Project Risk Management

profilekiaa_p1
ip_5_example_1_2_1.pdf

MPM344- Project Risk- Phase 1IP5

Wedding Planning

Student XXXX

June XX, XXXX

TT A B L E O F A B L E O F CC O N T E N T SO N T E N T S

II .. PP R O J E C T R O J E C T OO U T L I N E U T L I N E (( I PI P 1 )1 ) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . 11

1 .1 . PP R O P O S A L R O P O S A L AA P P R O V A LP P R O V A L . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 .2 . PP R O J E C T R O J E C T DD E S C R I P T I O NE S C R I P T I O N . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 .3 . MM I L E S T O N E SI L E S T O N E S . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . .

I II I .. RR I S K I S K MM A N A G E M E N T A N A G E M E N T JJ U S T I F I C A T I O N U S T I F I C A T I O N ( I( I PP 1 )1 ) . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . 99

1 .1 . TT H E I M P O R T A N C E O F R I SH E I M P O R T A N C E O F R I S KK -- T O T H E S P O N S O R T O T H E S P O N S O R . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . 2 .2 . SS T E P S T O D E V E L O P I N G AT E P S T O D E V E L O P I N G A R I S K M A N A G E M E N T P L A NR I S K M A N A G E M E N T P L A N . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . 3 .3 . FF L O W L O W DD I A G R A M O F S T E P S F O R I A G R A M O F S T E P S F O R A A R M PR M P . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . .

I I II I I .. PP R O J E C T R O J E C T RR I S K I S K II D E N T I F I C A T I O N D E N T I F I C A T I O N ( I( I PP 1 ,1 , II PP 2 )2 ) . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . 1 21 2

11 .. HH II -- L E V E L L E V E L BB R A I N S T O R M I N G O F R A I N S T O R M I N G O F RR I S K T H A T C O U L D O C C U RI S K T H A T C O U L D O C C U R . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . 22 .. RR I S K S I S K S CC A T E G O R I Z E D WA T E G O R I Z E D W // S W O TS W O T A N A L Y I S I SA N A L Y I S I S . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . 3 .3 . SS T A K E H O L D E R S T A K E H O L D E R S && PP R O J E C T R O J E C T TT E A M U T I L I Z E D T O I D E NE A M U T I L I Z E D T O I D E N T I F Y R I S K ST I F Y R I S K S . . . . . . . .. . . . . . . .

I VI V .. PP RR O J E C T O J E C T RR I S K I S K AA S S E S S M E N T S S E S S M E N T (( I PI P 2 )2 ) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 44

11 .. TT A B L E S H O W I N G R I S K SA B L E S H O W I N G R I S K S . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22 .. RR AA N K I N G O F N K I N G O F RR I S K S S H O W I N G I S K S S H O W I N G LL I K L I H O O D A N D I K L I H O O D A N D II M P A C T M P A C T . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . .

VV .. PP R I M A R Y R I M A R Y RR I S K I S K RR E S P O N S E E S P O N S E SS T R A T E G Y T R A T E G Y (( I PI P 3 )3 ) . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . 55

11 .. MM A T R I X A T R I X S H O W I N G S H O W I N G AA S S E S S M E N T S S E S S M E N T R E P O N S E S F O R E A C H R IR E P O N S E S F O R E A C H R I S KS K . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . 2 .2 . DD E T A I L E D E T A I L E D RR I S K I S K RR E S P O N S E S F O R T H E E S P O N S E S F O R T H E R I S K SR I S K S … . . .… . . . … … … … … … … … … … … … . . .… … … … … … … … … … … … . . .

V IV I .. PP RR O J E C T O J E C T RR I S K I S K MM A N A G A M E N T A N A G A M E N T PP L A N L A N (( I PI P 44 )) . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . 66

11 .. MM O N I T O R I N G O N I T O R I N G RR I S K I S K RR E S P O N S I B I L I T Y E S P O N S I B I L I T Y MM A T R I XA T R I X . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

V I IV I I .. PP R O J E C T R O J E C T RR I S K S I S K S MM O I N I T O R I N G O I N I T O R I N G && CC O N T R O L O N T R O L PP L A N L A N ( I( I PP 44 )) . . .. . . 77

11 .. FF L O W L O W CC H A R TH A R T . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . .

V I I IV I I I .. PP R O J E C T R O J E C T RR I S KI S K SS MM I L E S T O N E SI L E S T O N E S && BB U D G E T U D G E T UU P D A T E S P D A T E S (( I PI P 55 )) .. 88

11 .. MM I L E S T O N E SI L E S T O N E S ,, BB U D G E T U P D A T EU D G E T U P D A T E . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . .

