Business Plan

profileDonald Trump
bsbpmg522_project_planning_templates.docx

BSBPMG522 Undertake project work Project Planning Templates

Project Planning Templates BSBPMG522 Undertake project work

1.1 – Initiation and scope Templates

BSBPMG522A Undertake project work Page 2 of 23 © 2009 Innovation & Business Industry Skills Council Ltd

Part of a suite of support materials for the

BSB Business Services Training Package

IBSA_mono_40mm

Table of Contents

1.1 – Initiation and scope 1

Project brief 1

Project scope document 2

Stakeholder analysis 3

Communication plan (example) 4

Roles and responsibilities 5

Project snapshot 6

1.2 – Planning 7

Work breakdown structure 7

Project plan 8

Gantt chart 12

Activities schedule 13

Budget 14

Risk register 15

Risk assessment form 16

1.3 – Implementation 17

Change requests 17

Issues log 18

1.4 – Monitoring 19

Status update report 19

1.5 – Finalising and review 20

Budget variation report 20

Post-project review meeting 21

Handover report 22

Post-project review report 23

BSBPMG522A Undertake project work Project Planning Templates

1.1 – Initiation and scope

Project brief

Project purpose and rationale The justification and validity of the project needs to be confirmed before the project proceeds. This document is used to clarify the project purpose and justification and to gain approval to proceed to the next phase.

Project title Working title.

Project purpose Describe the purpose/need/rationale/feasibility for the project.

Background and strategic context Explain the background to the project and how it relates to the key strategic plans.

Priority Note the importance and/or urgency of the project to the organisation.

Related projects Any other projects that have been undertaken in the past, are currently underway, or planned for the future that will or may be affected by, or simply connected to, this project.

Project client/owner The person who requires the project to be undertaken.

Project sponsor The person who is providing the funds and has the ultimate authority over the project.

Project manager The person who has the responsibility to manage the project on a day-to-day basis.

Project status What has already been decided about the project? What decisions have already been made? What work has already been done in relation to the project? Any assumptions or constraints?

Special provisions Special regulations, ethical or legal considerations, etc.

Project approvals Add any signatures that are required for approval to proceed to the next phase.

Project Manager Project Sponsor

Project Client/Owner Other

Project Title:

Project Client:

Date: Version:

Project Sponsor:

Project Manager:

File Name:

Page x of y

Project scope document This template is a tool that can be used with key stakeholders to clearly define the logical boundaries of the project. Ensure that you note any requirements that are out of scope to achieve absolute clarity about what is and is not covered by this project, and to avoid the potential for problems later on.

In Scope

Out of scope (exclusions)

Assumptions

Constraints

These are items that you are definitely going to deliver/manage.

These are items that you are not responsible for – the assumption is that someone else will do them.

Exclusions are things that don’t form part of your project, but could influence whether or not you can successfully achieve your objective.

Knowledge about the project that is taken as being true or correct for the purposes of project planning.

Assumptions are circumstances and events that need to occur for the project to be successful but are outside the total control of the project team.

These could include any restrictions to the start/finish date, time, deliverable or milestone dates, budget limitations, resourcing limits, vendor restraints, legal constraints, etc.

Project Title:

Project Client:

Date: Version:

Project Sponsor:

Project Manager:

File Name:

Page x of y

Stakeholder analysis Use this template to identify areas, groups or individuals who may participate in, or are affected by, the project. Include everyone who has a vested interest. A useful question to ask is: ‘What will make this project a success for you?’

Name

Work area

Stakeholder type (client, end-user)

Impact on/by project, requirements, success criteria

Project Title:

Project Client:

Date: Version:

Project Sponsor:

Project Manager:

File Name:

Page x of y

Communication plan (example)

What

Who

Purpose

When/frequency

Type/methods

Initiation meeting

All stakeholders.

Gather information for initiation plan.

FIRST

Before project start date.

Meeting.

Distribute project initiation plan

All stakeholders.

Distribute plan to alert stakeholders of project scope and to gain buy in.

Before kick-off meeting.

Before project start date.

Project snapshot distributed via hard copy or electronically.

May be posted on project website.

Project kick-off

All stakeholders.

Communicate plans and stakeholder roles/ responsibilities.

Encourage communication among stakeholders.

At or near project start date.

Meeting.

Status reports

All stakeholders and project office.

Update stakeholders on progress of the project.

Regularly scheduled.

Weekly is recommended for small-medium projects.

Distribute status report electronically and post via website.

