Greendale Stadium Case
The G&E Company is preparing a bid to build the new 47,000 seat Greendale baseball stadium. The
construction must start July 1, 2011, and be completed in time for the start of the 2014 season. A
penalty clause of $100,000 per day of delay beyond May 20, 2014, is written into the contract.
Ben Keith, the president of the company, expressed optimism at obtaining the contract and revealed
that the company could net as much as $2 million on the project. He also said if they are successful, the
prospects for future projects are quite good since there is a projected renaissance in building classic ball
parks with modern luxury boxes.
ASSIGNMENT
Given the information provided in Table 6.3, construct a network schedule for the stadium project and
answer the following questions:
1. Will the project be able to be completed by the May 20 deadline? How long will it take?
2. What is the critical path for the project?
3. Based on the schedule would you recommend that G&E pursue this contract? Why? Include a
one-page Gantt chart for the stadium schedule.
TABLE 6.3
ID Activity Duration Predecessor(s)
1 Baseball Stadium
2 Clear stadium site 70 days --
3 Demolish building 30 days 2
4 Set up construction site 70 days 3
5 Drive support piling 120 days 2
6 Pour lower concrete bowl 120 days 2
7 Pour main concourse 120 days 3, 6
8 Install playing field 90 days 3, 6
9 Construct upper steel bowl 120 days 3, 6
10 Install seats 140 days 7, 9
11 Build luxury boxes 90 days 7, 9
12 Install jumbotron 30 days 7, 9
13 Stadium infrastructure 120 days 7, 9
14 Construct steel canopy 75 days 10
15 Light installation 30 days 14
16 Build roof supports 90 days 6
17 Construct roof 180 days 16
18 Install roof tracks 90 days 16
19 Install roof 90 days 17, 18
20 Inspection 20 days 8, 11, 13, 15, 19
CASE APPENDIX: TECHNICAL DETAILS OF THE GREENDALE BASEBALL STADIUM
The baseball stadium is an outdoor structure with a retractable roof. The project begins with clearing
the site, an activity that lasts 70 days. Once the site is clear, work can start simultaneously on the
structure itself and demolishing an adjacent building site. This demolition is necessary to create a
construction stage for storing materials and equipment. It will take 30 days to demolish the buildings
and another 70 days to set up the construction site.
The work on the stadium begins by driving 160 support pilings, which will take 120 days. Next comes the
pouring of the concrete bowl (120 days). Once this is done and the construction site has been set up,
then the pouring of the main concourse (120 days), the installation of the playing field (90 days), and the
construction of the upper steel bowl can occur (120 days).
Once the concourse and upper bowl are completed, work can start simultaneously on building the
luxury boxes (90 days), installing the seats (140 days), installing the jumbotron (30 days), and installing
the stadium infrastructure (120 days) which includes: bathrooms, lockers, restaurants, etc. Once the
seats are installed then the steel canopy can be constructed (75 days) followed by the installation of the
lights (30 days).
The retractable roof represents the most significant technically challenge to the project. Building the
roof track supports (90 days) can begin after the lower concrete bowl is constructed. At this time the
dimensions of the roof can be finalized and the construction of the roof at a separate site can begin (180
days). After the roof supports are completed ten the roof tracks can be installed (90 days). Once the
tracks and the roof are completed then the roof can be installed and made operational (90 days). Once
all activities are completed it will take 20 days to inspect the stadium.
For purposes of this case assume the following:
1. The following holidays are observed: January 1, Memorial Day (last Monday in May), July 4 th
,
Labor Day (first Monday in September), Thanksgiving Day (4 th
Thursday in November),
December 25 and 26.
2. If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a
Sunday them Monday will be given a day off.
3. The construction crew work Monday through Friday