2 . C2 . C O N T I N G E N C Y O N T I N G E N C Y BB U D G E T U D G E T UU P D A T EP D A T E … … … … … … … … … … … … … … … … … … …… … … … … … … … … … … … … … … … … … …

I XI X .. PP RR O J E C T O J E C T RR I S K S I S K S CC O M M U N I C A T I O N O M M U N I C A T I O N PP L A N L A N (( I PI P 5 )5 ) . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . 99

1 .1 . PP R O J E C T R O J E C T DD I R E C T O R YI R E C T O R Y . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 .2 . MM A T R I X F O R T H E C O M M U NA T R I X F O R T H E C O M M U N I C A T I O N S P L A N I C A T I O N S P L A N 33 GG U I D E L I N E S F O R C O M M U NU I D E L I N E S F O R C O M M U N I C A T I O N S M E E T I N G S I C A T I O N S M E E T I N G S … … … .… … … . … … … … … … … … … …… … … … … … … … … …

I .I . PP R O J E C T R O J E C T OO U T L I N EU T L I N E

1. PROPOSAL /APPROVAL

Dear Sponsor: Ronald Burke,

My proposal will give you the insights of why I am seeking your approval

to being the lead Project Manager for the project of Wedding Planning. I am really

excited to take on this new venture for I know it will help add to my resume and my

future growing endeavors with your company. As proposed, clients Walter James and

Gloria Jefferies decided to take on the commitment of marriage in June of 2013 and

are the official winners of “The $50,000 Wedding Give Away Day” from our

sweepstakes raffle. I understand before the kickoff of this project I would need your

approval of your sponsorship to take on such a large project. Even though I am a new

hire under your management team of project managers, this proposal is to declare my

ability and desire to taking on the Wedding Planning Project with delight, but first let

me explain in detail of why I strongly feel this way.

May 7, 2011 was one of the best days of my life….For it was my Wedding

Day! This is the year my husband and I promised ourselves and loved ones that we

would finally have a wedding which was on our 10th Year Anniversary. Besides that,

we felt that since our family is now complete they could participate in the ceremony as

well. Well we did just that. Our little girl was our mini bride/flower girl, our middle

son was the ring bearer and our older son actually walked me down the aisle, which

was very emotional, since my uncle passed away last year and was suppose to walk

me since he was just like a father to me.

However, I never knew until this project that the risks involved with an individual

planning their own wedding could be just as stressful, if not more, and loaded with a

ton of risks, than if you were to hire a project manager/planner to do it all. As a

matter-of-fact, I personally just experienced how substantial those risks and stresses

could be…and yes it was experienced, the hard way- without a risk plan.

I was a bride on a limited budget and decided to have my wedding on a cruise in

the Bahamas with 6 months of planning. Well, that idea fell through after the 4th

month and the plans had to change because the most important guests such as our

parents, siblings, etc. were not able to get on board with us for unseen circumstances.

My immediate family and my photographer were already booked for the cruise and at

this point we could not cancel. So to sum up the situation: our wedding funds were

tied up on a Carnival Cruise Ship that only my family of 5 plus my photographer

would be able to attend.

Instead of panicking, I decided to use the $ 2,000 dollar reserve funds that we set

aside as “spending money” on the cruise, to have a simple ceremony with 30 guests in

Orlando, FL the weekend week prior to our departure. I had two months to make the

plans. As anyone can imagine, those were the busiest 2 months of my life. The details

were mind boggling, the risks were endless, resources were many, the groom did not

disappear, as I’m sure he wanted to at times, and everything was beautiful in the end

for we finally had our 25 thousand dollar wedding on a 2 thousand dollar budget!

Afterwards we enjoyed our week of vacation in beautiful Orlando, Fl home of Mickey

Mouse, and at the end of the week we embarked on the ship and vacationed for 3 more

days. When it was all over, I can honestly say that I was extremely happy with the

results, for it was all worth it in the end.

I had previously told a friend of mine that if I could execute my wedding on

such short notice and budget that I will be able to plan anything and project

management was definitely my talent and calling. As a matter-of- fact, planning

weddings as a career has always been a life-long dream, and my purpose for my

education in project management. Therefore this proposal to lead the project of

“Wedding Planning” is being written with a little experience but a whole lot of zeal!

Mr. Burke thanks in advance for your consideration for approval of this proposal.

Respectfully Yours,

Jane Doe Project Manager

1. PROJECT DESCRIPTION

This risk management plan will identify risks that are associated with planning a

wedding. The planning of a wedding involves a lot of detail that must be thoroughly

planned out. There are a lot of milestones involved and sometimes can seem

overwhelming even for the most experienced project planner. Although similar, there

are no two weddings ever alike because everyone is different with different likes and

dislikes; this could make the planning of a wedding a risk all by itself. That is why it is

important for the project manager to be well -rounded and diverse because there are

simply no limits to where a wedding can take place. A wedding can be planned on top

of a mountain or at the bottom of a sea. Most of the time it is a preference, illusion or a

dream that the project manager is expected to make realistic… on schedule and most

of all within budget. For example it would not be ideal to go to a bride and tell her that

her wedding date needs to change or more money is needed to accommodate random

expenses that were never allotted for. This is just the tipping of the ice-burg when a

project manager is in charge of planning a wedding. However, this process does not

get any easier when one plans their own wedding as discussed earlier in section 1 (the

proposal/approval section).

