Essential skills for the project manager

A200SAM – Week 5

REVIEW OF THE LAST SEMINAR

Project initiation and definition

Project planning

WBS

Allocating and estimating time

Any questions?

WBS – diagrammatic view

Questions

What does the WBS help us to achieve?

Are there any drawbacks to the approach?

Project planning - 2

Activity

Using the handout worksheet, in pairs draw out the critical path for the activities.

What is the critical path for your project?

How much slack is there?

Be prepared to feedback.

Critical path analysis

Purpose

To calculate the longest sequence of dependent activities needed to complete the project

Use

Enables the PM to see the impact of delays/which activities can tolerate delays

Float highlights delay tolerance

Method

Two stages:

forward pass (earliest start)

reverse pass (latest start)

Critical path analysis

Purpose

To calculate the longest sequence of dependent activities needed to complete the project

Use

Enables the PM to see the impact of delays/which activities can tolerate delays

Float highlights delay tolerance

Method

Two stages:

Stage 1: forward pass (earliest start)

Stage 2: reverse pass (latest start)

Activity boxes/Nodes

Earliest start time (ES) Identifier number/code Earliest finish time (EF)
Float (FL) Activity descriptor
Latest start time (LS) Duration Latest finish time (LF)

Example (writing a book): organise activities

A
Write draft
B
Type manuscript
C
Create drawings
D
Design cover
E
Collate
F
Print

Earliest start time (ES) Identifier number/code Earliest finish time (EF)
Float (FL) Activity descriptor
Latest start time (LS) Duration Latest finish time (LF)

Example (writing a book): Forward pass: ES + Duration = EF

0 A 20
Write draft
20
20 B 30
Type manuscript
10
20 C 25
Create drawings
5
20 D 22
Design cover
2
30 E 36
Collate
6
36 F 41
Print
5

Earliest start time (ES) Identifier number/code Earliest finish time (EF)
Float (FL) Activity descriptor
Latest start time (LS) Duration Latest finish time (LF)

Example (writing a book): Backward pass: LF – Duration = LS

0 A 20
Write draft
0 20 20
20 B 30
Type manuscript
20 10 30
20 C 25
Create drawings
25 5 30
20 D 22
Design cover
28 2 30
30 E 36
Collate
30 6 36
36 F 41
Print
36 5 41

Earliest start time (ES) Identifier number/code Earliest finish time (EF)
Float (FL) Activity descriptor
Latest start time (LS) Duration Latest finish time (LF)

Example (writing a book): determine slack = difference between LS and ES

0 A 20
0 Write draft
0 20 20
20 B 30
0 Type manuscript
20 10 30
20 C 25
5 Create drawings
25 5 30
20 D 22
8 Design cover
28 2 30
30 E 36
0 Collate
30 6 36
36 F 41
0 Print
36 5 41

Earliest start time (ES) Identifier number/code Earliest finish time (EF)
Float (FL) Activity descriptor
Latest start time (LS) Duration Latest finish time (LF)

Activity

Using the handout worksheet, in pairs draw out the critical path for the activities.

What is the critical path for your project?

How much slack is there?

Be prepared to feedback.

GANTT CHARTS

Another way of representing scheduling information

Intuitively easier to interpret than networks

Note that:

activities are arranged from top to bottom

time is plotted to scale from left to right

activity bars begin at their earliest start time

critical activities are highlighted

(Source: Gardiner, 2005)

What next?

Resources

Costs