Project Charter
)
V 2.0
Project Charter
|
Project Name |
Timesheet Data Systems |
Project Number |
001 |
|
Project Team |
Development Team |
Prioritization |
1 |
|
Owner(s) |
Kenneth Smith
|
Start Date: |
Jan 15, 2017 |
|
Scheduled Completion Date: |
Dec 31, 2017 |
Mission/ Purpose |
This projects goal is to automate the company’s timesheet system in order to increase the company’s productivity and to ensure the accuracy of the employees’ salary computations and performance evaluation tasks. This in turn will contribute to the accomplishment of the company’s objectives of increased revenues and increased employee retention. This project is part of the company’s initiative to eventually automate all of the administrative tasks within the company. |
|||||
|
|
||||||
|
Project Description and Project Product |
This project will create a web-based timesheet application that will monitor the employees’ login and logout times, as well as their daily tasks. This will be accomplished by using HTML and SQL as the programming language and database. The employees will be able to access the application within the company’s intranet.
The project will include the following high-level deliverables:
· Business and Design Requirements · Program coding · User’s Guide and Online help
|
|||||
|
|
||||||
Objectives |
Objective: Develop a web-based timesheet system.
Goals
· Have login module completed by March 15, 2017 · Complete the timesheet module by May 5, 2017 · Have payroll module completed by August 5, 2017 · Introduce the timesheet system to the company by Dec 23, 2017
|
|||||
|
|
||||||
|
Business Need |
To create a web-based timesheet system that keeps track of the employees’ work hours and tasks. This would allow the employees to spend more time on their other tasks while increasing the company’s productivity. Also, the web-based timesheet system will be used as basis for the employees’ performance evaluations, therefore, increasing job satisfaction and increasing employee retention. |
|||||
|
|
||||||
|
Milestones |
1. Information requirements gathered 01/15/2017 2. Business Requirements Documents reviewed and signed off – 02/20/2017 3. Design Requirements Documents (DRD) created – 03/01/2017 4. DRDs reviewed and signed off – 03/10/2017 5. Testing completed for Login module – 07/15/2017 6. Testing completed for Timesheet module – 08/01/2017 7. Testing completed for Payroll module – 08/15/2017 8. Bug fixes completed – 10/01/2017 9. Training of employees – 11/01/2017 10. Roll out of system in the entire company – 12/15/2017
|
|||||
|
Budget |
|
|||||
|
|
Estimated Labor |
$25,000 |
||||
|
|
Estimated Materials |
$10,000 |
||||
|
|
Estimated Contractors |
$35,000 |
||||
|
|
Estimated Equipment and Facilities |
$20,000 |
||||
|
|
Estimated Travel |
$10,000 |
||||
|
|
Total Estimated Cost |
$100,000 |
||||
|
|
||||||
|
User Acceptance Criteria |
· The system test must prove to be 90% error free. · The system must produce 100% accuracy when it relates to salary related functions.
|
|||||
|
|
||||||
|
Major Risks |
1. Natural disasters that can prevent the project’s timely completion. 2. Power interruptions, which can lead to project delays. 3. Unavailability of the project team members, which can cause project delays. 4. Resignation of some project team members, which would require getting and orienting new members. This can lead to project delays. 5. Additional requirements from the client, which can lead to project delays. 6. Employees’ and managers’ lack of cooperation in providing the needed information. 7. Lack of cooperation in participating in the application’s testing. |
|||||
|
|
||||||
|
KEY STAKEHOLDERS
|
||||||
|
Project Manager Authority Level |
|
|||||
|
Project Core Team |
|
|||||
|
Subject Matter Experts (SMEs) |
CEO/Project Managers Department Managers IT Techs
|
|||||
|
APPROVALS |
||||||
Type Name |
Signature |
Date |
||||
|
Project Manager Approval
|
|
|
||||
|
Customer/Sponsor Approval
|
|
|