2. MILESTONES

a. Flowers

b. Cake and Catering

c. Music Getting Marriage License

d. Name Change on all cards (i.e. social security, credit, health etc.)

e. Preparing A Budget

f. Guest List

g. Invitations

h. Vendors

i. The Bride

j. The Groom

k. Wedding Party

l. Hair & Beauty

m. Ceremony

n. Reception

o. Honey moon

p. Photo & Video

q. Rehearsal Dinner

r. The Wedding day

s. Thank you gifts/ cards

II. RISK MANAGEMENT JUSTIFICATION

1. THE IMPORTANCE OF RISK- TO THE SPONSOR

Dear Ronald Burke,

Thank you for your approval. I wanted to write you a letter to inform you of the

importance of having a risk management plan (RMP) in place for the current wedding planning

project. Since my wedding it has opened my eyes to know that the risk involved in planning a

wedding is crucial to the success of it. Our current client/family is depending on our expertise to

making their dreams come true and we do not want to let them down. First of all, to identify

what a risk is, I would consider it as anything that could potential stop, tamper or change the

progression of the project. This could be a temporal stagnation or it could be permanent. We do

not want anything to cause our clients wedding from taking place. This could be devastating to

our client’s future and even though we are sponsoring it, our reputation is on the line. Therefore

this is my rationale for having a risk plan in place for this project.

Through the complete lifecycle of this project, the PRM can also help us stay on schedule. If

we have a plan for mitigating the risk, when it occurs we can continue plans without having to

cancel them. Risks are real. It is better to be prepared for them than not to be. A RMP gives us

this outlet to have changes already on the table before they can occur. Some risks are much

higher than others and must be respected as such. There are risks that maybe very rare and never

happen. In either case it is still better to be prepared. For example having the wedding outside in

June may be a risk of the weather conditions being either too hot or raining. In this case, we

would need to consider a back up location. Think about it, how can we promise our client a

wedding of their dreams if it rains on them, or if they or their guest fallout from a heat stroke?

These are the types of risks I’m speaking of. I hope I have convinced you in the importance of

having a project risk plan in place. In the meantime, I will continue my brainstorming of the risks

associated with this wedding and I would appreciate any insight you may foresee that I can

include in this document. Thank you for your time.

Respectfully Yours,

Jane Doe Project Manager

2. STEPS TO DEVELOPING A RISK MANAGEMENT PLAN (RMP)

.

a. First understand that it is very essential to the success of the project

b. Brainstorm with other stakeholders including bride and groom to partner and help form

this document

c. Define what constitutes as a risk in this business by researching historical data of

weddings gone wrong

d. Use expert judgment for identifying risk

e. Utilizing forecasts to determine unseen conditions

f. Categorizing the Risks for example (wedding dress, chapel, guest, etc.)

g. Rank the risk as to its significance and the likely hood of it happening (Burke, 2011)

h. Mitigating the risks with plans to overcome the expected obstacles (Barkley, 2004)

i. Develop a plan to identify, mointor control,and execute the risk

j. Write the plan

3. FLOW DIAGRAM OF A RISK MANAGEMENT PLAN

(Microsoft, 2007)

Iden%fy   Risk  

Analyze            Plan     Monitor   Control   Execute    

What  to  do   with  each  risk?  

III. PROJECT RISK IDENTIFICATION

1. HIGH LEVEL- POTENTIAL RISKS

a. Budget is Overrun

b. Guests don’t RSVP but arrive at wedding

c. Cake is wrong color and size

d. Food taste awful

e. Flowers shrivel before ceremony

f. Best Man forget his pants

g. Limo driver is held up by traffic

h. Bridal party arrives late

i. Brides zipper to her bridal gown breaks

j. Best Man looses one of the rings

k. Reception location is overbooked

l. 2 people from wedding party can’t be in wedding at last minute

m. Bride/ Groom’s selected songs has been left at home for ceremony on accident

n. Outside weather conditions are bad

o. The groom’s white suit gets a stained

p. DJ get into accident with all the equipment in van

q. Videographer forgets camcorder

r. Wedding Officiate looses the couple’s written vows to each other

2. RISKS CATEGORIZED USING A TABLE MATRIX & SWOT ANALYISIS

Risk   Categorized  

Risk  Categorized  &   Described  

Method/  Techniques  used  to   identify  risks  

Bride’s   Risks    

• Bride  zipper   breaking  on   wedding  day  

• Interview  of  Bride  

Groom’s   Risks    

• Best  Man   loosing  the   rings  

• Interview  of    

Groom  

Ceremony   Risks    

• Music  player   won’t  play  

• Music  left  at   home    

• Minister  loose   vows  

• PM  Team  

Assumptions/Brainstorming    

 Reception   Risks  

 

• Overbooked  

• Room  Set  up   Wrong  

• Flowers  die   because  of   room  temp.  

