ASSIGNMENT

profileamoha1234
calculating_earned_value.doc

Calculating Earned Value

Yes, you too can simultaneously monitor and control both schedule and cost using the formulas we have included in this document.

First, you have to understand the terms and get familiar with their acronyms.

Definition of Terms

How It Works/What It Determines/How You Use It

Earned value (EV)

Budgeted cost of work performed

Budgeted cost of work scheduled (BCWS)

Use BCWS to represent the value of work to be budgeted.

Actual cost of work performed (ACWP)

Use ACWP to represent the total cost spent to complete the task.

Budgeted cost of work performed (BCWP)

This is also known as earned value.

Cost variance (CV)

This is the difference between the planned and actual costs for the completed tasks. It can either be a positive or negative value.

Cost variance percentage (CV%)

Always express this as a percentage. A positive value indicates that the project is under budget. A negative value means that the project is over budget.

Schedule variance (SV)

This is the difference between the planned and actual costs for the completed tasks. It can either be a positive or negative value.

Schedule variance percentage (SV%)

Always express this as a percentage. A positive value indicates that the project is on schedule. A negative value means that the project is off schedule.

Estimate at completion (EAC)

Use this to recalculate a project budget to obtain a more accurate value of what the project will cost at the end.

Formulas for Calculating Earned Value

Determining Schedule Variances

(+)Variance = Ahead of Schedule

(-)Variance = Behind Schedule

SV = BCWP less BCWS

SV% = SV divided by BCWP

SPI = BCWP divided by BCWS

% Complete = 100 x SPI

Determining Cost Variances

(+)Variance = Below Budget

(-)Variance = Over Budget

CV = BCWP less ACWP

CV% = CV divided by BCWP

CPI = BCWP divided by ACWP

EAC = BAC times (ACWP divided by BCWP)