Weighted average technique

Most optimistic (a)

Most likely (m)

Most pessimistic (b)

Weighted average = a + 4m + b

6

Task dependencies

taskdependencies.jpg

What can be done now?

What must you have done before that?

What can be done at the same time?

What must follow what you do now?

Work Breakdown Structure – diagrammatic view

work-breakdown-structure.gif

WBS – tabular view showing activity dependencies

For more information on the purpose of a WBS see: http://www.projectsmart.co.uk/work-breakdown-structure-purpose-process-pitfalls.html