• Lead  PM  

Assumptions  

Wedding   Party  Risks      

• Back  out  of   wedding  at  last   minute  

• SWOT  Analysis  

Guest     Risks  

• Showing  up   without  prior   RSVP  

• SWOT  Analysis  

Sponsor   Risks  

• Budget   Overruns  

• Interview  of  Sponsor  

(Grewal & Levy, 2008, 2010)

3. STAKEHOLDERS & PROJECT TEAM UTILIZED TO IDENTIFY RISKS

a. Sponsor b. Project Management Team c. Lead Project Manager d. Bride and Groom

Note: The table below explains the role of the stakeholders that I brained stormed with

last week to categorize the risks. I have also added some additional responsibilities that

each key member adhered to. Each one has agreed and is committed to these

responsibilities during the project’s life cycle as the need arises. Everyone is now aware

of the importance of this document and would like to help in any way possible to be sure

it is a success. After all we are a team. Either we are all winners or we all fail. We have

Strengths

Good Budget to work with, Bride and Groom leaving most details to us, only Planning Agency to offer such reward in State

Opportunities

To make a clients dream come true, Can become the Leading Planning Agency by reputation

Weaknesses

Can’t predict the client/ or their families involved ; dependant on resources for a successful outcome

Threats

Risks associated with planning and executing the project/ Bad reputation for the company

agreed that failure is not an option. So we will work as a team to getting this project on its

way by mitigating the risks as often as possible.

ROLE RESPONSIBILITY TO RISK IDENTIFICATION

Project Sponsor ü Provided risk information for budget risks by interview. ü Provided mentoring regarding costs and schedules ü Facilitate monitoring and communications trough project life

cycle ü Act as liaison to ensure effective communication between team,

and vendors regarding project changes

Project Management Team Members

ü Brainstorming with risks that could affect the overall success of the project.

ü Provide input for mitigation strategies ü

Lead Project Manager ü Established the importance of a RMP ü Ensure vender contracts and other deliverables are met ü Meet w/ vendors and clients to go over a comprehensive project

risk assessment to identify unforeseen risk ü Keep open communication and reports to sponsor, clients ü Present project risks to sponsor and communicate client’s

mitigation plans according to their desires ü Ensure risk mitigations are being adhered to and on schedule ü Report progress to all stakeholders ü Obtain schedules requested for all tasks and procure availability

of vendors

Bride & Groom ü Communicate all known risks that could hinder their wedding day

ü Interview explaining their expectations ü Insight on family tendencies

IV. PROJECT RISK ASSESSMENT

1 .1 . TT A B L E A B L E SS H O W I N G H O W I N G RR I S K SI S K S ,, T H E I RT H E I R L I K E L I H O O D A N D L I K E L I H O O D A N D II M P A C T SM P A C T S

Risk Name

Risk Description

Risk Likelihood

Scoring #’s for 2x2 matrix

Below

Risk Impact Ranking

Risk Impact Description

Bride’s

Risks Bride zipper breaking on wedding day

Low (2) High Ceremony would be delayed until problem fixed

Groom’s Risks

Best Man loosing the rings

Low (2) High Ceremony would be delayed

Ceremony

Risks Music player won’t play

Low (2) High Upset bridal party ceremony will probably be delayed

Reception

Risks

overbooked Low (2) High No reception

Wedding

Party Risks

Back out of wedding at last minute

High (1) High Unequal wedding party/no escort for someone

Limo Venue Risks

Traffic /wrong directions

High (1) Low Could delay schedule

Guest Risks

Showing up without prior RSVP

High (1) High Could cause the costs to be impacted

Sponsor Risks

Budget Overruns

High (1) High A Loss for client/company

2 .2 . RR A N K I N GA N K I N G RR I S K SI S K S (( ## ’’ SS D E S C R I P T I O N A B O V ED E S C R I P T I O N A B O V E )) S H O W I N G S H O W I N G LL I K L I H O O D I K L I H O O D A N D A N D II M P A C TM P A C T              

 

****Please refer to the above table/chart for actual risk matrix with detail. *** All of the risks in the above table risk fell in between #’s (1) and (2).

All risks in quadrants (1) should receive the highest priority since these risks are more likely to happen. The others will receive the least attention arranged by number from 2-5 as shown above.

