Project management assignment. need both parts completed.
Final Exam Part 2 start
| Data Table | ||||||||||||
| Work Package | Predecessor | Duration (weeks) | Early Start | Early Finish | Late Start | Late Finish | Slack | On Critical Path (Y/N)? | ES | Legend | EF | |
| A | -- | 2 | Slack | |||||||||
| B | A | 2 | LS | Duration | LF | |||||||
| C | A | 3 | ||||||||||
| D | A | 4 | ||||||||||
| E | B | 2 | A | |||||||||
| F | C | 3 | ||||||||||
| G | D | 6 | ||||||||||
| H | E,F | 2 | ||||||||||
| I | E,F | 5 | ||||||||||
| J | G,I | 1 | ||||||||||
| K | H,J | 2 | ||||||||||
| 1 | What is the critical path? | |||||||||||
| 2 | What is the projected length of this project (in weeks)? | |||||||||||
| 3 | What is the impact on the project (and the project manager) of changing the duration of task H from 2 weeks to 6 weeks? | |||||||||||