APPENDIX B: SAMPLE RISK ASSESSMENT REPORT OUTLINE

EXECUTIVE SUMMARY

I. Introduction

• Purpose • Scope of this risk assessment

Describe the system components, elements, users, field site locations (if any), and any other details about the system to be considered in the assessment.

II. Risk Assessment Approach

Briefly describe the approach used to conduct the risk assessment, such as—

• The participants (e.g., risk assessment team members) • The technique used to gather information (e.g., the use of tools, questionnaires) • The development and description of risk scale (e.g., a 3 x 3, 4 x 4 , or 5 x 5 risk-level

matrix).

III. System Characterization

Characterize the system, including hardware (server, router, switch), software (e.g., application, operating system, protocol), system interfaces (e.g., communication link), data, and users. Provide connectivity diagram or system input and output flowchart to delineate the scope of this risk assessment effort.

IV. Threat Statement

Compile and list the potential threat-sources and associated threat actions applicable to the system assessed.

V. Risk Assessment Results

List the observations (vulnerability/threat pairs). Each observation must include—

• Observation number and brief description of observation (e.g., Observation 1: User system passwords can be guessed or cracked)

• A discussion of the threat-source and vulnerability pair • Identification of existing mitigating security controls • Likelihood discussion and evaluation (e.g., High, Medium, or Low likelihood) • Impact analysis discussion and evaluation (e.g., High, Medium, or Low impact) • Risk rating based on the risk-level matrix (e.g., High, Medium, or Low risk level) • Recommended controls or alternative options for reducing the risk.

VI. Summary

Total the number of observations. Summarize the observations, the associated risk levels, the

SP 800-30 Page B-1

recommendations, and any comments in a table format to facilitate the implementation of recommended controls during the risk mitigation process.

SP 800-30 Page B-2

(1) Risk

(Vulnerability/ Threat Pair)

(2) Risk Level

(3) Recommended

Controls

(4) Action

Priority

(5) Selected Planned Controls

(6) Required Resources

(7) Responsible

Team/Persons

(8) Start Date/ End Date

• Disallow inbound telnet

• Disallow “world” access to sensitive company files

• Disabled the guest ID

APPENDIX C: SAMPLE SAFEGUARD IMPLEMENTATION PLAN SUMMARY TABLE

(9) Maintenance Requirement/

Comments Unauthorized users can telnet to XYZ server and browse sensitive company files with the guest ID.

High

• Disallow inbound telnet

• Disallow “world” access to sensitive company files

• Disable the guest ID or assign difficult-to-guess password to the guest ID

High

10 hours to reconfigure and test the system

John Doe, XYZ server system administrator; Jim Smith, company firewall administrator

9-1-2001 to 9-2-2001

• Perform periodic system security review and testing to ensure adequate security is provided for the XYZ server

(1) The risks (vulnerability/threat pairs) are output from the risk assessment process (2) The associated risk level of each identified risk (vulnerability/threat pair) is the output from the risk assessment process (3) Recommended controls are output from the risk assessment process (4) Action priority is determined based on the risk levels and available resources (e.g., funds, people, technology) (5) Planned controls selected from the recommended controls for implementation (6) Resources required for implementing the selected planned controls (7) List of team(s) and persons who will be responsible for implementing the new or enhanced controls (8) Start date and projected end date for implementing the new or enhanced controls (9) Maintenance requirement for the new or enhanced controls after implementation.

SP 800-30 Page C-1