(Burke, 2011)

V. PROJECT RISKS RESPONSES STRATEGY

1. RISK RESPONSE ASSESSMENT MATRIX

Risk Name

Risk Description

Risk Likelihood

Scoring #’s for 2x2 matrix

Below

Risk Impact Ranking

Risk Impact Description

Risk Response

Type

Risk Response Description

Bride’s

Risks Bride zipper breaking on wedding day

Low (2) High Ceremony would be delayed until problem fixed

Avoid Be sure seamstress put a corset backing instead of a zipper to avoid the risk totally

Groom’s Risks

Best Man loosing the rings

Low (2) High Ceremony would be delayed

Mitigate Have the rings pinned inside a bag inside of his pockets instead of them being loose or in a box.

Ceremony

Risks Music player won’t play

Low (2) High Upset bridal party ceremony will probably be delayed

Transfer Have another music player on standby just in case the first one stops working

Reception

Risks

overbooked Low (2) High No reception

Avoid/Transfer Have a backup location/venue

Wedding

Party Risks

Back out of wedding at last minute

High (1) High Unequal wedding party/no escort for someone

Transfer Have the extra person to perform a different task such as usher or escort the guest in if it is

a male or if it is a female she can help with hair and makeup etc.

Limo Venue Risks

Traffic /wrong directions

High (1) Low Could delay schedule

Avoid Allot extra time by planning everything one hour ahead

Guest Risks

Showing up without prior RSVP

High (1) High Could cause the costs to be impacted

Mitigate Have a guest greeter checking RSVP’s at the door to eliminate the budget from being depleted with having to pay for guest that were not accounted for.

Sponsor Risks

Budget Overruns

High (1) High A Loss of revenue for the company

Avoid Request all transactions to be reported daily via email by all project managers to stay abreast. Request all changes are handled through the sponsor first which includes changes in all costs and schedules.

2. DETAILED RISK RESPONSES STRATEGIES

First Risk:

The bride’s zipper breaks before the wedding ceremony. This risk will be mitigated

by getting the bride’s zipper dress altered to a corset by the seamstress. This will

avoid this risk all together. This risk is a low likelihood, but the impact could be

high so we do not want to take on this risk at all. In adding a corset backing, the

costs will be an extra $150.00 which will increase our budget for the dress by that

amount.

Second Risk:

The Best man loosing the rings is the second risk. The likelihood of this risk is low

but the impact would be high. Therefore it is important to mitigate this risk by the

groom having the groom inside a box that will be placed in a jewelry bag that will

be pinned to the inside of the groom’s right pants pocket. This will allow the rings

to stay safe, unless the Best mans looses’ his pants. This will not change the budget

for the bag is part of the ring purchase.

Third Risk:

This risk involves having Sound System problems where the music player won’t

play during ceremony. This risk is high and the impact would be high for it could

delay the wedding’s schedule. This could also cause the budget to change because

it will mean more time in the chapel as well as more money to be spent on new

equipment. This risk will be avoided by purchasing a back up sound system if

needed. This will cause the costs to increase by $1000.000. The vendor will need

to deliver the first sound system on time and on schedule to be tested. It will also

be tested one week and one day prior to the ceremony. If the vendor cannot fulfill

the requirements of the delivery contract, they will assume all costs as agreed to.

Fourth Risk:

The fourth risk of the reception location being overbooked is less likely to happen,

but will have a high impact on the project. Therefore, having a backup location we

will mitigate this risk. This information will need to be verified well in advanced

for proper planning. A contract will need to be signed. In the event the location has

been overbooked we will request that the original vendor returns all money for

deposits. This could cause our cost and schedule to change if a new vendor is

needed. For example if the new location costs more than the current one it would

cause the budget to increase. Also if the new location date requested is unavailable

it would cause the schedule to change.

Fifth Risk:

The fifth risk is that several of the wedding party back out of wedding two weeks

before the wedding. This risk is high and the impact is high for this could cause the

wedding party to be unequal. There could possibly be for example not enough men

for the women to be escorted or vice versa. This could also alter the entrance and

standing arrangements. In this case, the risk will be transferred by having the extra

wedding party fulfill other tasks such as an extra male could act as an usher or

escort of guests to their seats. The extra females can be used to help with make-up

hair and dressing. A back up rehearsal should also be performed. The wedding

party can rehearse walking in alone and also walking in with escorts. This will

transfer this risk for everyone will be prepared either way.

Sixth Risk:

Limo driver has traffic issues and does not get the wedding party to the chapel on

time. This risk is high and likely to happen. The impact will also be high because it

will cause the schedule and possibly cost to change. Most wedding chapels allow

you to rent it by the hour. If the limo drive is an hour late, this could cause a charge

to occur that was not planned for. Therefore, we would like to avoid this risk by

planning the Limo driver to arrive an hour ahead of schedule. We will also be sure

that the limo driver has made a test run to be sure he will know where he is going

on the day of the ceremony. If for any reason he does take the bridal party to

another location in the contract it will be stated that he will be responsible for any

extra fees that his company will charge for they also charge by the hour.

