Assignment - Critical Path Diagram

For a project with the following tasks, durations, and task precedence data:

• Draw a Critical path diagram. Sometimes referred to as PERT or a CPM diagram. • How long will the project take to complete.

Task Description Duration (days)

Preceding Task

1 Requirements Collection 5 - 2 Screen Design 6 1 3 Report Design 6 1 4 Database Design 2 2,3 5 User Documentation 5.5 4 6 Programming 5 4 7 Testing 3 6 8 Installation 1 5,7