Essential Skills for the Project Manager

A200SAM – Week 4

Review of last week

Project roles

Organisational structure

Any questions?

Pre-planning

Reminder: project lifecycle

Example of a project lifecycle:

Initiation and definition

Planning

Execution and control

Closure

Initiation and definition

Project identification

Scoping

Requirements

Stakeholders

Critical Success Factors

Objectives

Work Breakdown Structure

Project team

Scoping

“The process of establishing and agreeing with all the stakeholders what the project will involve and where its boundaries are”

Gardiner (2005)

Why you are doing the project (business need)

Strategic fit (eg preceded or followed by other projects)

Expectations of main stakeholders

Resources and budget available – people, equipment, financial parameters

Main deliverables/activities

CRITICAL SUCCESS FACTORS (CSFs)

"The limited number of areas in which results, if they are satisfactory, will ensure successful competitive performance for the organization. They are the few key areas where things must go right for the business to flourish. If results in these areas are not adequate, the organization's efforts for the period will be less than desired.“

John F Rockart, MIT Sloan Management School

Example: Farm Fresh Produce

Mission statement

"To become the number one produce store in Main Street by selling the highest quality, freshest farm produce, from farm to customer in under 24 hours on 75% of our range and with 98% customer satisfaction.“

From www.mindtools.com

Strategic objectives

The strategic objectives of Farm Fresh are to:

Gain market share locally of 25%.

Achieve fresh supplies of "farm to customer" in 24 hours for 75% of products.

Sustain a customer satisfaction rate of 98%.

Expand product range to attract more customers.

Have sufficient store space to accommodate the range of products that customers want.

TWO CSFs FOR FARM FRESH PRODUCE

Gain market share locally of 25%

Attract new customers

Achieve fresh supplies of “farm to customer” in 24 hours for 75% of products

Sustain successful relationships with local suppliers

First steps in the Planning Process

Key factors in planning projects

Scheduling

Timescales

Resources

Task dependencies

Cost

Budget setting

Allocation

Quality

Work breakdown structure

What is a work breakdown structure?

“a logical, hierarchical tree of all the tasks needed to complete a project”

Lock (2007), p165

A WBS organises tasks into a logical sequence, allowing them to be planned in time and allocated to people

WBS – diagrammatic view

WBS – task list view

Project activity

Project brief:

To build a new chicken house and run for Beryl and Gladys

Budget:

£500

Timescale:

4 weeks

Project sponsor:

Anmoal Thethi

Activity – 20 mins

A. Scoping - 5 mins

Focus on:

Requirements

Objectives

B. Work Breakdown Structure - 15 mins

- produce a WBS in diagrammatic view

- you may find using post-it notes helpful

Allocating time to activities

Once a WBS is agreed, time can be allocated to each stage/task.

How do we estimate time?

Using historical data

Based upon past experience

Time the activity

Trial run

Impact of learning

Using a probabilistic method

With uncertainty/no experience

e.g. Weighted Average technique

Weighted average technique

Based upon three estimates of duration for the activity:

Most optimistic (a)

Most likely (m)

Most pessimistic (b)

Weighted average = a + 4m + b

6

Example

a = 24 hrs (most optimistic)

m = 48 hrs (most likely)

b = 96 hrs (most pessimistic)

WA = 24 + (4x48) + 96 = 52 hrs

6

Test the weighted average technique

Choose three tasks from your WBS for constructing the new chicken house and run

For each task, agree as a group how long you think the task will take based upon your collective experience (historical data)

Next test a weighted average approach on both tasks

Basic gantt chart

MS project gantt chart

Task dependencies

Four simple questions

What can be done now?

What must you have done before that?

What can be done at the same time?

What must follow what you do now?

Activity: Identifying dependencies

Do you have task dependencies in your chicken house project?

Give each task an ID (1, 2, 3... or A, B, C...)

Identify whether each task is a predecessor for another task

Note down the ID and the relationship (FF, FS, SS, SF)

Predecessors in ms project

Predecessor task links in ms project

MS project gantt chart

Example of a network diagram

Activity boxes

Earliest start time Duration Earliest finish time
Task name and code
Latest start time Float Latest finish time

Assignment brief

Submission information

Deadline: 5th May 2017, 11:55pm

Submission via Turnitin

Draft Turnitin also available

No paper copy required

Assignment format

The assignment is in two parts:

For Part 1 you are asked to prepare a project report, for the ‘Bank Station Capacity Upgrade’, through critically evaluating the project and drawing on relevant project management theory and framework to present to your company’s board of directors for approval.

Part 2 asks you to research and reflect upon the technical and management skills required to manage projects successfully?

The coursework should be submitted as one document comprising the two questions

Please use 1.5 or double-line spacing and (preferably) Calibri/12 font

Word count and mark allocation

Part 1 – 1500 words and 80% of the marks

Part 2 – 500 words and 20% of the marks

There is a 10% word limit tolerance. Maximum/Minimum Range: 1800 to 2200 words in total

Please include the number of words used in your report on the front page of your report

Word limit excludes reference list, diagrams and appendices

Submitted as a single document, submitted to Turnitin

Assignment – Part 1

Drawing on relevant project management theory, you should critically evaluate the project, focussing your report on two of the following areas of project management, you should ensure that your report is underpinned by reference to relevant project management theory presented in academic and professional publications:

Stakeholder Management

Risk Management

Project Planning

Process for recording lessons learned

Assignment - Part 2 (500 words)

‘Using your research on project management as a starting point, reflect upon the technical and management skills required for the role of a project manager to manage the project. What technical and management skills do you think a project manager should have and how effectively they can integrate it to manage the project successfully?’

Remember to draw on project management research to support your answer.

Points to remember

All analysis and recommendations should be supported by reference to academic and professional publications

Your report should demonstrate project management theory throughout

CU Harvard referencing must be used

You must ensure you are not plagiarising other published works

Appendices should only be used to support information within the report

Assessment criteria

Note the split of marks across the 6 assessment criteria

Any questions?

Preparation for next week

Pert

PERT = Project Evaluation and Review Technique

Useful introduction to PERT:

http:// tinyurl.com/pert-toolkit

Produced by Manchester Metropolitan University Business Improvement Team

Network diagram

Try building a network diagram for the chicken house project or making a cup of tea

Refer to these slides, your reading and the MMU guide (see previous slide)

We will review the technique in two weeks’ time

Reading

Week 6 - Project planning: tools and techniques

Suggested reading

Pick a selection from the following:

Newton (2009) – chapter 6

Pinto (2013) - chapters 5 and 9

Lock (2007) – chapters 3, 5, 12 and 16

Gardiner (2005) – chapter 9