Develop a drum schedule (pipeline)

profilerana900
assignment_3_1.ppt

Assignment 3

AMS 655 Project Management

Name

Develop a drum schedule (pipeline) for multiple projects by their priority and insert the capacity-constraint buffers (CCB) and drum (capacity) buffers as needed.

  • The capacity of the drum resource is 2 units.
  • The drum is resource B
  • The priority of the projects is project 1, project 2, then project 3.

~10 days

Letters (A, B, C) = resource

Numbers (8, 18, etc.) = time duration estimate at 50% probability

Project 1

Project 2

Project 3

C

6

C

15

C

18

C

8

A

18

B

28

A

4

B

6

A

5

C

6

C

15

C

18

C

8

A

18

B

28

A

4

B

6

A

5

C

6

C

15

C

8

A

4

B

6

A

5

B

6

A

18