Project management assignment. need both parts completed.

profileiamnickok
project_part_2_start.xlsx

Final Exam Part 2 start

Data Table
Work Package Predecessor Duration (weeks) Early Start Early Finish Late Start Late Finish Slack On Critical Path (Y/N)? ES Legend EF
A -- 2 Slack
B A 2 LS Duration LF
C A 3
D A 4
E B 2 A
F C 3
G D 6
H E,F 2
I E,F 5
J G,I 1
K H,J 2
1 What is the critical path?
2 What is the projected length of this project (in weeks)?
3 What is the impact on the project (and the project manager) of changing the duration of task H from 2 weeks to 6 weeks?

&22&A