Seventh Risk:

Guest showing up at the wedding that has not RSVP. The likely hood of this

happening is high for people show up all the times to places they have not

reserved. In this case this could cause the budget, planning, and everything to

increase. We will mitigate this risk by having a greeter that will check names and

RSVP information at the door. If that person is not on the list they will not be

allowed to attend.

Eighth Risk:

The last risk of budget overruns for this project has a high likelihood and a high

impact. This could cause the entire project to be canceled. This risk will be

mitigated by keeping an open line of communication by requesting that all

transactions to be reported daily between all project managers to stay abreast. It is

also required that all changes are presented and approved by the sponsor first. This

does include changes in all costs and schedules.

VI. PROJECT RISKS MANAGEMENT PLAN

1. Monitoring Risk Responsibility Matrix

R=Responsible, A=Approver, S= Support, I=Information N/A=not applicable

Responsible = person who take full responsibility of monitoring and controlling the risk of the task.

Approver = person who approves or allow changes to occur to budget, schedule, changes etc.(takes action) Support= person who provides their response to the risk or support regarding any aspects of the project.

Information= person who should be notified but does not possess any control for decisions n/a= monitoring risk plan does not apply in that particular task

Name

Wedding

Project

Schedule Risks

Overall

Project Cost/

Budget

Risks

Decorations

Type, Set up

And take down risks

Staff

Work

Hours

Wedding

Vendor non- Performance

Risks

Wedding

Party Attire

Activities

Associated

To Mitigating

Wedding Risks

Wedding changes/ status

updates

Wedding Guest RSVP Risk

Project sponsor

A A A A A A A A A

Lead Project Manager/ Coordinator

R R R R R R R R R

Project Management Staff

I I S I R S I I I

Vendors I I R I R I I S I

Design Team

I S R I I R S S I

Bride/Groom I I A I A I A S

Bridal Party S R n/a n/a n/a A I S S

Wedding Guest

I n/a n/a n/a n/a n/a I I S

PROJECT MONITORING & CONTROL PLAN

Risk monitoring and control is the process of identifying, analyzing, and

planning for newly discovered risks and managing identified risks. Throughout this

process, the responsible person of the risk identifies the risks, identifies new risks,

implements risk response plans, and measures the risk response plans

effectiveness. The actual inputs to Risk Monitoring and Control are: Risk

Management Plan, Risk Register, Approved Change Requests, Work Performance

Information and Performance Reports which most will be discussed in more detail.

The wedding giveaway sweep steak project must be obtained in a solid risk

monitoring and control plan in order to reassure the project goes according to plan.

The risk monitoring and control must be carried out during the entire life cycle of

the project. What this means is that this process will include but not be limited to

analyzing and identifying risk as they derive and documenting them to form

contingency plans for if and when they do arise. This helps the project stay on task

and helps monitor if our company’s resources that are being utilized for the project

are operating correctly (FFIEC, 2008).

Effective Risk monitoring and control will be essential to the schedule, cost and

overall budget. There are techniques involved in the risk monitoring process to

ensure the execution of the project (PMI, 2008). Each and every one of the

stakeholders involved in this development of the wedding project will either lose

or gain from the success or failure of it. A successful outcome is desired so that is

where project risk and monitoring will come into play because it ensures but does

not guarantee the project’s success. Put it this way, it will make the chances much

greater of being successful than if this process was not implemented at all.

The project management team, sponsor and other key stakeholders must always

be ready to not just identify the risk, but take a proactive approach to mitigating the

risk that are associated with it. In other words, they must always be prepared to

take a stance to eliminate the associated problem at hand. The techniques that are

used to manage the risks must be embodied within our project risk paradigm. The

basic techniques used to manage the risks are the following: identify, analyze, plan,

track, control, and communicate, (PMI, 2008).

We will use spreadsheets, performance reviews, variance analysis (VA) and

Microsoft project manager as the software tool to schedule and track the tasks to

help identify and document the risks. We will also use communication methods

such as by phone, fax, face to face or email to name a few ways to keep one

another abreast on any changes. If changes are needed such as in schedules or

costs, that final decision must be made by the Sponsor and our Executive Team.

The Project managers, vendor or anyone for that matter has the option to request a

change, but the request must be made known to the lead project manager which

will communicate it to the sponsor team right away for the decision making

process.

Monitoring and Controlling of this project will also deal with tracking and

periodically reviewing the information from the spreadsheets or risk analysis (RA).

