Using MS Project create a Gantt chart

profileprimecontents
pj_4_group.xlsx

Sheet1

System definition Duration Start date
1,1 Identification of organizational goals and scope 20 Days 01.Tpa.17
1.1.1 Set targets and goals 1 week
1.1.2 Defining rules and regulations 1 week
1.1.3 Organizational culture 6 days
1.2 Operational Feasibility 14 Days
1.2.1 Cost 3 days
1.2.2 Document and schedule charts and feasibility 5days
1.2.3 Technicalities and processes 2 days
1.2.4 Management decisions and reviews 2 days
1.2.5 Stakeholder lists, deliveries and processes 2days
1.3 Project Plan
1.3.1 Establishment of milestones 30 Days
1.3.2 Creation and documentation of Work Breakdown structure(WBS) 15 days
1.3.3 Resource requirments 15 days
1.3.3.1 Employees 3 days
1.3.3.2.Stakeholder supply chain 3 days
1.3.3.3 Travel expenses 3 days
1.3.3.4 Automates payment trascations 3 days
1.3.3.5 Knowledge based systems (database for deliveries 3 days
1.4 Project Team 35 Days
1.4.1 Meeting and discussion between theimmediate stakehoders
1.4.2 Outsource IT professional for efficient delivery database system
1.4.3 Develop Job descriptions and payment schemes
1.4.4 Hire two delivery personnel to improve efficiency