critical chain plan, including all the appropriate buffers.

profilerana900
singleprojects_toc_1_example_.xlsx

Crititcal Chain

1 0 2 0 3 0 4 0 5 0 6 0 7 0 8 0
A3 (4)
A5 (15)
A6 (15)
A7 (20)
A9 (18)
B3 (8)
C1 (5)
C5 (6)
D7 (9)
D9 (6)
E3 (10)
E5 (28)
F3 (20)
F5 (14)
F7 (7)
F9 (10)

Critical Chain with Buffers

0 2 0 3 0 4 0 5 0 6 0 7 0 8 0 9 0 1 0 0
A1 (4)
A5 (15)
A6 (15)
A7 (20)
A9 (18) PROJECT BUFFER (20)
B3 (8)
C1 (5)
C5 (6)
D7 (9)
D9 (6) FEED BUFFER (17)
E3 (10)
E5 (28) RES.. BUFFER (8)
F3 (20) 1 0.2941176471
F5 (14) 2.9411764706
F7 (7)
F9 (10) FEED BUFFER (25)
PROJECT BUFFER 20 DAYS , 25% OF CRITHICAL CHAIN (81 DAYS)
FEED BUFFER 17 DAYS, 50% OF FEEDERS TASKS
RESOURCES BUFFER 17 DAYS, ARRANGE WITH THE RESOURCES TO BE AVAILABLE FOR THE CRITICAL CHAIN WHEN NEEDED
FEED BUFFER 25 DAYS, 50% OF FEEDERS TASKS