Team meetings

Entire project team.

Individual meetings for sub-teams as appropriate.

To review detailed plans (tasks, assignments, and action items).

Regularly scheduled.

Weekly is recommended for entire team. Weekly or bi-weekly for subteams as needed.

Meeting: detailed plan.

Sponsor meetings

Sponsor/s and Project Manager.

Update sponsor/s on status and discuss critical issues.

Seek approval for changes to project plan.

Regularly scheduled.

Recommended biweekly or monthly and also as needed when issues cannot be resolved or changes need to be made to project plan.

Meeting.

Project Title:

Project Client:

Date: Version:

Project Sponsor:

Project Manager:

File Name:

Page x of y

Roles and responsibilities It is important to identify who the major players are on the project. List the major project roles, responsibilities and the actual people involved. Add in any additional roles as required.

Role

Name/s

Responsibilities

Signature/s (if required)

Project client/owner The person who requires the project to be undertaken.

Project sponsor/project director/project board Senior management of the project. Accountable for the success of the project. Has the authority to commit resources.

Project manager Person responsible for running the project on a day-to-day basis within defined authorities for cost and schedule as agreed with the project sponsor/board.

Manager of the project manager The operational/line manager who the project manager reports to on a day-to-day basis.

Project team members Staff who will be working on the project.

Steering committee/ working party To provide advice and recommendations.

Project Title:

Project Client:

Date: Version:

Project Sponsor:

Project Manager:

File Name:

Page x of y

Project snapshot The project snapshot summarises the purpose, deliverables, stakeholders, resources, risks, interdependencies and success criteria of the project.

Project snapshot

Name of project:

Project purpose: What are the goals/objectives of this project? Why are we undertaking it? What is the problem/opportunity?

Deliverables with timeframes What, when, etc.

Stakeholders Who is the sponsor, project manager, customers, and other key groups who can impact, or be impacted by, this project.

Resources Cash flow, people, equipment, facilities, software, etc.

Risks Resource limitations, deadlines, budget, technology, legal and other constraints, etc.

Interdependencies With other projects, groups, system interfaces, etc.

Success criteria How we know we are successful.

Project Title:

Project Client:

Date: Version:

Project Sponsor:

Project Manager:

File Name:

Page x of y

1.2 – Planning

Work breakdown structure A work breakdown structure (WBS) in project management is a tool used to define and group the project’s discrete work elements (or tasks) in a way that helps organise and define the total work scope of the project. The WBS is a dynamic tool and can be revised and updated as needed by the project manager.

Level 1

Level 2

Level 3

Task 1

Sub-task 1.1

Work item 1.1.1

Work item 1.1.2

Work item 1.1.3

Sub-task 1.2

Work item 1.2.1

Work item 1.2.2

Work item 1.2.3

Task 2

Sub-task 2.1

Work item 2.1.1

Work item 2.1.2

Work item 2.1.3

Sub-task 2.2

Work item 2.2.1

Work item 2.2.2

Project Title:

Project Client:

Date: Version:

Project Sponsor:

Project Manager:

File Name:

Page x of y

Project plan The project plan is the basis for monitoring and controlling the project. All project information is consolidated to date, forming the basis for monitoring and controlling once implementation of the project commences.

Project title:

Project purpose

From project proposal – update if required.

Background and strategic context

From project proposal – update if required.

Other related projects

From project proposal – update if required.

Project objective

From project proposal – update if required.

Scope including key deliverables

From project proposal – update if required.

In scope.

Out of scope.

Assumptions

Constraints

Deliverables

Governance

From project proposal – update if required. Attach a project organisation chart and additional information on responsibilities if required.

Project client/owner

From project proposal.

Project sponsor

Project Manager

Manager of the project manager

Project team members

Key stakeholders

From project proposal – update if required. Include a more detailed stakeholder analysis in the Appendices, if required.

Schedule

Using the information you generated in the work breakdown structure, update the schedule. Include a Gantt chart or additional planning information in the Appendices.

Item

Milestone date

Responsibility

Resource and cost plan

Resource planning is where you determine what resources (people, equipment and materials) and what quantities of each should be used to perform activities. Once the resources have been determined, estimate the project costs. Include a more detailed resource and cost plan in the appendices if required.

Deliverable/milestone/phase

Resource

Cost

Project risk assessment

From project proposal – update if required. Include a more detailed risk management plan in the appendices.