This will enable us to regulate the process to meeting the performance that is

defined within the project scope and project management plan (PMI, 2008). Some

of the things that we will use to monitor and controlling the deliverables for this

wedding project are (1) collect information from all parties involved such as

reports showing work in progress and or completed. (2) Measure how this

information compares to the actual schedule and costs.

When a risk occurs, the control process is to first of all assess the risk, modify it

by determining if we can accept, avoid, or mitigate the risk. (3) The lead project

manager is in control of disturbing the performance information to the sponsor and

others that are of interest. (4) Last, perform measurements to effectively make

process improvements will be assessed. This information will be repeated the

entire time until the project is over and the couples have returned happily from

their honey moon.

This long duration of monitoring and controlling will ensure that corrective

actions will be taken in the event a risk does arise which is a part of the control

process. As a breakdown of the planned project monitor and control work that will

take place for this project the task are as following:

1. Continue to compare the actual performance of vendors, team members, etc.

to the project plan

2. Determine if there are actions needed to correct or prevent risks and

recommend them.

3. Identify new risks by analyzing, tracking and monitoring the wedding

project at hand. Also current and or past risk as well to be sure they are

identified, reported, and response mechanisms has been put into place

4. Keep an up to date status of the progression or digression of the project’s

progress throughout the project life cycle.

5. Inform the team and sponsor of support status reports, forecasting, and

progress measurements

6. Keep a detailed log of forecasts, current costs and current schedule

information to stay current and keep stakeholders current

7. Implement monitoring of approved changes from the sponsor as they occur

to the team members and vendors (PMI, 2008).

8. Quality assurance, Quality control Inputs and Risk Analysis performed ( i.e.

flowcharting to determine if improvements are needed) (PMI, 2008).

9. Documentation of lessons learned regarding the project will be indicated as

well

10. Close the project.

2. DIAGRAM FLOW CHART

(Microsoft Word Smart Art, 2011)

Risk   Iden%fied  

Risk   Register  

Access  Risk   Respond  to  the  Risk  

Work     Perform ance  

 Requested   Changes  

Con%gency   Plan  

Introduced  

Previous   and  New   Risk    

iden%fied,    

VIII. PROJECT RISKS MILESTONES & BUDGET UPDATE

1. MILESTONES & UPDATES

a. Flowers

b. Cake and Catering

c. Music Getting Marriage License

d. Name Change on all cards (i.e. social security, credit, health etc.)

e. Preparing A Budget

f. Guest List

g. Invitations

h. Vendors

i. The Bride

j. The Groom

k. Wedding Party

l. Hair & Beauty

m. Ceremony

n. Reception

o. Honey moon

p. Photo & Video

q. Rehearsal Dinner

r. The Wedding day

s. Thank you gifts/ cards

t. Weekly meeting

u. Monthly meeting

v. Consult bride and groom w/ updates

w. Contact vendors monthly

x. Pay vendor in full one month prior to event

y. Contact catering company 1 month prior with exact numbers of guests

z. Contact wedding reception venue 1 month prior with exact number of guests

aa. Fitting for brides dress 3 months prior to event

bb. Wedding Party attire dress rehearsal 1 month and 1 week prior to event

cc. Rehearsal Dinner 1 week prior to event

dd. Limo driver test drive locations- obtain status report

ee. Flowers, Decorations, etc. Needs to be delivered two days prior

ff. Refrigerate flowers

gg. Check on cake venue be sure it is on schedule for delivery the day of event

hh. Accessories for flower girls and brides maids needs to be picked up 3 months

prior

ii. Last fitting of entire wedding party 2 weeks prior to event

jj. Chairs, tables, and all equipment delivered on week prior to event

kk. Set up team arrive 7 am to chapel (1 day prior to wedding day)

ll. Take down at 7pm at wedding chapel (1day post wedding day)

mm. Photography and Videographer arrive (1 day prior for shots of décor)

nn. Contact Reception Hall tour (1 day prior to be sure set up is correct)

oo. Test all equipment to ensure functionality 1 month, 1 week, 1 day prior

pp. Take a break and relax by 6pm. (1 day prior to event)

2. CONTINGENCY BUDGET -UPDATES

As of June 20th, 2011 our budget of $50,000 has not overrun. As a matter of fact we are

predicted to come in under budget by 20% or 5,000 dollars due making the Estimated Cost (EC)

to be $45,000. This is due to the recent changes in the reception location. The cost for the new

location is the same and the only difference is they will do all the decorations as per the

bride/grooms preference. This is part of their complimentary packages and services. Another

thing is they are accommodating the bride and groom a free honey moon suit the night of the

event. The guests are also allowed to stay with a group rate charge of 100.00 per night which is a

50% savings off the regular price. (Each guest will be responsible for his/her own fees). With

these amazing changes, this has allowed the event to be on schedule and under budget.

