final report and brochure
i
An Abstract of
North Gateway Project
by
Team A-3
Dylan Orwig, Team Leader
Bryan Phlipot, Team Member
Aaron Tendam, Team Member
Stephen Stout, Team Member
for
ENGT 4050
Senior Technology Capstone
Fall Semester 2013
The University of Toledo
Problem: The recent demolition of the White, Dowd, and Nash residence halls has
created an opportunity for construction in a prime location at the most northwestern
corner of campus.
Solution: Project Team A-3 has proposed retail and restaurant shops be built on the
existing site to help give the campus and surrounding communities a social and
community gathering spot.
Method: Team A-3 started using brainstorming methods to decide what ideas would best
be implemented in the new open space. The best ideas were chosen and AutoCAD,
Autodesk Revit, 3D models, Microsoft Project, and Ecotect were used to develop the
ideas into a clear concise visual representation.
Results: The produced design plans of building foundations, floor plans of the restaurants
and retail shops, and final renderings of the buildings show the final product.
Conclusion: The proposed buildings will repurpose an unoccupied area with innovative
design, student and community accommodations, and an “up-tempo” atmosphere. This
new space will bring the campus and surrounding communities together at one
centralized social hub.
ii
Acknowledgements
Capstone group A-3 would like to acknowledge the people that made this project possible
including:
Professor Linda Beall- Capstone Faculty Advisor
Professor Richard Springman- Capstone Instructor
Dr. Nicholas Kissoff- Program Director
Janotta and Herner Inc.- Help with estimation and scheduling
Mr. Alan Kossow- Help with 3D modeling
iii
Table of Contents
Preface
Abstract i
Acknowledgements ii
Table of Contents iii
List of Figures iv
List of Abbreviations vii
Body
Introduction 1
Project Objectives 2
Project Team 3
Design and Analysis 4
Results 5
Discussion and Conclusions 6
References 7
Budget 7
Appendices A
Team Resumes 8
Appendices B
Gantt Chart with Project Schedule 12
Appendices C
Project Estimate 14
iv
List of Figures
Fig. 1 – Building Footprint: Shops labeled 1-6. Restaurants labeled 1-2.
1 2 3 4 5 6
1
2
v
Fig. 2 – 3-D Building Model
Fig. 3 – Interior View of Restaurant
vi
Fig. 4 - Walkway Inbetween Shop Buildings. Same View On Both Sides
Fig. 5 – South View Shop Elevation Buildings
Fig. 6 – North Elevation View Shop Buildings
Fig. 7 – East Elevation Shop Building
Fig. 8 - South Elevation Restaurant Building
Fig. 9 – West Elevation Restaurant Building
Fig. 10 – East Elevation Restaurant Building
vii
Fig. 11-Site Location
List of Abbreviations
UT – University of Toledo
CAD – Computer Aided Design
SF – Square Feet