B Re-scope project, focusing on time and resourcing
Project Manager
2 Lack of technical skills in staff H H A Develop training plan Consultant
3
Adequate Use of financial resources
M H B Creating plan to segregate resource from each of the department to the project.
Project Manager
4
Over Time M H A Create an cost analysis Project Manager, Marketing Specialist, Business Analyst
5
Over Budget
H H A
21
Project Reports
In the Project report, each have there assigned role and responsibility which
each they have to prepare each week to what is the current status of the
project. It has to be submitted every Monday 4.30 p.m. The status report
has to be either handed over to the project manager or contact via email to
send in the status report. The report will include name, role and current job,
any issues they are facing and the percentage of work has been done...
Technical Process
Methods
The project will be using the prototype approach will be used for developing
the application.
Tools and Techniques
Document Management
Microsoft Word XP will be used for all documentation creation.
Project Development
In design phase of the project we will be using Microsoft Project
to create the Gantt charts. CASE diagrams will be created using Enterprise
Architect. We will also use security software to create a secure subscription
service for the user. The CASE Tools required for the project are Use-Case
diagrams, Sequence diagrams and Class Diagrams.
Communications:-
It is a set of channels which will be used to communications between the
team and the project manager. The project team will meet every Monday at
3.30 p.m. In the Monday meeting the will be set the schedule of the week
and the deliverables and the requirements that have to be met during the
week. If any problem arises the team will discuss about the issue and the
project manager decides how the project should be progressed. Outside the
22
meeting hours the team members will be able to communicate via email and
telephone.
5.0 Work Breakdown Structure
Task ID
Task Name Start Date Finish Date Predecess ors
1. Initializing Mon 14/05/08 Wed 16/05/08
2. Assign Project Manager Mon 14/05/08 Mon 14/05/08
3. Form Project Team Mon 14/05/08 Mon 14/05/08
4. Develop Project charter Tue 15/05/08 Wed 16/05/08 3
5. Planning Thu 17/05/08 Mon 21/05/08 1
6. Develop Standard Documentation Thu 17/05/08 Fri 18/05/08
7. Define user requirements Fri 18/05/08 Fri 18/05/08
8. Define Risks and risk management approaches
Fri 18/05/08 Mon 21/05/08 7
9. Design Tue 22/05/08 Wed 23/05/08
10. Research Similar Customize finance application
Tue 22/05/08 Tue 22/05/08
11. Develop design document Wed 23/05/08 Thu 24/05/08 6
12. Develop Thu 24/05/08 Mon 29/05/08
13. Develop Prototype Thu 24/05/08 Fri 25/05/08 14. Define Project Management Related
Deliverables
Fri 25/05/08 Fri 25/05/08
15. Create Project Management Plan Mon 28/05/08 Mon 28/05/08 6
16. Scope Statement Tue 29/05/08 Tue 29/05/08 6
17. Work Breakdown Structure Wed 30/05/08 Wed 30/05/08 6
18. Implementation Thu 31/05/08 Thu 31/05/08 19. Testing Thu 31/05/08 Fri 01/06/08 20. Develop a Test Plan Thu 31/05/08 Fri 01/06/08 21. Develop a Usability Test Plan Fri 01/06/08 Fri 01/06/08 6
22. Controlling Mon 14/05/08 Mon 04/06/08
23. Team Meeting Mon 14/05/08 Mon 04/06/08
24. Risk Management Plan Review & Update Mon 14/05/08 Mon 04/06/08
25. Control Changes Mon 14/05/08 Mon 04/05/08
26. Closing Mon 04/06/08 Thu 07/06/08 1,5,9,12
27. Final Project Report Mon 04/06/08 Mon 04/06/08
23
28. Present Final Application of Project Tue 05/06/08 Tue 05/06/08
29. Produce Lesson Learnt Document Wed 06/06/08 Wed 06/06/08
30. Project completed Thu 07/06/08 Thu 07/06/08 29
Summary of Project Deliverables:-
Project Management –
Related Deliverables:
� Project Charter
� Team Contract
� Scope Statement
� WBS ( Work Breakdown Structure)
� Gantt Chart
� Responsibility Matrix Diagram
� Risk Management Plan
� Milestone Report
� Change Request
� Lesson Learned
Project Success Criteria: - Our objective is to complete the application
within the duration which is 10 months for no more than $ 180,000. The
project provide various purpose like payroll, debtors, creditors, BAS calculation,
bank reconciliation, stock control, reports etc… We must also develop a method
for capturing the benefits in the application being developed, tested, and
altered. Even if the projects take little more in cost and time the project still
will be success as it helps out various developers do coding. It will benefit the
organizations
24
Schedule
6.1 Work Packages For more information relating to work packages refer to 3.2
Resource Requirement
In this Customized Finance Application there are 11 roles which have to be
equally delegated to each member of the team. Each member is requested to
have a desktop computer, a laptop for demonstration of the prototype. Each
laptop should have Microsoft Office for documentation, IDE and Microsoft
Project for creating a work breakdown structure and Gantt chart.
