An Abstract of

North Gateway Project

by

Team A-3

Dylan Orwig, Team Leader

Bryan Phlipot, Team Member

Aaron Tendam, Team Member

Stephen Stout, Team Member

for

ENGT 4050

Senior Technology Capstone

Fall Semester 2013

The University of Toledo

Problem: The recent demolition of the White, Dowd, and Nash residence halls has

created an opportunity for construction in a prime location at the most northwestern

corner of campus.

Solution: Project Team A-3 has proposed retail and restaurant shops be built on the

existing site to help give the campus and surrounding communities a social and

community gathering spot.

Method: Team A-3 started using brainstorming methods to decide what ideas would best

be implemented in the new open space. The best ideas were chosen and AutoCAD,

Autodesk Revit, 3D models, Microsoft Project, and Ecotect were used to develop the

ideas into a clear concise visual representation.

Results: The produced design plans of building foundations, floor plans of the restaurants

and retail shops, and final renderings of the buildings show the final product.

Conclusion: The proposed buildings will repurpose an unoccupied area with innovative

design, student and community accommodations, and an “up-tempo” atmosphere. This

new space will bring the campus and surrounding communities together at one

centralized social hub.

ii

Acknowledgements

Capstone group A-3 would like to acknowledge the people that made this project possible

including:

Professor Linda Beall- Capstone Faculty Advisor

Professor Richard Springman- Capstone Instructor

Dr. Nicholas Kissoff- Program Director

Janotta and Herner Inc.- Help with estimation and scheduling

Mr. Alan Kossow- Help with 3D modeling

iii

Table of Contents

Preface

Abstract i

Acknowledgements ii

Table of Contents iii

List of Figures iv

List of Abbreviations vii

Body

Introduction 1

Project Objectives 2

Project Team 3

Design and Analysis 4

Results 5

Discussion and Conclusions 6

References 7

Budget 7

Appendices A

Team Resumes 8

Appendices B

Gantt Chart with Project Schedule 12

Appendices C

Project Estimate 14

iv

List of Figures

Fig. 1 – Building Footprint: Shops labeled 1-6. Restaurants labeled 1-2.

1 2 3 4 5 6

1

2

v

Fig. 2 – 3-D Building Model

Fig. 3 – Interior View of Restaurant

vi

Fig. 4 - Walkway Inbetween Shop Buildings. Same View On Both Sides

Fig. 5 – South View Shop Elevation Buildings

Fig. 6 – North Elevation View Shop Buildings

Fig. 7 – East Elevation Shop Building

Fig. 8 - South Elevation Restaurant Building

Fig. 9 – West Elevation Restaurant Building

Fig. 10 – East Elevation Restaurant Building

vii

Fig. 11-Site Location

List of Abbreviations

UT – University of Toledo

CAD – Computer Aided Design

SF – Square Feet