Risk

Level (high/medium/low)

Management strategy

Quality management plan

Include a high level quality management plan here. Include a more detailed quality management plan in the appendices if required.

Item from WBS

Agreed quality standard

Recovery procedure

Communications and reporting

Include a high level communications plan here. Include a more detailed communications management plan in the appendices if required.

Stakeholder

Information required

When required

Format

Controls

Outline how you are going to track, monitor and report on the project. For example:

· status reports

· exception reports

· issues/risk log

· variance requests.

Appendices

List the appendices that are attached to your project plan, for example:

· stakeholder needs analysis

· work breakdown structure

· Gantt chart

· activities schedule

· budget/cash flow

· human resource planning schedule

· roles and responsibilities

· procurement schedule

· combined resources and cost schedule

· risk management plan

· quality management plan

· communications management plan.

Future related projects

Project approvals

Add any signatures that are required for approval to proceed to the next phase.

Project Manager Project Sponsor

Project Client/Owner Other

Project Title:

Project Client:

Date: Version:

Project Sponsor:

Project Manager:

File Name:

Page x of y

Gantt chart To use a Gantt chart, list the activities and tasks in column A, select an appropriate time interval (days, weeks or months), allocate the dates to columns B onwards and plot the expected time duration (total time from start to completion) under the appropriate column by selecting shading from the cells. When you wish to provide a status report, simply colour or shade in black those items that are completed or estimate the percentage complete. This will give you an immediate visual representation as to whether or not you are on schedule. You can add extra columns for assignment of responsibilities, etc.

For small projects, a Gantt chart can be created as a spreadsheet.

Activity/task

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

Legend If there are many tasks or stages in your project, you can identify them with a key or legend.

Task 1

Task 5

Task 2

Task 6

Task 3

Task 7

Task 4

Task 8

Project Title:

Project Client:

Date: Version:

Project Sponsor:

Project Manager:

File Name:

Page x of y

BSBPMG522 Undertake project work Project Planning Templates

© 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1

Page 2 of 24

Activities schedule The activities schedule is a tool used to monitor individual activities against the project plan. Information recorded on the schedule can be used when providing project status updates to stakeholders.

Phases & activities

Responsibility

Resources

Effort (hrs)

Started

Deadline

Actually completed

Comment/status

Project Title:

Project Client:

Date: Version:

Project Sponsor:

Project Manager:

File Name:

Page x of y

BSBPMG522 Undertake project work Project Planning Templates

© 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1

Page 13 of 24

Budget The project budget is a prediction of the costs associated with a particular project. These costs include labour, materials, and other resources required to complete the project.

Project Name:

Income

Inc. GST

Ex. GST

Total income

Expense

Inc. GST

Ex. GST

Subtotal

Contingency (+10%)

TOTAL

Project Title:

Project Client:

Date: Version:

Project Sponsor:

Project Manager:

File Name:

Page x of y

Risk register This template is used to record identified risks associated with your project, analyse the impact and determine resultant action to be taken.

Risk

Likelihood (H/M/L)

Impact (H/M/L)

Risk response (contingency strategies)

Responsible

Project Title:

Project Client:

Date: Version:

Project Sponsor:

Project Manager:

File Name:

Page x of y

Risk assessment form Identified risks are logged on a risk form and a copy is forwarded to the project manager.

Project details

Project Name: Project Name Project name to which the risk relates.

Project Manager: Name of the project manager responsible for mitigating the risk.

Risk details

Risk ID: Number allocated to this risk.

Raised by: Name of person who has raised the risk.

Date raised: Date of completion of this form.

Description of risk: Briefly describe the identified risk and its possible impact on the project (e.g. scope, resources, deliverables, timelines and/or budgets).

Likelihood of risk: Describe and rank the likelihood of the risk occurring (i.e. low, medium or high).

Impact of risk: Describe and rank the impact on the project if the risk occurs (i.e. low, medium or high).

Risk mitigation

Preventative actions recommended: Briefly describe any action that should be taken to prevent the risk from occurring.

Contingency actions recommended: Briefly describe any action that should be taken, should the risk occur, to minimise its impact on the project.

Approval details

Supporting documentation: Details of any supporting documentation used to substantiate this risk.

Signature: _______________________ Date: ___ /___ /____

PLEASE FORWARD THIS FORM TO THE PROJECT MANAGER

Project Title:

Project Client:

Date: Version:

Project Sponsor:

Project Manager:

File Name:

Page x of y

1.3 – Implementation

Change requests This form is used to assist with recording and management of changes in scope, time, quality or budget. The change management procedure must be negotiated with the key stakeholders prior to the sign-off of the project plan.