6.0 Schedule
Task ID Task Name Duration Start Date Finish Date
31. Initializing 3days Mon 14/05/08 Wed 16/05/08
32. Assign Project Manager 1day Mon 14/05/08 Mon 14/05/08
33. Form Project Team 1day Mon 14/05/08 Mon 14/05/08
34. Develop Project charter 1day Tue 15/05/08 Wed 16/05/08
35. Planning 2days Thu 17/05/08 Mon 21/05/08
36. Develop Standard Documentation 1day Thu 17/05/08 Fri 18/05/08
37. Define user requirements 1day Fri 18/05/08 Fri 18/05/08
38. Define Risks and risk management approaches
2days Fri 18/05/08 Mon 21/05/08
39. Design 3days Tue 22/05/08 Wed 23/05/08
40. Research Similar Customise finance application
1day Tue 22/05/08 Tue 22/05/08
41. Develop design document 2days Wed 23/05/08 Thu 24/05/08
42. Develop 6days Thu 24/05/08 Mon 29/05/08
43. Develop Prototype 2days Thu 24/05/08 Fri 25/05/08
44. Define Project Management Related 1day Fri 25/05/08 Fri 25/05/08
25
Deliverables
45. Create Project Management Plan 1day Mon 28/05/08 Mon 28/05/08
46. Scope Statement 1day Tue 29/05/08 Tue 29/05/08
47. Work Breakdown Structure 1day Wed 30/05/08 Wed 30/05/08
48. Implementation 1day Thu 31/05/08 Thu 31/05/08
49. Testing 2days Thu 31/05/08 Fri 01/06/08
50. Develop a Test Plan 2days Thu 31/05/08 Fri 01/06/08
51. Develop a Usability Test Plan 1day Fri 01/06/08 Fri 01/06/08
52. Controlling 16days Mon 14/05/08 Mon 04/06/08
53. Team Meeting 16days Mon 14/05/08 Mon 04/06/08
54. Risk Management Plan Review & Update 16days Mon 14/05/08 Mon 04/06/08
55. Control Changes 16days Mon 14/05/08 Mon 04/05/08
56. Closing 4days Mon 04/06/08 Thu 07/06/08
57. Final Project Report 1day Mon 04/06/08 Mon 04/06/08
58. Present Final Application of Project 1day Tue 05/06/08 Tue 05/06/08
59. Produce Lesson Learnt Document 1d Wed 06/06/08 Wed 06/06/08
60. Project completed 1d Thu 07/06/08 Thu 07/06/08
7.0 Budget
Any expenses encountered by the project team will be divided between the
team members. This project is not expecting large costs however small costs
(such as printing and binding) are to be expected. Any team member that
spends money on the project should keep the receipt and give it to the PM at
the next meeting. The PM will keep a tab of all costs incurred by each
member and at the end of each semester will add up all costs of the team.
26
Each member will pay or be reimbursed accordingly, with a goal of each
team member paying an equal amount.
