project management report

profilejiafeng1
a200sam_week_6_slides.pptx

Essential skills for the Project Manager

A200SAM ADD+VANTAGE MODULE

Review of week 5

Critical Path Analysis

Identifying activities on the critical path

Identifying activities with float

Resourcing the plan

Resource smoothing

Resource levelling

Project cost estimation

Any questions?

Risks and opportunities

Projects and risk

Projects are subject to higher levels of uncertainty for several reasons:

they are unique/one-off

project organisations are often temporary

they are about change

What are risks and opportunities?

In small groups, discuss the use of the following terms in project management:

Risks

Opportunities

Uncertainty

Risk management

Risk definitions

‘Project risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on a project objective.’

(PMI Guide to the PMBoK, 2004: 373)

‘The potential of an action or event to impact on the achievement of objectives.’

(apm.org.uk, accessed 22/2/2013)

Definitions from risk publications

‘…a threat (or opportunity) which could affect adversely (or favourably) achievement of the objectives ...’

(ICE’s RAMP Guide, 2005: 19)

‘A risk consists of a combination of the probability of a perceived threat or opportunity occurring and the magnitude of its impact on objectives.’

(Office of Government Commerce’s M_o_R, 2007: 1)

‘…an uncertain event or set of circumstances that, should it occur, will have an effect on the achievement of the project’s objectives.’

(APM’s PRAM Guide, 2004: 176)

Institution of Civil Eng – Risk Analysis and Management for Projects

MoR – Management of Risk

APM Project Risk Analysis and Management (PRAM)

Change in definitions

The view of risk management changed to incorporate positive and negative outcomes during the period 1997 to 2000

Pre-1997, risk definitions were threat-based

Post- 2000, usage embraces both threat and opportunity

‘There is increasing awareness that risk management can and should be used to minimise the negative effect of downside threat-risks, while also attempting to maximise the positive effect of upside opportunity-risks, in order to optimise achievement of objectives’

(Hillson and Murray-Webster, 2007: 6)

Most projects carry speculative risk – chance of a seizing an opportunity through (say) using new technology or running in to problems if the new technology doesn’t perform as expected.

Opportunity

‘A positive risk event that, if it occurs, will have a beneficial effect on achievement of objectives.’ (apm.org.uk, accessed 22/2/2013)

‘An opportunity can be defined as an uncertain event or set of conditions that, if it occurs, would benefit the project or business.’

(Hillson, 2003: 18)

Risk management

‘A process that allows individual risk events and overall risk to be understood and managed proactively, optimising success by minimising threats and maximising opportunities.’

(apm.org.uk, accessed 22/2/2013)

‘The objective of risk management is to minimise the negative impacts of risks on the project and to benefit from opportunities.’

(Koster, 2010: 100)

Outline of management process

Identification

Analysis

Planning

Monitoring and control

Identifying risks

Sources of risks

Risks arising from factors under the project’s control:

expertise of team and project stakeholders

management systems and processes

performance of contractors

Risks arising from factors in the wider external environment which are only controllable by decision makers elsewhere:

competitor action

changes in government policy

Risks arising from factors which are uncontrollable:

weather / climate

commodity prices

terrorism

Risk identification – Activity (10 mins)

Read the short case study

In groups of 4/5, identify all the negative and positive risks you can associate with this project

Write down your list of risks

Risk analysis

Analysing risks enables an assessment of the following features of risk:

Probability – how likely is this risk to occur?

Impact – if it does occur, what would its effect be on the project?

Trigger – what event/circumstances etc might trigger the occurrence of the risk?

Which of the risks will have the most positive or negative impact upon the project? (or upon the organisation)

IMPACT AND PROBABILITY EXAMPLE

Impact

Days to resolve or deviation in budget

Low 1 < 1 day/<£250

Low/medium 2 1-3 days/£251-1000

Medium 3 4-7 days/£1001-2000

Medium/high 4 8-12 days/£2001-4000

High 5 > 12 days/>£4000

Probability

% chance of occurring

Low 1 0-10%

Low/medium 2 11-25%

Medium 3 26-50%

Medium/high 4 51-75%

High 5 76-99%

Example – Planning a conference

Probability/impact matrix

Tool for risk prioritization

Combines the likelihood of risk occurrence with the effect the risk will have on the project objectives

Provides stakeholders with overview of risk propensity

Categorization of risks in terms of project impact/probability can be put on a scale

eg three stage (low, medium, high) or five stage (insignificant, minor, moderate, major, severe)

Probability/impact matrix example

LOW

MEDIUM

HIGH

LOW

MEDIUM

HIGH

Probability

Impact

Risk analysis – Activity (5 mins)

Using your list of negative and positive risks identified from the case study:

assess their impact and probability

plot the risks on a matrix

Risk response strategies

There are a number or risk response strategies available when planning for potential risks.

These are the main five strategies:

Avoidance

Acceptance

Sharing

Mitigation

Transfer

Risk response strategies

There are a number or risk response strategies available when planning for potential risks.

These are the main five strategies:

Avoidance – remove the source of risk

Acceptance – acknowledge and tolerate risk

Sharing – share risk through collaboration with others

Mitigation – reduce the probability or impact of the risk

Transfer – pass risk to another party (e.g. insurance)

Avoidance – e,g, avoid using a small contractor who could go bankrupt – use a large one instead

SELECTING A RESPONSE

Cost of action

Likelihood and impact of risk occurring

e.g. is it worth a charity carnival taking out insurance for £3000 guaranteeing £6000 if the carnival is rained off?

Risk planning - activity (10 mins)

Choose five risks (negative and positive) from your case study list

Working in your groups, can you consider a suitable response to five of the risks to the project you have identified?

Monitor and control risks

Risks must be managed once the project is underway

Commonly done by use of risk registers

All risks should be transferred to a risk register and be a live document

Each risk will have a risk owner

Risks and triggers should be monitored

Communication of risk status is part of management

Risk register
Risk No. Risk description Cause of risk Probability of occur-rence Impact on project Risk response plan Risk owner Date of entry

Examples of risk registers

10

Preparation for week 7

Week 7

Project methodologies

For next week, you must research one of the following project management methodologies ready to prepare and give a short group presentation on the methodology in next week’s seminar.

Waterfall

Agile

Scrum

PRINCE2

Critical chain project management

Consider (1)

This requires some more in-depth research. How will you achieve this in the time allocated?

How you will present? (i.e. PowerPoint, Flipchart poster etc.)

What examples/illustrations/models you will use to aid understanding?

Who will present?

How you will keep to time?

Consider (2)

Who will respond to any questions asked by the audience?

Ensure each group considers what questions they might ask of other groups.

Be respectful of others presenting.

Note: There will be a prize for the best group presentation (as voted for by the class)!