Change request – Project

Issued by

Item affected

Nature of change requested

Reason for change

Impact on scope

Impact on budget

Impact on schedule

Change authorised:

Yes/No

Adj. completion date:

Adj. final budget: $

Signed:

Project Manager

Signed

Sponsor

Signed

Client

Signed

Date

Date

Date

Date

Project Title:

Project Client:

Date: Version:

Project Sponsor:

Project Manager:

File Name:

Page x of y

Issues log In this template all issues are treated as risks. They should be recorded when they arise, assigned a number and responsibility, a recovery strategy or alternate path agreed, acted upon and recorded when closed.

Item

Strategy

Date logged

Date resolved

Signed:

Project Manager

Signed:

Sponsor

Signed:

Client

Signed:

Date:

Date:

Date:

Date:

Project Title:

Project Client:

Date: Version:

Project Sponsor:

Project Manager:

File Name:

Page x of y

BSBPMG522 Undertake project work Project Planning Templates

© 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1

Page 18 of 24

1.4 – Monitoring

Status update report This is one example of a status report. The preferred format should be negotiated with the project sponsor. Attach minutes of project meetings.

Status report – Project

Item

Work completed todate

Milestone date

Revised/ actual date

Budgeted cost

Revised/ actual cost

Responsible

Project Title:

Project Client:

Date: Version:

Project Sponsor:

Project Manager:

File Name:

Page x of y

BSBPMG522 Undertake project work Project Planning Templates

© 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1

Page 19 of 24

1.5 – Finalising and review

Budget variation report The project budget is a prediction of the costs associated with a particular project. These costs include labour, materials, and other resources required to complete the project.

Project name:

Income

Budget

Actual

% Variation

Total income

Expense

Budget

Actual

% Variation

Subtotal

TOTAL

Project Title:

Project Client:

Date: Version:

Project Sponsor:

Project Manager:

File Name:

Page x of y

Post-project review meeting This template provides a proposed post-project review meeting agenda, detailing items to be discussed when reviewing the overall project.

Post-Project Review Meeting – Agenda

Topic

Speaker

Time

Brief overview of project: Purpose of project, major accomplishments, comments.

Project Manager

5 mins

Review by team: Goals, objectives, deliverables, schedule, budget, and success criteria (Were they met, partially met, or missed?).

All

10 mins

What worked/what could have gone better? Some areas to consider:

· project planning

· project management

· project scheduling and tracking

· project estimating

· communication (with team, other groups/stakeholders, sponsor)

· risk management

· vendor management

· issues management

· stakeholder management

· resourcing

· users

· development approach:

· methodology

· analysis and design

· development

· testing

· implementation

· training, documentation

· technology

· overall approach to project (i.e. vendor package, staged implementation, etc.)

· production and operation support.

All

20 mins

Lessons learned

All

10 mins

Next steps

All

5 mins

Project Title:

Project Client:

Date: Version:

Project Sponsor:

Project Manager:

File Name:

Page x of y

Handover report This template summarises the project as delivered and any agreed changes to baseline scope, quality, costs and schedule.

Handover report

Initial overall objectives

Agreed changes to objectives

Final agreed deliverables

Item

Budgeted cost

Final cost

Schedule date

Final date

Total

Issues summary

Item

Strategy

Date logged

Date resolved

Documents attached

No.

Title

____________________

Project Manager

_____________________

Project Sponsor

_____________________

Project Client

Project Title:

Project Client:

Date: Version:

Project Sponsor:

Project Manager:

File Name:

Page x of y

Post-project review report This template can be used to guide you through the process of conducting a post-project review. This template can be used to document the key learning in terms of what worked well and what could have been improved.

Post-Project Review Report

Name of project:

Date and location of meeting:

Names of attendees:

1. Overview by Project Manager: Brief summary of highlights and achievements, etc.

2. Review by team of goals, objectives/deliverables and schedule as outlined in project plan Cut and paste from project plan.

Met

Missed

Partially met

Comments

Project goal/s

Objectives/deliverables

Success criteria

Schedule

Budget

3. What worked well; what could have gone better?

Worked well

Could have gone better

4. Lessons learned

5. Next steps / improvement plans

Project Title:

Project Client:

Date: Version:

Project Sponsor:

Project Manager:

File Name:

Page x of y

© 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1

Page 20 of 24