Detail Budget
Total Budget Summary Cost Management Total Cost
Wages $128,480.00
Software $3563.00
Hardware $5630.00
Office Supplies $2450.00
Other $1000.00
Total Cost $178,000.00
6.3.1.2Resource Sheet
Project Roles Number of Employees
Days Working (9am – 5pm)
Hourly Rate Total Duration
Project manager 1 120 days $ 130/hour $81,600.00
Programmer 1 100 days $ 77/hour $48,000.00
27
System Analyst 1 25 days $ 82/hour $13,000.00
Business Analyst 1 10 days $ 87/hour $5600.00
Research Specialists 1 10 days $ 102/hour $6800.00
Testers 2 40 days $ 72/hour $35,200.00
Documenters 1 12 days $ 74/hour $4800.00
Purchasing Specialist 1 5 days $ 82/hour $2600.00
Marketing Specialist 1 12days $ 102/hour $8160.00
Consultant 1 4 days $102 /hour $2720.00
Total Cost 78000.00
*Assumed that working hours from 9 a.m to 5 p.m
* Assumed all products purchased in Australian Dollars
Software Name Quantity Total
Windows XP Professional 4 $1,912.00
Microsoft XP office 4 $1152.00
Microsoft Project 4 ----------
Microsoft excel 1 $499.00
Java Standard 1 ------
Total Cost
28
Hardware Budget:
Software Name Quantity Total
Windows XP Professional 4 $1,912.00
Microsoft XP office 4 $1152.00
Microsoft Project 4 ----------
Microsoft Excel 1 $499.00
Java Standard 1 ------
Total Cost $3,563.00
Software Name Quantity Total
Windows XP Professional 4 $1,912.00
Microsoft XP office 4 $1152.00
Microsoft Project 4 ----------
Microsoft Excel 1 $499.00
Java Standard 1 ------
Total Cost $3,563.00
Hardware Name
Quantity
Total Item Cost
Dell OptiPlex 4 $4632.00
Dell Inspiron 1300 1 $998.00
Total Cost $5630.00
29
Supplies Budget Materials and Supplies
Total Item Cost
General office supplies $400.00
Photocopying $1000.00
Printing $1000.00
Blank CDs $50.00
Total Cost S2,450.00
Other Budget Other items Total Item costs
Deliveries $1000.00
Total Cost $1000.00
30
Conclusion:- The Project Management Plan gives an idea what the
project is about and what is on the process for a completion of a project. The
Scope pf the project is mad with assumptions creates the project plan. Even
if there is a slight change in the assumptions and the project deliverables will
change drastically. The creation of Customized financial application with the
secure subscription is to be created in the project. The over all budget for the
creation of customize finance application was $ 180,000.00, the figures
where quite under the budget. Even though the project is under budget the
project will be successful with the help of well assessed cope statement
defining the client needs.
31
Change Request Form
Change Request Form Project Name: Date Request Submitted: Submitted by: (name and contact information) Change Category: � Scope � Schedule � Cost � Technology � Other Description of change requested: Events that made this change necessary or desirable: Justification : Impact of the proposed change on: Scope: Schedule: Cost: Staffing: Risk: Other: Suggested implementation if the change request is approved: Required approvals:
Name/Title Date Approve/Reject
32
Gantt chart
33
Bibliography :
Project Smart. (2007). Project Management Success with Top 7 Best Practices. Retrieved
April15th, 2008, from
http://www.projectsmart.co.uk/project_management_success.html
Method123. (2003). Project Management Life Cycle Methodology. Retrieved April 15,
2008, from
http://www.method123.com/project-lifecycle.php
Berkun, Scott (2005). Art of Project Management. Cambridge, MA: O'Reilly Media.
Brooks, Fred (1995). The Mythical Man-Month, 20th Anniversary Edition, Adison
Wesley. I
Comninos D &, Frigenti E (2002). The Practice of Project Management - a guide to the
business-focused approach. Kogan Page.
Heerkens, Gary (2001). Project Management (The Briefcase Book Series). McGraw-Hill.
Kerzner, Harold (2003). Project Management: A Systems Approach to Planning,
Scheduling, and Controlling, 8th Ed., Wiley.
Lewis, James (2002). Fundamentals of Project Management, 2nd ed., American
Management Association.
Meredith, Jack R. and Mantel, Samuel J. (2002). Project Management: A Managerial
Approach, 5th ed., Wiley.