This brings me to mention about the couple’s one week cruise honey moon package to the

Bahamas. It is still on schedule to take place the day after the wedding. They will have a honey

moon suite w/ balcony view. We have also added a surprise bonus to this package ( thanks to

contributions made by our loyal customer’s) of a $5,000 spending voucher as well as limo

service transportation to and from the loading dock in Port Canaveral Fl.

We are sure to make this couple’s wedding day a dream come true and a day to remember for

the rest of their lives! We are also expected to receive a 30 % percent growth in client base and

revenue after this project is completed for it has received nationwide attention by the media. This

story is due to air on a “Wedding Story” on TLC the following month with permission from our

bride and groom of course! We are all excited about this project and have taking all the

necessary approaches to identify and mitigate the budget and planning risks according to this

plan.

IX. PROJECT RISKS COMMUNICATIONS PLAN

1. PROJECT TEAM DIRECTORY

This table is a representation of the contact information for the persons that are identified in this communications

management plan. The phone numbers/ email address will be one of the methods used to communicate with each of

them as needed. Role Name Email Phone

Project Sponsor Lead Project Manager Jane Doe

Project Staff Switchboard/Directory

Project Management Team line

[email protected] 555-555-1212

Customer (Bride/Groom) Francesca Griffin and Randy Watson

[email protected] 555-777-2345

Vendor Switchboard Vendors Exclusive Switchboard

[email protected] 555-222-7890

Design Team Switchboard Design Team [email protected] 555-888-4567

2. Matrix for the Communications Plan

This table identifies the form of communications that is requirements for this event. Communication

Type Communication

Objective

Type Frequency Audiences Owner Deliverable

Kickoff Meeting The Wedding Project

introduced as well as team

members. Management Approach- Objectives explained

• Face to Face 1x • Project Leader • Project Team • Bride Groom • Stakeholders

Project Sponsor

• Meetings • Agenda

Project Team Meetings

Project Status • Email • Conference

Call • Face to Face

Weekly • Project Team • Project Sponsor

Project Manager

Staff

• Meetings • Agenda

Design Team Meetings

Develop and Discuss design plans/solutions for the project.

• Face to Face As Needed • Project Design Team/ Lead PM

Lead Project

Manager

• Agenda • Meeting

Status Meetings for the Project

Reports of the status of the

project to team

• Face to Face • Conference

Call • Email

• Smartphone

Monthly • Entire Project Team

Project Manager

• Agenda

Status Reports

Of the Project

Report the status of the project risk, activities costs problems

etc.

• Email • Conference call • News letter

Monthly • Project Sponsor • Project Team • Stakeholders

Project Lead

Manager

• Status Report

3. Guidelines for the Meetings

Meeting Agenda

The Meeting Agenda will be sent out a week before each meeting. It will explain the topic and allow room for notes for

questions or comments that should be presented in the meeting. The Agenda will also express the presenter and

their contact information. The agenda will be reviewed each week to be sure it follows the previous meeting’s updates

and changes as needed to ensure all items are addressed and responded to. Occasionally the agenda will express

the actions by review if such case is permissible.

Owner of Meeting/ Presenter

The Owner of the meeting/ presenter will be identified as the “Chair Person” for that week and is responsible for

distributing the agenda of the meeting to all persons of interest. The times of both starting and ending will also

be their responsibility. It is asked that the meetings does not run 30 minutes over or they should be rescheduled

and reviewed during the next weeks meeting or conference. This will vary especially when meeting with the

customers (bride and groom) for they may have questions or concerns that may go over the allotted time. In the

case of emergencies will be the only time this restriction can be lifted but must be approved by the sponsor

because this will put the employees in an overtime status. This could cause the budget to overrun. Or team

members are welcome to talk and meet at any time off of the company’s paid hours.

Note Taker

It is important that the chair person picks someone to take notes of the meetings to ensure an accurate recording

of updates and status reports to other stakeholders that may not be present and also as a good review

mechanism. At the end of the meeting the note taker is responsible to hand over the notes to the chair person

which will get the notes copied and prepared as needed for following meetings etc.

.

REFERENCES Barkley, B. T. (2004). Project Risk Management. New York: The McGraw- Hill Companies, Inc.

Boyet, (2010). A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition Translations Retrieved from

http://www.pmi.org/en/About-Us/Press-Releases/A-Guide-to-the-Project-Management- Body- of-Knowledge.aspx

Burke, R. (2011). MPM344 Live Chat. Colorodo Tech University Online.

Haughty, (2009). The Project Management Book of Knowledge. Retrieved from website http://www.projectsmart.co.uk/pmbok.html

(PMBOK® Guide); Project Management Institute, Inc. (PMI); 2000, Newtown Square, PA : Project Management Institute

Project Management Body of Knowledge (PMBOK Guide). (2008). Newton Square 4th edition: Project Management Institue, Inc.